PARTIES TO DISPUTE:



THE NEW YORK CENTRAL RAILROAD COMPANY

(Line West of Buffalo)


STATEMENT OF CLAIM: Claims of the General Committee of The Order of Railroad Telegraphers on the New York Central Railroad (Line West of Buffalo) that:












6971-2 1071

    3. Carrier shall in addition thereto compensate E. G. Atkins in the sum of 98 cents for deadhead time from Charleston, West Virginia, to Nitro and return, a distance of 16 miles, at the rate of .030480 per minute for 32 minutes.


                CASE NO. 3


    1. Carrier violated the Agreement between the parties hereto, when on the 31st day of December 1952, it failed to use extra employe R. N. Burdette to perform services on third shift "BK" Office ins'ead of operator R. J. Williams.


      2. Carrier shall compensate R. N. Burdette at the straight time

    rate for eight hours on December 31, 1952, at the rate applicable to third shift "BK" Office. ($14.76.)


    3. Carrier shall in addition thereto compensate R. N. Burdette in the sum of $9.96 for deadhead time from Leon, West Virginia, to "BK" and return, a distance of 162 miles, at the ra'e of .0375¢ per minute for 324 minutes.


    EMPLOYES' STATEMENT OF FACTS:


                CASE NO. 1


K. J. McKinley and R. E. Cavin were at all times hereinafter mentioned, extra employes covered by the Telegraphers' Agreement.


Cavin was, on September 3, 1952, assigned by Carrier to second shift Kile, for the purpose of relieving Mrs. F. M. Runyon for her vacation. He filled this assignment from September 3 to 14 inclusive. The rest days of this assignment are Mondays and Tuesdays. The assignment at Kile included the following days and dates:


    Wednesday September 3, 1952 (Second Shift)

    Thursday 4,1952 "

    Friday 5, 1952 "

    Saturday 6, 1952 "

    Sunday 7, 1952 "


    Monday Rest Day (8th)

    Tuesday Rest Day (9th)

    Wednesday September 10, 1952 " "

    Thursday 11, 1952 "

    Friday 12, 1952 "

    Saturday 13, 1952 "

    Sunday 14, 1952 "


    Monday Rest Day (15th) (actually worked West

    Columbus third shift)

    Tuesday Rest Day (16th) (actually worked West

    Columbus third shift)


McKinley was idle on September 12, 13, 14, 15, 16, 1952. His last work was on September 7, 8, 9, 10 and 11. He was available for service and was not used to fill the third shift at West Columbus on September 15 (Monday) and September 16 (Tuesday), although entitled to the work.


                CASE NO. 2


R. J. Williams and E. G. Atkins are extra employes. On January 6, 1953, Williams was assigned to work, and did work at Fultonham, Ohio, as follows:

6971-26 1095

      3. Rules cited by the Organization not only do not support the claims but, when associated with other rules and, particularly, with the eptember 27 1950 Memorandum of Understanding effective November 1, 1950, actually refute the claims;


      4. Board Awards involving work performed by extra operators on other railroads which do not have rules and understandings in effect analogous to those applicable on this property do not have any precedent value in this docket;


      5. The claims are built up on untenable premises wholly at variance with existing rules and understandings and should be denied.


All evidence and data set forth in this dispute have been considered by the parties in conference.


    (Exhibits not reproduced.)


OPINION OF BOARD: In case No. 1 of this claim, it appears that Claimant Cavin worked a regular assignment in relief of the occupant of the position. The assignment was Wednesday through Sunday, with Monday and Tuesday as rest days. Claimant worked Wednesday, September 10, 1952, through Sunday, September 14, 1952. Having worked 40 hours in the work week being relieved, the Monday and Tuesday following were claimant's rest days. Claimant having been assigned to work September 15 and 16, 1952, his rest days, he is entitled to be paid at the time and one-half rate.


When an extra employe takes the assignment of a regular employe, he assumes the conditions of that assignment. He takes the work week of the occupant and the rest days incidental thereto. Article 10, Section 1(h) current Agreement. When he works 40 hours in the work week of the position assumed, he is entitled to the rest days thereof. If he works on his rest days, he is entitled to be paid for rest day work. The senior extra employe cannot claim extra work in excess of forty hours in his work week as against an available junior extra employe who has had less than 40 hours' work in his work week. Article 21 (b), current Agreement. The rules applicable are more fully discussed in Award 6970. They apply to the factual situation existing in the present case and control its result. Claimant Cavin is entitled to be paid the time and one-half rate for his work on September 15 and 16, 1952.


Claims 3 and 4 of Case 1 should also be sustained. R. E. Cavin was not entitled to the work as against Claimant McKinley under Article 21 (b), the latter not having worked 40 hours in his work week.


In Case 2, Claimant Atkins was entitled to work the position in question January 12, 1953, for the reasons hereinbefore set out. In Case 3, Claimant Burdette was likewise entitled to work the position in question on December 31, 1952.


We do not think that the claims for deadhead time contained in Cases 2 and 3 are valid. This time allowance under Article 14 (a), computed on the basis of two minutes for each mile is in the nature of expense for driving an automobile. Claimants not having earned such an expense item, they not having driven their automobiles, they have no basis for claim on these items. In any event one day's pay provides an adequate penalty for the violation.


FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:


That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;

6971-27 1096

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and

    That the Agreement was violated.


                AWARD


Claims in Case 1 sustained. Claims 1 and 2 in Case 2 sustained; Claim 3 denied. Claims 1 and 2 in Case 3 sustained; Claim 3 denied.

              NATIONAL RAILROAD ADJUSTMENT BOARD

              By Order of Third Division


ATTEST: (Sgd.) A. Ivan Tummon
Secretary

Dated at Chicago, Illinois this 29th day of April, 1955.