PARTIES TO DISPUTE:
BROTHERHOOD OF RAILROAD SIGNALMEN OF AMERICA
THE LONG ISLAND RAIL ROAD COMPANY

STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood of Railroad Signalmen of America on the Long Island Rail Road that:






EMPLOYES' STATEMENT OF FACTS: The Scope work involved in this case consists of a concrete manhole (20%' x 5' x 7'%z ) which was installed by contractor, Hendrickson Brothers Company, whose workers were not covered by the controlling and governing working agreement covering T. & S. and T. & T. employes on the Long Island Rail Road.


On January 3, 1952, one of the contractor's workers while operating a bulldozer incident to sewer construction, dug up a fibre-concrete duct line containing T. & S. and T. & T. wires at a location approximately 250 feet west of Saterie Avenue, Valley Stream.


The purpose of installing this manhole in lieu of replacing the duct line in its original form was to provide working space for T. & S. employes to permanently splice the severed cables instead of renewing the existing severed cables which were approximately 500 ft. in length.


The installation of manholes is not an unusual task for employes covered by the T. & S. agreement. A gang of T. & S. employes only a short time prior



7840-5 493





OPINION OF BOARD: Hendrickson Brothers Company was awarded a contract by Nassau County, New York, for the construction of a sewer and drainage project in that county.


While this work was in progress, early in January of 1952, a bulldozer operator, in the employ of Hendrickson Brothers Company, inadvertently drove his machine into a fibre-concrete duct line, demolishing it. This duct line contained Carrier's T&S and T&T wires.


The severed lines were repaired by Carrier's T&S employes and placed in a temporary wood casing pending completion of the sewer project. The new sewer line was being constructed at a right angle to, and ten feet below, the duct line which housed Carrier's wires.


Since responsibility for the damage rested with Nassau County and the general contractor, as County's agent, the damage was repaired by the contractor at no cost o Carrier. It was accomplished by constructing a concrete manhole above and astride the new sewer line.


Once the manhole was completed, all work incident to restoration of Carrier's wire system was performed by Carrier's T&S employes.


The Organization claims that because the damaged duct line "is maintained by T&S employes so therefore the use of persons other than T&S employes to work on this duct line is a violation of the current T&S Agreement."


It is argued by the Organization that the contractor had no right to do the work in question; that T&S employes in the past have built a form of manhole which Carrier called a pullbox, that T&S employes have performed that class of work. It was further argued that the Organization's General Chairman was available to Carrier, and Carrier could have consulted with him regarding the work in question.


Award 3251 (Carter) and Award 4870 (Shake), are cited on behalf of the Organization in support of its position.


The Carrier involved in Award 3251 contracted with workers outside the Agreement to repaint signal apparatus and structures. It was held to be work clearly within the Signalmen's Agreement, and work ruled to be ordinarily and customarily performed by Signalmen, and the Organization's claim was upheld.


In sustaining the Organization's claim in Award 4870, this Board noted it "is also proper to say that when a carrier contracts out work which would appear to be within the scope of the agreement, it must assume the burden of establishing that such conduct was reasonably justified by the facts."


Carrier, on the other hand, makes the point that construction of this concrete manhole was not work within the Scope of the parties' Agreement because the Carrier was not responsible for it nor did it control the execution of the work.


Carrier also cites a number of Awards in support of its position, among them



7840-6 49¢







Here, unlike the situation in Awards 3251 and 4870, Carrier did not contract the work out. It was not its work to perform. It was the liability of Nassau County, and the County had the right to determine the manner in which the work was to be pefformed and by whom.




FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and uon the whole record and all the evidence, finds and holds:


That the Carrier and the Employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act, as approved June 21, 1934;


That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and












Dated at Chicago, Illinois, this 30th day of April, 1957.