NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Edward A. Lynch, Referee
PARTIES TO DISPUTE:
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
CHICAGO GREAT' WESTERN RAILWAY COMPANY
STATEMENT OF CLAIM:
Claim of the System Committee of the
Brotherhood that:
(1) The Carrier violated the Agreement when it assigned
Track Department employes to renew and replace a culvert at or
near Mile Post 444-1 instead of assigning the work to B. & B. Department Employes;
(2) The Carrier further violated the Agreement when it
failed to compensate the aforesaid Track Department employes at
the applicable Bridge and Building rates of pay for the culvert
renewal and replacement work performed;
(3) The Agreement was further violated when Traveling
Carpenter Emil Larson was required to perform B. & B. Foreman's
duties in connection with the work referred to in part (1) of this
claim at his regular traveling carpenter's rate of pay;
(4) Section Foreman W. L. Fischer and Section Foreman
A. W. Culvert be allowed the difference in pay between what they
received at their section foreman's rate and what they should have
received at the B. & B. foreman's rate for five
(5)
hours each on
April 13,
1953;
(5) Section Laborers T. Roe, D. Switzer, A. Stucky, C. Whelldon, G. F. Grace, Paul Reich, C. D. Eastman be allowed the difference in pay between what they did receive at their section laborer's
rate of pay and what they should have received at the B. & B. carpenter's rate of pay for five
(5)
hours each on April
13, 1953;
(6) Traveling B. & B. Carpenter Emil Larson be allowed the
difference in pay in what he did receive at his Traveling Carpenter's
rate of pay and what he should have received at the B. & B.
Foreman's rate of pay for five
(5)
hours on April
13, 1953;
(7) Each B. & B. employe holding seniority on the Minnesota
Division, (except Emil Larson), be allowed pay at their respective
straight time rates for an equal proportionate 'share of the total
[3151
7964-2
316
man-hours (45) consumed by the above referred to section crews
while installing the culvert on April 13, 1953.
EMPLOYES' STATEMENT OF FACTS:
A stone culvert approximately
three feet square with a steel rail reinforced top which had been in service
under the Carrier's man line at Mile Post 444-1 had deteriorated to the extent that replacement was deemed necessary.
Arrangements were, therefore, made to replace that broken-down stone
culvert with a flat Armco corrugated iron culvert, which was three feet in
diameter and twenty-four feet long.
The Armco corrugated iron culvert was purchased in two sections, one
section being about eighteen (18) feet in length; the other section about six
(6) feet in length.
On April 13, 1953, the section forces from the McIntire section and
from the Elkton section installed the eighteen-foot length of new culvert.
The culvert installation work was in charge of Traveling Bridge and Building
Carpenter Emil Larson.
Several months later the six-foot section was installed by Bridge and
Building forces.
The track forces were only allowed and paid as section men and section
foreman respectively for the time they consumed in the culvert replacement
work performed on April 13, 1953, and no attempt was made to send Bridge
and Building forces to perform the work in question.
The instant cla'.m was properly presented and progressed on the property in the usual and' customary manner; the Carrier declining to allow the
claim at all stages of appeal.
The Agreement in effect between the two parties to this dispute dated
April 15, 1940, together with supplements, amendments, and interpretations
thereto are by reference made a part of tis Statement of Facts.
POSITION OF EMPLOYES:
As pointed out in the Employes' Statement of Facts, on April 13, 1953 two (2) section crews installed an eighteen
(18) foot lenth of a new culvert in the Carrier's main line track at Mile
Post 444-1. The entire length of the culvert to be installed was twenty-four
(24) feet, eighteen (18) feet of which was installed, as stated, by the two
section crews, who were taking their orders from a Traveling Bridge and
Building Carpenter, and the remaining six (6) feet being installed several
months later by Bridge and Building forces. In the aggregate, a total of
ten (10) employes, consisting of the following classifications, were used by
the Carrier to mae partial installation upon the project in question on
April 13, 1953:
One (1) Traveling Bridge and Building Carpenter
Two (2) Section Foremen
Seven (7) Section Laborers
Rule 1, Scope of the effective Agreement provides:
"The rules contained herein shall govern the hours of service,
working conditions and rates of pay of all employes in the Maintenance of Way and Structures Department but not including:
1. Supervisory forces above the rank of Foreman.
2. Signal, Telegraph, and Telephone employes.
3. Clerks."
7964-11
335
straight time rate of pay and what they should have received at the
section laborer's straight time rate of pay while so engaged in the
work and on the dates referred to above;
(3) Section laborers and section foreman assigned to Section B East Yard, Minneapolis, on the dates referred to in Part
(1) of this claim e allowed pay at their respective straight time
rates for an equal proportionate share of the total man-hours consumed by the extra gang employes in performing the work referred
to in Part (1) of this claim."
"OPINION OF BOARD:
The Employes contend that Extra Gang No. 4, a lower wage
rated class of employes, performing the work of a higher wage
rated classification and that those persons who actually did the
work are entitled to be compensated at the difference between the
lower wage rate of their class and that for Section Gang 'B'; also,
that Section Gang 'B' should be paid additional compensation for
the days in question at straight time rates for an equal proportionate
share of the man-hours worked by the extra gang.
Rule 36 allows for composite service on payment of the rate
applicable to class of work under conditions stated. While it has
no application to the intermingling and commingling of which we
here speak it adds to the need for observing classification lines and
serves to restrain Carrier in the indiscriminate use of extra gangs
to do section laborers' work.
Claim (3) will be denied. The violation, under facts and circumstances of record, appearing to be one of working employes
under the same contract out of classification, rather than a clear
invasion of another's work domain, we see no need to look beyond
the composite service rule in the Agreement for a remedy. Actual
overtime not being involved, and there being nothing of record on
which to base a finding that the extra gang was worked in place of
regular section gang to avoid overtime, Rule 26 (g) is not applicable to the facts in dispute."
In the instant case the work was performed during regular working hours
-not on overtime-and in view of the Board's findings in Award 6953, it
is apparent that even if the Carrier violated the Agreement by working section crews out of classification (which we again deny) the proper and only
penalty is payment of the higher rates under the Composite Service Rule.
In view of the foregoing claim should be denied in its entirety.
OPINION OF BOARD:
A corrugated iron culvert, 3 feet in diameter
and 24 feet in length, was purchased by Carrier in two lengths-one 18 feet,
the other 6 feet. The IS foot section was installed by Carrier's Section forces,
the C foot section by B. and B. employes some several months after the original section.
It is Organization's contention the installation belongs exclusively to
B. and B. employes.
It is Carrier's contention the Agreement is silent as to what class of
employes should have the exclusive right to install or repair culverts; that the
practice was "to use section crews to install culvert pipes where actual or
potential disturbance of the roadbed is involved, or where it is only necessary
to remove track and roadbed over culvert, roll in pipe, then replace roadbed
and track; especially when, as here, no timber work is necessary to close
openings or support track while work is being performed."
7964-12
326
The only comment offered by the Organization is that Carrier's argument,
above, is "directly in conflict with * * * Rule 51 (c), with the Opinion
of
this Board in Award 5485 and with the history of work assignments on this
property as we know them to be."
The original culvert, which the one here involved replaced, was installed
by an outside contractor prior to 1899.
While Organization contends the Carrier "unquestionably recognized they
had improperly * * * used * * * section crews (to install the 18 foot section)
because B. & B. employes were permitted to complete the installation of the
remaining six feet of the culvert in question," Carrier states installation of
the 6 foot pipe three months later "did not involve removal of rails or ties
or potential disturbance thereof but consisted primarily of applying connecting
band to one end of the 18 foot pipe thereby extending culvert pipe to permit
proper passage of the water."
Rule 51 (c), relied upon by the Organization reads as follows:
"An employe assigned to construction, repair, maintenance or
dismantling of buildings, bridges or other structures, (except the
iron or steel work), including the building of concrete forms, erecting
false work, etc., or who is assigned to miscellaneous mechanic's
work of this nature shall constitute a Bridge and Building carpenter
and/or mechanic."
It is argued on behalf of Organization that "certainly the work which
is the subject of this claim falls squarely into this category. The Carrier
points out that a culvert is a drain. Of course it is that, but as the Employes
have pointed out at page 26 it is also a bridge over which the tracks are
place It is work belonging to Bridge and Building employes and the assignment of this work to other employes was a violation of the Agreement."
On the other
hand, it is argued on behalf of Carrier that the "record in
this case shows that where the installation of culvert pipes necessitates disturbance of rails, ties and roadbed, it has been the practice for track employes
to perform such work. The record also shows that when culvert pipes are
installed without disturbing the roadbed employes of the B. & B. Department
have in some instances performed the work. Petitioner has not overcome
these statements. Neither has petitioner shown that the particular work involved has been re:;erved to B. & B. employes exclusively by rule, practice,
custom or tradition. We have consistently held that the burden of presenting
positive and substantive evidence in support of a claim is upon the party
seeking its allowance. (Awards 7584, 7362, 7353, 7180, 7179, 6964 and
6748 among many others.) Petitioner has simply failed to sustain the burden
of proving a violation."
Organization relied on Award 5485 (Donaldson) but the basic facts of
that claim are not analogous. In Award 5485, Carrier contracted out the
building of an extension to an existing concrete culvert.
Carrier cites Award 6053 (Begley) where Organization charged Carrier
violated the Agreement when it assigned Track Department employes in an
Extra Gang to install culverts. In denying that claim, this Board said:
"This claim to be allowed must be supported by rules of the
Agreement. Neither the scope rule or the seniority rules cited
grants the work in question exclusively to the Bridge and Building
employes. This Board has decided this question many times starting
with Award 615 down through Award 6007. We find the work here
performed * * * to be work incident to and directly attached
to the duties of their jabs and work of a type they have performed
in the past under all the agreements including this effective
agreement."
7964-13
327
The following excerpt from Award 5491 (Donaldson) is also offered on
behalf of Carrier:
"* * * the case is peculiarly similar to that subject of Award
1134. We affirm what we there said, namely, 'In digging the trench
beneath three main tracks of the railroad, as was done, and its
extensions otherwise, in the circumstances appearing, potential disturbance of the roadbed at vital points challenged the Carrier's concern to a degree not lightly to be regarded, and the back filling
partook of the same potentialities. Throughout the process, as we
are persuaded, responsibility for the finished job in relation to the
trench proper-digging and back filling rested on the track force.
"We cannot conclude that under circumstances here proven
that claimants were required to fill the position of other employes
within the meaning of Rule 32. Rather, they were performing divisible work, under and along the roadbed, their recognized domain,
for which they were responsible and to which their regular rate of
pay applied."
In view of the record here established we must and do conclude a denial
award is indicated.
FINDINGS:
The Third Division of the Adjustment Board, after giving
the parties to this dispute due notice of hearing thereon, and upon the whole
record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement has not been violated.
AWARD
Claim denied in its entirety.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of THIRD DIVISION
ATTEST: A. Ivan Tummon
Executive Secretary
Dated at Chicago, Illinois, this 13th day of June, 1957.