NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
PARTIES TO DISPUTE:
THE ORDER OF RAILROAD TELEGRAPHERS
THE NEW YORK, NEW HAVEN AND HARTFORD RAILROAD
COMPANY
STATEMENT OF CLAIM: Claim of the General Committee of The
Order of Railroad Telegraphers on The New York, New Haven and Hartford
Railroad, that:
1. Carrier violates and continues to violate the agreement
between the parties when it requires or permits the agent at Moosup,
Connecticut, to suspend work during his regular hours at Moosup and
perform work at Central Village, Connecticut; Carrier further violates and continues to violate the agreement between the parties
when it requires or permits the agent at Moosup, Connecticut, to
suspend work during his regular hours at Moosup and perform work
at Wauregan, Connecticut.
2. Carrier shall be required to compensate the senior idle employe, extra in preference, in the seniority district in the amount
of a day's pay of eight hours for each violation on each day that
it occurs, commencing with October 27, 1956, and continuing
thereafter until the violation is corrected.
FINDINGS: The Third Division of the Adjustment Board finds:
That the dispute was certified to the Third Division of the Adjustment
Board ex parte by the complainant party; and
That hearing thereon has been held and concluded. Under date of
July 14, 1959, the parties jointly addressed a formal communication to the
Secretary of the Third Division requesting withdrawal of this case from
further consideration by the Division, which request is hereby granted.
AWARD
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of THIRD DIVISION
ATTEST: A. Ivan Tummon
Executive Secretary
Dated at Chicago, Illinois, this 5th day of August, 1959.
(1891