PARTIES TO DISPUTE:


STATEMENT OF CLAIM: Claim of the General Committee of The Order of Railroad Telegraphers on the Norfolk Southern Railway that:





















9022-2 666

That the dispute was certified to the Third Division of the Adjustment Board ex parte by the complainant party; and


That hearing was waived and under date of September 21, 1959 the parties jointly addressed a formal communication to the Secretary of the Third Division requesting withdrawal of this case, which request is hereby granted.


                  AWARD


    Claim dismissed.


              NATIONAL RAILROAD ADJUSTMENT BOARD By Order of THIRD DIVISION


              ATTEST: S. H. Schulty

              Executive Secretary


Dated at Chicago, Illinois, this 13th day of October, 1959.