NATIONAL RAILROAD ADJUSTMENT BOARD
Raymond E. LaDriere, Referee
PARTIES TO DISPUTE:
THE ORDER OR RAILROAD TELEGRAPHERS
GEORGIA RAILROAD
STATEMENT OF CLAIM:
Claim of the General Committee of The
Order of Railroad Telegraphers on the Georgia Railroad that:
1. Carrier is in violation of the agreement between the parties
when it combined the work of the Telegraph Clerk with the work of
the Agent Telegrapher at Milledgeville, Georgia, each Monday,
beginning with the first Monday following September 1, 1949, continuing until March 23, 1951, requiring the Agent-Telegrapher to
perform such combined duties on each such Monday, the assigned
rest day of the Telegrapher-Clerk, and
2. When it combined the duties of the Agent Telegrapher with
the duties of the Telegrapher-Clerk each Saturday for the same period
of time named in paragraph 1, requiring the Telegrapher-Clerk to
perform such combined duties on each Saturday, the assigned rest day
of the Agent-Telegrapher, and
3. The Carrier shall now compensate the senior idle extra,
available telegrapher for eight (8) hours at the straight time rate
for each Monday and Saturday that the occupants of the positions
named in paragraphs 1 and 2 were so used, or if no such extra idle
available telegrapher, then the Carrier shall compensate the regular
occupants of the positions of Agent-Telegrapher and TelegrapherClerk at Milledgeville, Ga., for eight (8) hours at the time and onehalf rate for each such Monday and Saturday that such violation of
the agreement existed.
4. Where a holiday is involved the compensation for any employe shall be at the time and one-half rate.
EMPLOYES' STATEMENT OF FACTS: The facts and rules of the
agreement involved in this claim are exactly similar to the facts and rules
submitted in Award 6690 between the same two parties which was sustained
on the 25th day of June 1954, for a violation at Thompson, Ga. In view of this
exact parallel this case was not submitted to the Adjustment Board and it was
believed that the decision rendered in the Thompson case would govern the
disposition of both cases.
[8807
9954-9
888
tation placed upon classes or classification of work. Award 6690
appears to have adopted the same erroneous conclusions. We think
the foregoing awards fail to consider the overall purpose of the 40Hour Week Agreement. They fail to consider all of the provisions
of that Agreement and give stress to particular provisions which
create an illusory result. A part of the bargain for a five day week at
the then existing pay for six days' work, was the right of the Carrier
to eliminate the necessary rest day work to the extent that it could
by the expedient of staggering work weeks."
The attention of the Division is respectfully called to its Awards 5545, 5555,
5557, 6001, 6002, 6042, 6075, 6184, 6212, 6216, 6232, 6602 and Second Division
Awards 1528, 1565, 1566, 1644, 1669.
For the reasons outlined above, it is our opinion claim is without
merit
and we respectfully request it be declined.
All data contained herein has been made available to Petitioners.
OPINION OF BOARD:
The Carrier employs an Agent-Telegrapher and
a Telegrapher-Clerk in its station at Milledgeville, Georgia. With the inauguration of the forty hour week September 1, 1949, the Carrier staggered the
work weeks in accordance with operational requirements, the Agent-Telegrapher being assigned to work Monday through Friday with Saturday and
Sunday as rest days and the Telegrapher-Clerk to work Tuesday through
Saturday with Sunday and Monday as rest days. Both the Agent-Telegrapher
and the Telegrapher-Clerk are covered by the Agreement, are in the same
seniority district and perform the same class of work.
Petitioner contends that Carrier cannot stagger work weeks under the
circumstances stated and relies particularly on Award 6690-Leiserson which
involved these same parties, the same agreement, a similar factual situation
but a different town.
Carrier relies particularly on Award 6946-Carter, which not only involved
similar, if not identical, rules and a similar factual situation, but which
reached a result contrary to Award 6690 and expressly overruled that award.
The question here presented, therefore, is whether this Board should uphold,
Award 6690 or Award 6946.
This Division has long held that, unless palpably wrong, the Board is
never warranted in overruling, in a subsequent dispute, a previous Award
construing the same provision in their agreement. Awards 7968-Elkouri,
8104-Guthrie, 8687-Lynch; and whether a prior award constitutes a controlling
precedent is dependent upon the soundness of the reasoning upon which it
is based. Awards 8687-Lynch, 4516-Carter, 6094-Whiting, 4770-Stone, and
others.
The arguments used by the petitioner in what became Award 6690 were
the same as those in the docket decided by Award 6946, and in rejecting them
it was said:
"The question raised as to whether or not the occupant of a
position may be used on one of his regularly assigned days to do
work on a rest day of a different position having different duties by
combining such necessary duties with those of his own position, is a
wholly different matter. The Division appears to have passed on the
9954-10
889
question several times with conflicting results. We shall attempt to
resolve the issue by a careful and complete consideration of the
applicable rules and the intendments of the parties that may be
drawn therefrom.
The Organization relies primarily upon the following rules, the
pertinent parts of which are:
`Section 6. The Carriers
will establish, effective September 1, 1949, for all employes, subject to the exceptions
contained in the Sections 6-22, a work week of 40 hours,
consisting of five days of eight hours each, with two consecutive days off in each seven; the work weeks may be
staggered in accordance with the carriers' operational requirements; so far as practicable the days off shall be
Saturday and Sunday. The foregoing work week rule is
subject to the provisions of this Agreement: * * ".' Article
3, See. 6, Current Agreement.
Section 14. Where work is required by the Carrier to
be performed on a day which is not a part of any assignment, it may be performed by an available extra or unassigned employe who will otherwise not have 40 hours of
work that week; in all all other cases by the regular employe.'
Article 3, Sect. 14, Current Agreement.
"Other rules are relied upon which we do not deem necessary
to quote. We shall refer to their provisions when the need arises.
The Carrier relies substantially upon the same agreement provisions.
The dispute grows out of the different meanings which the parties
have gathered from identical language.
The situation at Stillwater, briefly is: The Telegrapher-Clerk
was assigned Tuesday through Saturday and the Agent-Telegrapher
was assigned Monday through Friday, after September 1, 1949. On
Mondays and Saturdays each was required to do whatever work
was necessary to be done, including some of the duties of the other.
Both employes belonged to the Telegraphers craft, were in the same
seniority district, were carried on the same seniority roster, and
each was qualified to perform the work of the other. The positions
were not identical and the rates of pay were different. The Organization asserts that the assignments are violative of agreement rules
and claim is made for reparations on that basis.
The record and briefs are long and the awards cited are
numerous. W e cannot hope to exhaustively discuss each phase of the
case in detail. We shall confine the opinion to a statement of our
conclusions and a concise exposition of the reasons upon which they
rest.
It will be noted that the staggering of work weeks is an integral
part of Article ITI, Section 6. It is clearly of equal importance with
the establishment of the 40 hour week itself. In other words, the
establishing of the 40 hour week with two rest days in seven and
the staggering of work weeks in accordance with the carriers'
operational requirements are the two primary provisions of the
40 Hour Week Agreement, even though they
are subject to other
9954-11
Sg0
provisions of that agreement. It is plain that the right to stagger
work weeks to meet carriers' operational requirements was of equal
importance with the establishment of the 40 hour work week itself.
We must conclude that the establishment of the 40 hour week without a reduction in weekly pay carried with it the idea that the
carriers could eliminate certain unnecessary employes through the
process of staggering work weeks. It was one of the compensating
factors that was of advantage to the carriers when they agreed to
the 40 hour work week with the same pay as the previous six day
week. Award 5545.
The next question that naturally follows is what positions might
be staggered to accomplish the purposes of the agreement. It is clear,
we think, that a position within the scope of one craft could not be
staggered with a position under another craft when the work is the
exclusive work of one. Two positions occupied by a signalman and a
telegrapher, for instance, could not be staggered as craft lines are
not wiped out by the 40 Hour Week Agreement. Neither could two
employes in the same craft holding positions in different seniority
districts be staggered under this agreement; nor may two positions
in different classes be staggered where common seniority between the
classes does not exist. But where classes are established within a
craft for purposes other than the establishment of seniority rights,
positions in the two classes may properly be staggered if each is
qualified to perform the work of the other. If these are the proper
concept's contained in the 40 Hour Week Agreement, and we think
they are, the Carrier had the right to stagger the two positions in the
dispute before us. The fact that Carrier changed the duties of the positions as of September 1, 1349, in order that the positions could be
staggered to meet operational needs is not a material fact. Either
party may do these things which the contract permits for any reason that he deems sufficient.
The claim that the rest days of six day positions must be filled
under the circumstances here shown is without merit. It was clearly
contemplated that work weeks could be staggered in accordance with
the carriers' operational requirements in order to reduce the costs
of operation. It is only when carriers' operations require rest days
to be worked that the rules governing rest day work come into
play. When work on rest days of six and seven day positions is
required, the carriers are obligated under Section 10-a to establish
all possible relief assignments with five days of work. Such regular
relief assignments are not required to be established except where
carriers' operational requirements make them necessary.
Where work remains to be performed on unassigned days remaining after all regular relief assignments have been made which are
possible to be made, Section 14 provides that it may be performed
by an available extra or unassigned employe who will otherwise not
have 40 hours of work that week and, in all other cases, by the regular
employe. This rule means just what it says, as we have consistently
held, and when the work involved falls within its terms, the Carrier
has no alternative method of getting the work done. But in the case
before us, the Carrier procurred the performance of all necessary
work on the days involved by the expedient of staggering the work
weeks of the Agent-Telegrapher and the Telegrapher-Ticket Clerk.
Under such circumstances the rules governing regular relief assign-
9954-12
891
ments and work on unassigned days have no application. We have
repeatedly held, and correctly we think, that the assignment of regular
relief positions and of work on unassigned days is not a condition
precedent to the staggering of work weeks. The meaning of the 40
Hour Work Week Agreement is quite the contrary; the Carrier may
procure the performance of all necessary work that it can by the
staggering of work weeks before the assignment of rest day work
comes into the picture. It is clear, therefore that the Carrier did
not violate the Agreement under the facts and circumstances shown
in the present case.
The foregoing conclusions are sustained generally by Awards
5545, 5555, 5557, 6001, 6002, 6042, 6075, 6184, 6212, 6216, 6232, 6602.
Awards 1528, 1528, 1565. 1566, 1644, 1669 Second Division.
The position of the Organization has support under some of the
previous holdings of the Board. We feel obligated under such circumstances, to point out our reasons for not accepting the interpretation
it places upon the Agreement.
It is pointed out that since the origin of `rest days' as we now
understand them, the idea has prevailed that work on rest days
should be assigned to a regular relief employe; or if there is no such
employe available, to an extra employe; and if there is neither a
relief or extra employe available, then the regular employe is to be
used on an overtime basis. For the purpose of this case, we accept
this statement as being correct on this Carrier prior to September 1,
1949, under the provisions of Mediation Agreement A-2070. We grant,
also, that the same provisions relative to rest day work were retained
after the advent of the 40 hour week
when rest day rules became
applicable under that agreement. But they did not become applicable
until the expedient of staggering work weeks was first applied to
meet operational needs. It the work necessary to be performed can be
done through the expedient of staggering work weeks of regularly
assigned employe, the necessity for rest day relief assignments does
not exist. The relationship of Mediation Agreement A-2070 to the
present situation is discussed in Award 6184 and although the discussion is in connection with a dispute on another carrier, the general
holdings of that award control the situation before us. We necessarily
conclude that rest day work is to be assigned just as it was prior to
the 40 Hour Week Agreement when it is necessary to be assigned.
The Carrier asserts that the language `all possible regular relief
assignments * * * will be established to do the work necessary on rest
days' contained in Section 10-a, means that relief positions need not be
established unless they are necessary and that the staggering of
work weeks permits the combining of rest day work with the work
of another position. The Organization strongly excepts to this construction. But nonetheless, the position of the Carrier is the correct
one when it is applied within the limitations which we have heretofore set out. We quite agree that there is work to be performed on
each day of a six day position, but rest day assignments are necessary
only when staggering of regular five day work week assignments
will not meet the needs of carriers' operations. To hold otherwise
would be to deprive the Carrier of a rule it bought in agreeing to the
40 hour week with pay on a 48 hour basis." (Emphasis theirs.)
9954-13
892
See Awards 5545 (Elson), 5555, 5556, 5557, 6947, 6948, 7073, 7317, (Carter),
5912 (Douglass, D. R.),
6001 (Daugherty), 6023 (Parker), 6042 (Whiting),
6075, 9199 (Begley), 6184, 6212 (Wenke), 6232 (Stone), 6602 (Sharps), 8003,
8531 (Bailer), 8136, 8137, 8138, 8139, 9504 (Elkouri), 8278 (Lynch), 9030, 9105,
9392 (Hornbeck), 9042, 9043 (Weston) and Awards 9574, 9575 (H. A. Johnson),
9772, 9773 (Larkin), as well as Second Division Awards 1528 (Parker), 1565,
1566 (Weeks), and 1644, 1669 (Carter), among others.
Award 6688 reached the same conclusion as Award 6690 and with respect to these Awards it was further held in Award 6946,-
We point out that no effect is given to the right of Carrier to
stagger work weeks in Award 6688. The award holds: 'We cannot
agree that it does have the right so to combine the two assignments of
different classifications so that on Saturday one employe will perform the duties of both.' We quite agree with this controlling provision if the 'different classifications' do not have common seniority.
This is the meaning given the provision in Award 6184, which we
think is the correct one. It must be borne in mind that classifications
of employes may be made on trifling differences for many different
reasons. The classifications which are of interest here are those
which have some relation to the issue before us. A classification for
pay purposes or the exercise of orderly displacements is not such. It
is classifications for purposes of seniority only that have application here. It appears from Award 6688 that the employes involved
were of the same craft, in the same seniority district, carried on the
same seniority roster, were in classes having common seniority, and
were qualified to perform the work involved.
Under such circumstances, we cannot agree with the result
reached. We think the right to stagger work weeks in accordance with
carriers' operational requirements contemplates that such positions
may be staggered for the very purpose of avoiding the assignment
of rest day work which is not necessary to the economic and efficient
operation of the railroad. We cannot agree with the holdings of
Award 6688 with reference to carriers' right to stagger work weeks
or with the interpretation placed upon classes or classifications of
work. Award 6690 appears to have adopted the same erroneous conclusions. We think the foregoing awards fail to consider the overall
purpose of the 40 Hour Week Agreement. They fail to consider all
of the provisions of that Agreement and give stress to particular
provisions which create an illusory result. A part of the bargain
for a five day week at the then existing pay for six days' work, was
the right of the Carrier to eliminate the necessary rest day work to
the extent that it could by the expedient of staggering work weeks."
See Awards 7073, 7317 (Carter), 8003, 8531 (Bailer), 8137, 8138, 8139
(Elkouri), 8278 (Lynch), 9030, 9105 (Hornbeck), 9042, 9043 (Weston), 9119
(Begley), and 9574, 9575 (H. A. Johnson), previously cited herein.
The Opinion of the Board in Award 6946, thus quoted from at length,
presents more fully and capably the position of this Board than could be
done in any other way. Written by Judge Carter, a Referee who wrote more
opinions over a greater period of years than any other, it indicates clearly
that Awards 6690 and 6688 tend to emasculate and weaken the provision for
staggered work weeks and therefore Award 6946 should be followed.
9954-14
893
This Board therefore disapproves the holding in Awards 6688 and 6690
(insofar as herein indicated) and affirms our holding in Award 6946.
FINDINGS: The Third Division of the Adjustment Board, after giving
the parties to this dispute due notice of hearing thereon, and upon the whole
record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Carrier did not violate the Agreement.
AWARD
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of THIRD DIVISION
ATTEST: S. H. Schulty
Executive Secretary
Dated at Chicago, Illinois this 26th day of May, 1961.
DISSENT TO AWARD 9954, DOCKET TE-8599
The majority here, as in numerous other cases, has merely followed the
erroneous holdings of Award 6946.
My dissents to Awards 9574 and 9575 amply set forth my reasons for
disagreeing with such decisions, and apply with equal force here. They are,
by this reference, extended to the present case, Award 9954, which I consider to be equally erroneous.
J. W. Whitehouse
Labor Member