NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
(Supplemental)
PARTIES TO DISPUTE:
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
SOUTHERN RAILWAY COMPANY
STATEMENT OF CLAIM: Claim of the System Committee of the
Brotherhood that:
(1) The Carrier violated the effective Agreement when, on
March 7, 8, 9, 10, 11, 16, 17, 18, 21, 22, 23, 28, 29, 30, 31, 1955
and on April 1, 4, 5, 6, 7, 8, 11, 12, 13, 14, and 15, 1955, it assigned
Track Laborer Talmadge Thomas to perform the usual and customary duties of a helper on Crane CTS-14 and failed and refused to
compensate him at the Crane Operator helper's rate of pay.
(2) The Carrier now be required to reimburse Track Laborer
Talmadge Thomas for the difference between what he received at the
track laborer's rate and what he should have received at the Crane
Operator Helper's rate of pay for services as rendered on the dates
referred to in part (1) of this claim.
FINDINGS: The Third Division of the Adjustment Board, after giving
the parties to this dispute due notice of hearing thereon, and upon the whole
record and all the evidence, finds and holds:
That Carrier and Employes involved in this dispute are respectively
Carrier and Employes within the meaning of the Railway Labor Act, as
approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein;
That the dispute was certified to the Third Division of the Adjustment
Board ex parts by the complainant party; and
That hearing thereon has been held and concluded. Under date of
June 26, 1961, the parties jointly advised the Secretary of the Third Division
of their desire to withdraw this case from further consideration by the Division which request is hereby granted.
(4867
10004-z
¢g7
AWARD
Case dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of THIRD DIVISION
ATTEST: S. H. Schulty
Executive Secretary
Dated at Chicago, Illinois, this 19th day of July, 1961.