STATEMENT OF CLAIM: Claim of the General Committee of The Order of Railroad Telegraphers on the Lehigh Valley Railroad, that:
EMPLOYES' STATEMENT OF FACTS: There is in full force and effect a collective bargaining agreement between the parties to this dispute.. The agreement, as amended, is on file with the Division and is by reference made a part of this submission as though set out herein word for word.
The Railroad will hereinafter be referred to as Carrier or Management, and the Telegraphers will be referred to as Employes or Telegraphers.
This dispute was handled on the property in the usual manner through the highest officer designated by Carrier to handle such disputes, and failed of adjustment. The dispute concerns interpretation of the collective bargaining agreement and is, under the provisions of the Railway Labor Act, as amended, properly referred to this Board for award.
The facts presented in this submission were made a matter of discussion with the Committee in conference on the property.
OPINION OF BOARD: Mr. H. C. Pfeiffer is the regular occupant of a cycle relief position whose assignment is as follows:
On Wednesday, October 19, 1956, Mr. Pfeiffer was directed to perform work as telegrapher (2:00 P. M. to 10:00 P. M.) at Packerton, Pennsylvania in lieu of his regularly assigned relief position at Bethlehem, 9:45 P. M. to 5:45 A. M.
There is no dispute between the parties regarding the facts in this instant. The problem with which we are confronted is to determine whether the assignment of Mr. Pfeiffer on October 19, 1955 to perform work as telegrapher at Packerton, Pennsylvania instead of performing his regularly assigned duties at Bethlehem, Pennsylvania was in fact an emergency as provided for in Rule 6 of the Agreement above stated.
On October 3, 1955 a serious wreck occurred on the Carrier's line at New Market, New Jersey as a result of two trains colliding, causing much property damage and personal injury. An investigation to determine the cause and responsibility for the wreck was scheduled and held in October 20, 1955 by the Superintendent in his office at Jersey City, New Jersey. The Superintendent decided it would be required to have the Assistant Chief Dispatcher, who was on duty and working at the time the wreck occurred at 10861-8 ';p4
New Market, New Jersey on October 3, 1955, attend the investigation scheduled for October 20, 1955. This Assistant Chief Dispatcher was scheduled to work on the third trick the night of October 19 through to the morning of October 20 and in order for him to be available he was relieved from his assignment that night. The vacancy was filled by using the senior available extra Assistant Chief Dispatcher whose regular assignment was second trick telegrapher, Packerton, Pennsylvania with hours of assignment from 2:00 P. M. to 10:00 P. M. The Claimant was then assigned to fill the position open at Packerton, Pennsylvania from 2:00 P. M. to 10:00 P. M. on October 19, 1955.
The Carrier states in its submission (Record page 33) that Emergency has been defined in the First Division Award 14450 as follows:
An emergency situation did take place on the date of the collision and not in the opinion of this Board on October 19, 1955 the date prior to the investigation regarding the causes of the accident. It cannot be argued by the Carrier that October 20 was not voluntarily set by the Carrier and that this date was not set several days prior to October 20. We hold with the opinion expressed in Award 2942 which in part is as follows:
It follows then that if an emergency situation did not occur that Rule 6 is not applicable.
It appears inconsistant for the Organization, as in this instant, to argue that an emergency did not occur, to, at the same time claim the benefits provided under the emergency rule or Rule 6 (above quoted).
The Organization claims that Rule 11 was violated. Rule 11 is as follows:
We therefore have a violation of Rule 11 (b) with pro rata time and Rule 13 with time and a half for actual time worked.
We hold with the opinion expressed in Award 5473 which in part is as follows "Our late awards hold that to allow both penalties concurrently is to allow double penalty, and that the greater penalty alone should be allowed. Awards 4109, 5423."
Claim is therefore sustained for 8 hours at the regular rate of the Bethlehem position which Claimant was scheduled to work on date of claim, in addition to amount already paid for services rendered on this date.
FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and