NATIONAL RAILROAD ADJUSTMENT BOARD

THIRD DIVISION

(Supplemental)

Preston J· Moore, Referee


PARTIES TO DISPUTE:

BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
MISSOURI-KANSAS-TEXAS RAILROAD COMPANY
MISSOURI-KANSAS-TEXAS RAILROAD COMPANY OF TEXAS

STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:




EMPLOYES' STATEMENT OF FACTS: In 1957 the Carrier decided to construct a number of new tracks between mile posts 841 and 842 in its Bellmead Yard.


Commencing on or about May 1, 1957, the work of constructing the new grade for the above referred to tracks was assigned to and performed by a General Contractor.


The work was of the nature and character that has been traditionally performed by employes holding seniority in the Machine Operator's class or craft, using equipment provided by the Carrier.


The employes holding seniority in the Machine Operator's class or craft on the territory where the work was performed were available, fully qualified and could have expeditiously performed the above referred to Machine Operator's work.


The Agreement violation was protested and the instant claim filed in behalf of the claimants.



11477-35 47



OPINION OF BOARD: On or about May 1, 1957, the Carrier began work on constructing new grade for tracks between milepost 841 and 842 in its Bellmead Yard. Petitioner contends that the work was of the nature and character that has been traditionally done by employes holding seniority in the machine operators class or craft. Petitioner contends that by provision of the scope rule that was work belonging to them. Carrier contends that petitioner alleged no past practice on the property and submitted no proof of past practice.


We find from examination of the record that the scope rule is general in character. Therefore, we must turn to past practice on the property to determine if the work is of the nature that has been reserved to the claimants.


The only evidence furnished by petitioner is a letter which is inadequate to sustain an allegation of past practice on the property. There is in the record an instrument entitled: "File Memorandum Contracting Maintenance Of Way Work" which is set forth in full below:







We note the paragraph wherein it was agreed that they would not formulate any statement or agreement on that question at that time. We can construe the instrument as to general procedure as to how the parties were going to continue to treat the contracting out of maintenance of way work. We note that one exception which provided that the railroad could contract out maintenance of way work was where the railroad did not possess a sufficient amount of suitable equipment necessary for the performance of the job. Petitioner contends they could have purchased or rented the equipment. However, this provision is not in the File Memorandum Agreement and therefore does not compare with the general line of cases where no such memorandum is in effect.

11477-36 4S

The Board holds that there is insufficient evidence to sustain a claim of past practice on the property. For that reason we find the agreement was not violated.

FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:

That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and













Dated at Chicago, Illinois, this 6th day of June 1963.