THIRD DIVISION
(Supplemental)
(1) The Carrier violated the effective Agreement when it assigned the work of constructing concrete foundations for air compressors in the Power House Building and the installation of a concrete floor in that building; the remodeling of the Oil House Building; the construction of concrete skids; the construction of a Paint and Lumber Building and the construction of a concrete roadway at Clinton, Iowa was assigned to and performed by a general contractor whose employes hold no seniority rights under the provisions of this Agreement;
(2) The B&B foremen, Carpenters and Carpenter Helper named in General Chairman Schultz's letter of April 24, 1957 to Engineer of Maintenance, Mr. M. S. Reid each be allowed pay at their respective straight time rates for an equal proportionate share of the total man hours consumed by the contractor's forces in performing the work referred to in Part (1) of this claim.
Attention of the Board is directed to this matter in order that this Board may be fully familiar with the circumstances in this case and as showing to this Board that the agreement in effect when this Board's Awards 6299 and 6300 were rendered is still effective on this property.
The carrier submits that the claim in this case must be denied in its entirety.
All information contained herein has previously been submitted to the employes during the course of handling of this case on the property and is hereby made a part of the particular question here in dispute.
OPINION OF BOARD: The dispute is centered about the contracting out of certain work, for which the Claimants claim compensation at their respective straight time rates, for an equal number of hours as that required by outside contractors to perform work, on behalf of listed Maintenance of Way employes. The claim is based on the Scope Rule of the effective Agreement which reads as follows:
Prior to the contracting out of the work, the Carrier wrote on June 13, 1956 to the General Chairman as follows:
Subsequently the General Chairman replied by letter that he was not in concurrence with the request of the above letter, but still later he responded with the following letter:
With further reference to my letter dated June 29, 1956 in regard to your request that you be permitted to contract and construct a mill type building 160' x 1,000' at Clinton, Iowa.
The Carrier then contracted out the construction of the building, which contract, in addition to the construction of the building 160 feet by 1,000 feet included the construction of a Paint and Lumber Building, requiring 9,750 hours of outside labor, a concrete floor in the Power House Building, including concrete foundations for air compressors, requiring 1,530 hours of outside labor; remodeling the Oil House, requiring 3,379 hours of outside labor; the construction of a concrete roadway north of the 160 x 1,000 foot car shop building requiring 1,993 hours of outside labor; and the construction of concrete skids east of the Car Shop building, requiring 565 hours of outside labor.
The employes claim the work listed above, other than the construction involved in the Car Shop building, for which concurrence was obtained in Chairman Schultz's letter of July 3, 1956.
A. That the concurrence of the General Chairman was given, and that the work done was either incidental to the main building, or formerly a part 12132-25 1030
of that building and through a subsequent change of plans, constructed outside the building;
B. That the contract did not require concurrence of the Organization for such work, as it was outside the scope of the effective Agreement and the employes did not have exclusive right to such work.
C. That in the past, the Carrier had contracted out work of much lesser magnitude, thus evidencing the right to so contract.
It is apparent that Chairman Schultz did concur in the contracting out of the main building. The concrete driveway and the concrete skids, north and east, respectively, of the main shop building, were clearly incidental appurtenances of the Shop building, and thus included in the concurrence of Chairman Schultz. The Carrier's position that the balance of the work was included, cannot be sustained. The Power House Building and the Oil House Building were separate buildings existing prior to the construction of the main shop building. The Paint and Lumber Building (160 feet by 40 feet) was additional roof area not included in the 1,000 feet by 160 feet shop building. The shop building was not reduced in size. In no sense could the construction of the paint building be included within the meaning of painting facilities mentioned in the original letter of June 13, 1956, as included in the main building.
We now must consider the question of the Scope Rule. The Carrier has cited numerous awards indicating that work of constructing entire buildings may be contracted to outside contractors. The contract has been negotiated several times since these awards were handed down, but no change had been made in the Scope Rule. (See Awards 6299 and 6300.) The cited awards, on this same property, indicate that construction of much less than this magnitude has been contracted out for a long period of time, and denies a claim involving a building 22 feet by 44 feet. Award 6299, on page 11 thereof, reads in part:
"In the record we find a showing made by the Carrier that between November 1, 1941 and November 1, 1951, it contracted out work of the character here involved in 29 instances. The effective Agreement bears date of January 1, 1947, and part of the 29 construction contracts were awarded before and part after that Agreement was negotiated. The Carrier also makes the positive statement that for thirty years it has been its uniform practice to contract for the construction of new facilities as it did in this case, without any protest whatever from the Organization in the past ten years. New contracts have been negotiated between the parties while these practices obtained."
The Organization bases its position in part, on Awards 4158, and 5090, both on this property. In Award 5090, the Carrier contracted out certain work which the award describes as follows:
`OPINION OF BOARD: On or about October 7, 1947, the Carrier awarded to an independent contractor work involving (a) construction of reinforced concrete three stall drop pit in enginehouse at Chadron, Nebraska, (b) construction of concrete piers and abutment wing walls at Bridges 732 and 738 in the vicinity of Glen, Nebraska, and (c) construction of 112 pre-cast reinforced concrete blocks to be placed on bridge seats of 12 bridges between Ft. Robinson and Glen, Nebraska. 12132-26 1031
It is to be noted that the claim only concerned the making of reinforced concrete blocks for bridge seats, and that concurrence was given by the Organization for a drop pit, while neither concurrence nor claim is found in regard to bridge piers, or abutment wing walls. Award 5090 makes a careful analysis of previous awards, among those being Awards 4158 and 4159 which are dealt with as follows:
Thus, the authority has been established in these awards, as in 6299 and 6300, that such construction work is not exclusive, and that the work has not been exclusive under the scope rule. Interpretation and past practice, however, has established the principle that the work may not be contracted out to others, if it is of the type and magnitude usually performed by the employes of the Carrier.
Here, where the work was of sufficient magnitude the contracting out of the work was in order. The Carrier obtained the General Chairman's concurrence to such contracting-out, though such concurrence is not required by the Agreement or previous awards. Work was then performed which was not within the concurrence obtained, but was a part of the general contract for which claim is here made. Award 10300 comments on a similar situation as follows:
The instant claim for 74 employes of the Clinton, Iowa, force, involved only a part of the entire contract, but the parts claimed required over seventeen thousand hours of labor. The Claimant crew had a daily potential of but 592 hours; thus, the work claimed would have required their entire attention for thirty days to the exclusion of all normal work, clearly beyond the capability of the Claimant force, even if such force were substantially augmented. The claim, therefore, will have to be denied.
FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and