THE DENVER AND RIO GRANDE WESTERN
RAILROAD COMPANY
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
EMPLOYES' STATEMENT OF FACTS: Without benefit of negotiations with or approval of representatives of the Carrier's Maintenance of Way employes, the Carrier assigned to the Hemmenger Construction Company the work of constructing and erecting a prefabricated steel building to be used as a paint shop for carmen at Burnham Yards. The building is of simple design and construction, is 180 feet long and 26 feet wide with a concrete foundation and floor. All skills, tools and equipment necessary to construct and erect this building were readily available to and from the Carrier's B&B forces, such B&B forces having constructed and erected similar buildings in the past, in addition to the performance of considerable repair, maintenance and remodeling work on other prefabricated metal buildings.
The Contractor's forces started work on this building on January 10, 1959, at which time there were at least fifty (50) employes holding seniority in the B&B department who were in a furloughed status due to force reductions on the Pueblo Division (where the subject work was performed).
The instant claim was timely and properly presented and progressed on the property and was declined at each and every stage of handling, with the only excuse given by each Carrier officer for his respective declination of the claim being the statement that the subject work represented "new construction" with the inference that new construction work is not encompassed within the scope of the Agreement.
and obviously, if under the existing agreement Carrier did not have the right, to contract out certain work, there would be no need for the employes to seek the inclusion of the rule above quoted in the current agreement. See Third Division Awards 213, 507, 887, 1257, 1397, 2326, 2436, 3727 and 4349.
The Employes may contend as in numerous cases that have been appealed to your Board in the past, all of which have been denied to date, that they have performed certain parts of the work that was necessary to be performed under the contract in question. There are many technical and mechanical items of construction in this contract which B&B employes have never performed and it has been consistently held by the Third Division that work contracted out may not be subdivided for the purpose of determining whether some part could be performed by employes of the Carrier. See Third Division Awards 3206, 4776, 4954, 5304 and 5563 enunciating this principle.
OPINION OF BOARD: Under date of December 22, 1958, a contract was made by and between the Carrier and Edward Tamminga of Denver, Colorado, a building contractor, for furnishing labor and materials for the construction of a 26 ft. x 120 ft. paint shop with a 40 ft. x 12 ft. addition and a 26 ft. x 60 ft. stencil shed; trackage within said paint building; drainage of the immediate area; and all exterior utility lines; the said work including all general construction, plumbing, heating, ventilating and electrical work, with the exception that railroad forces perform all track work to 6 feet outside the building limits.
Further, the Carrier contracted with the DeVilbiss Company for installation of a traveling spray painting booth, exhaust duct work, exhaust stack and installation of machinery for handling disposal of paint spray. The contract with Tamminga amounted to $57,650 which included in addition to the building: the electrical work, the sheet metal work, plumbing, heating and ventilating, which items alone amounted to $14,000. The DeVilbiss contract was for $43,360 for their portion of the contract, making a total contract of over $101,000. This building, extensions and technical machinery, ventilation, etc., was of such magnitude as to require approximately nine months to complete.
Claim was made by the Brotherhood of Maintenance of Way Employes for seven named claimants who were at that time employed on the B&B gang for straight time rate for an equal proportionate share of the total number of man hours consumed by Contractor Tamminga's forces in constructing the buildings described.
The Organization submitted a series of photographs designed to demonstrate that the building in question, while it consists of new construction, is not beyond the capacity of the B&B employes to perform as contrasted with other work done by these men in the past and, since only B&B employes are covered by the Agreement of the parties, to have assigned the work to other employes not covered by the contract represents a violation of the Scope Rule of the Agreement.
The Scope Rule in the instant case nowhere sets forth the class or character of work employes are to perform. Nor is there any provision elsewhere in the Agreement explicitly indicating that the maintenance of way employes have a contractual right to perform the work claimed herein. The Carrier's practice of more than 42 years in contracting similar construction, all set forth on page 30 of Third Division Award 6549 on this property, 12632-16
demonstrates a consistent past practice where new construction is involved. The instant matter concerns a new paint shop which was entirely new construction.
It is significant to point out that the practice of contracting out work of magnitude was the usual procedure when the employes negotiated the present Agreement, effective February 1, 1941. There was no request from the Organization at that time to extend the Scope Rule to guarantee use of maintenance forces to perform heavy construction. On May 22, 1957 the Organization served a Section 6 Notice on the Carrier to revise the existing agreement to add the following rule:
"RULE I%-CONTRACTING OF MAINTENANCE OF WAY
AND STRUCTURES WORK
The record is silent as to whether this proposal was agreed to and included in the current Agreement. There is no such Rule included on pages 10-12 of Rule 9 in the Agreement. Nor does such additional Rule appear in Supplement E, Rule 9 (f) or elsewhere in the said Agreement, and the above quoted language does not appear in the Scope Rule.
It would seem clear that if the Organization thought its Agreement precluded the Carrier from contracting out heavy construction work and thereby giving work to employes not covered by the Seniority provisions of the Agreement, there would be no reason to seek a new Rule giving them this protection. See Third Division Awards 4259, 8538 and 11878 which hold, inter alia, that:
For a dispositive statement of the principles which govern the instant case, the Board cites with approval Award No. 8538 (Coburn) where, in an analogous set of circumstances, we held as follows:
The Carrier does not deny that there were certain parts of the work involved in this entire project which could have been performed by its Bridge and Building employes. But there were so many technical and mechanical items of construction which Bridge and Building employes have never performed that it would have been impractical to subdivide the project for purpose of allocating to these employes that part of the work they were capable of handling. This Board has many times held that if a Carrier has the right to contract "new" construction work, the work need not be subdivided for the purpose of determining whether some part could be performed by employes of the Carrier. See Awards 3206, 4776, 4954, 5304 and 5563.
The Carrier recites in its submission the pracise dimensions of the buildings and an itemization of the work that was contracted out and the cost of the contracts, plus the further fact that the work contemplated was of such magnitude as to require approximately nine months to complete.
FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and