PARTIES TO DISPUTE:
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
SEABOARD AIR LINE RAILROAD COMPANY

STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:




EMPLOYES' STATEMENT OF FACTS: On or about April 5, 1959,. the Carrier placed into operation a new Rail Welding Plant at its Old Savannah Yard, Savannah, Georgia, for the purpose of welding rails into continuous lengths.


Up until May 8, 1959, Claimant C. E. Tucker, who has established and holds seniority in the Track Sub-department, and who was assigned to the position of Extra Gang Foreman in that Sub-department, supervised and' directed the work of Track Laborers in the performance of rail-handling work at this facility.


Effective as of May 8, 1959, the Track Laborers, together with the rail handling work, were arbitrarily removed from the claimant's supervision and jurisdiction and were thereafter assigned to the supervision and jurisdiction of the welding Sub-department Foreman. Effective as of May 11, 1959, the claimant's Extra Gang Foreman's position was abolished and the claimant was returned to the position of Apprentice Foreman as will be noted from. the following:



13838-15 53

welding plant incidental to it being welded into ribbon rail and to carry the time worked by them.

OPINION OF BOARD: In the handling of the dispute on the property and in its submission to this Board the Carrier took the position that the claim had not been handled in accordance with the requirements of Article V of the Agreement of August 21, 1954. That issue was referred to the National Disputes Committee established by Memorandum Agreement dated May 31, 1963, to decide disputes involving interpretation or application of certain stated provisions of specified National Non-operating Employee Agreements. On March 17, 1965, that Committee rendered the following Findings and Desision (NDC Decision 8):










Proceeding now to the merits of the claim, the following facts are deemed material and relevant:
13838-16 54

Early in 1959 facilities were constructed by the Carrier at Savannah, Georgia for the welding of rail into continuous lengths; what is comomnly referred to as "ribbon rail." An extra gang in charge of Foreman C. E. Tucker, the Claimant herein, performed the necessary track work in constructing the plant. The construction work was completed on May 7, 1959, whereupon the extra gang was cut off and Claimant reverted to his position of Apprentice Track Foreman on May 8.


When the welding plant was placed in operation, this being a new process on this Carrier, two welding gangs were organized to do the work, on two shifts, the gangs consisting of foremen, welders, welder helpers, and laborers to handle the rail from storage tables or racks on rollers to and from the points or stations where the rail was heated, welded and cut. Laborers cut off with the extra gang on May 7 were assigned to the welding gangs, under the supervision of the welding foremen, beginning May 8 and remaining until July 9, 1959, when the rail welding operations were completed and the gangs cut off.


Employes contend that an extra gang foreman should have been placed in charge of the laborers.


Carrier asserts that the work performed by the laborers at the welding plant "was an integral part of the welding operations" which were under the supervision of a welding foreman, and that there was no need for or an agreement rule requiring the use of a gang or track foreman to supervise the aforesaid work.


Rule 1 of the Agreement is the Scope Rule and lists the classifications of "Extra Gang Foremen" and "Laborers" within the Sub-department titled "Track". As we understand the Employes' position, it is, in effect, that by reason of the inclusion of these classifications within the same sub-department, no one other than foremen so listed therein may properly be used to supervise any work performed by such laborers.


The Board has heretofore ruled on claims similarly grounded. In Award 4992 (Referee Carter) we said:



Again in Award 6705 (Referee Donaldson) the Board, in denying a claim that a painter foreman should have been used when painters were assigned to work under the supervision of a B&B foreman, held:



13838-17 55



The issue here raised appears to have been settled by prior Board rulings. There is nothing in evidence here which would compel the reversal of these well-reasoned and sound decisions. Accordingly, the claim will be denied.

FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:

That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 2.1, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and





    Claim denied.


              NATIONAL RAILROAD ADJUSTMENT BOARD By Order of THIRD DIVISION


              ATTEST: S. H. Schulty

              Executive Secretary


Dated at Chicago, Illinois, this 17th day of September 1965.