PARTIES TO DISPUTE:
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
UNION PACIFIC RAILROAD COMPANY

STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:






EMPLOYES' STATEMENT OF FACTS: Commencing on or about September 3, 1983, the Carrier, without benefit of negotiations with or the concurrence of the employes' authorized representatives, assigned the work of repairing the roof on the roundhouse at Green River, Wyoming to the P. K. Roofing Company of Rock Springs, Wyoming.


The work consisted mainly of renewing the roofing on a portion of the subject roof. The work was completed on or about September 20, 1983.


This work was of the nature and character that has heretofore been assigned to and performed by the Carrier's Bridge and Building Department employes.


The claimants were available, willing and fully qualified and could have efficiently and expeditiously performed the work here involved, had the Carrier so desired.


The Agreement in effect between the two parties to this dispute dated May 1, 1958, together with supplements, amendments and interpretations thereto, is by reference made a part of this Statement of Facts.

14061-20 613

handled by the private contractor. At the time the work was performed by the private contractor all B&B employes on the roster were working and the roster was completely exhausted. There were thus no employes "available to perform such work" within the meaning of the letter agreement, and Carrier was clearly entitled under the provisions and intent of that agreement to have such work performed by private contractor in accordance with the established and long accepted practice.


The letter agreement recognizes and confirms the right of the Carrier to contract any of its work to the extent it had previously done so during normal peacetime periods. This particular work of renovating a roof was that type of work which, both prior and subsequent to that letter agreement, the Carrier had assigned to private contractors. In addition, the letter agreement only restricts the use of contractors to perform "maintenance work" where regular Company forces are available. The regular Company forces were not available in this case. They were all fully employed during this period and were being utilized to perform other usual and necessary work. Neither the Claimants nor any other employe suffered any loss whatsoever by reason of this work being performed by a private contractor. Under these circumstances, the performance of this work by a private contractor was fully in compliance with the provisions and intent of the letter agreement of November 18, 2943, and the claim of alleged contract violation is entirely without foundation. The claims are without merit and should be denied.




OPINION OF BOARD: Carrier, about September 3, 1963, contracted out repair of the roof of its roundhouse at Green River, Wyoming. The work, according to Carrier, involved approximately 20,000 square feet of roof and consisted of "tearing off of the old roofing to the sheathing, replacement of layer of 15 lb. felt, installation of new gravel top, mopping of two layers of 25 lb. felt, then mopping of 2 layer of 65 lb. cap sheet, and, finally, a brushing with aluminum coating." The Organization alleges that the Agreement reserved this work to B&B Carpenters.


Carrier's given reasons for declination of the Claim, on the property, were consistent at each stage in the usual handling on the property. The chief operating officer of Carrier designated to handle the dispute set them forth in a letter, herein called Carrier's Position, to the organization which, in pertinent part, reads:



14061-21 614


















There is no evidence of an unforeseen or unforeseeable need to repair or replace the roofing material. Carrier admits the "project had been deferred for a considerable time account it was felt would not require immediate attention." This admission rules out a defense of emergency.
14061-22 615

We are not concerned with Carrier's auditing, disbursement, and budgeting procedures. They have no bearing on Carrier's obligations to comply with the Collective Bargaining Agreement.


Carrier adduced no evidence to prove "the possibility of sudden complete failure of the roof." Its own description of the work performed belies any structural failure of the roof.


Carrier's assertion that "the company was within its rights to contract this work which was done under normal conditions", fails for lack of proof' in the record as made on the property.




We are not confronted with interpretation and application of a Scope Rule general in nature. The Claim is founded on an alleged breach of the Agreement effective May I, 1958. Rule 3 of the Agreement specifically grants, work of the nature here involved, as follows:



Usual defenses to failure to comply with such a grant are: (1) emergency; (2) lack of skills; (3) lack of special tools and equipment; (4) size of the project not within the contemplation of the parties at the time of execution of the Agreement; and (5) lack of manpower. Of these, only the last one is a probable defense in this case. We consider it, infra.




Carrier cites Award No. 8184 as being dispositive of the issue raised in the instant Claim. In that case "The Organization took the position that the erection, and painting of the addition to the building was of the type that was contemplated by the Scope Rule of the efective agreement, and as such, to be performed by the employes covered thereby. It was asserted that the work was of a nature that had historically and traditionally been performed by Maintenance of Way forces." It was concluded in the Opinion in that Award that:


"The Scope Rule of this agreement is a general one; it does not enumerate the work covered thereby. However, we are confronted with a special understanding between the parties which concerns the right of this Carrier to assign construction work to others than those covered by the effective Agreement. This Memorandum of Understanding was entered into on November 18, 2943, and among other things contained the following provisions:



14061-23


The alleged violation in Award No. 8184 occurred in October and November, 1953. The Agreement there involved was effective September 1, 1949. The Agreement involved in the instant case became effective May 1, 1958. While both Agreements have appended the Memorandum of Understanding dated November 18, 1943, its force and effect have been diminished by the 1958 Agreement.


In Award No. 8184 we were confronted with interpretation and application of a Scope Rule, general in nature. Not so here, for in the 2958 Agreement a specific grant of the work here involved was agreed to in Rule 3, Note 9, supra. This specific grant prevails over the Scope Rule and the 1943 Memorandum of Understanding. It is an elementary principle of contract construction that a later agreement between the same parties prevails in variances with an earlier but continuing agreement.


Even assuming the interpretation that Carrier would give to the 1943 Memorandum of Understanding, Carrier fails to merit its application inasmuch as it did not prove, in the record made on the property, its affirmative defense of "normal conditions."


We find no aid to adjudication of the instant case in Awards Nos. 21 and 23 of Special Board of Adjustment No. 313.




Carrier has not controverted that Claimants herein-B&B Carpenterswould have performed the work involved if it had been done by its employes. Its defenses are: (1) "all B&B employes were working;" (2) "all of the B&B forces were on maintenance and repair work as well as work order projects that were just as important and necessary to handle to completion;" (3) "the company was within its rights to contract this work which was done under normal conditions;" and (4) Claimants were not available and suffered no loss of wages. The Organization admits the averment in (1). Two and three are affirmative defenses which were put to issue by the Organization. As we have repeatedly held, controverted assertions are not evidence-they have no probative value. The burden of proving defenses (2) and (3) was Carrier's. In this it failed. We, therefore, find wanting affirmative defenses (2) and (3) for lack of proof.


It is not enough for Carrier to assert that Claimants were not available to perform the work contracted out because they "were on maintenance and repair work as well as work order projects that were just as important and necessary to handle to completion;" because, this assertion was also put in issue by the Organization. The Organization averred that Carrier, without detriment, could have scheduled the work so as to be performed by Claimants. Here, again, Carrier failed to satisfy its burden of proof.

14061-24 617

Because of the nature of the work involved and Carrier's admission that "project had been deferred for a considerable time account it was felt would not require immediate attention", we find, in the light of the evidence properly before us, that acumen on the part of Carrier would have permitted it to schedule the work for performance by Claimants. Its failure to do :;o violated the Agreement and resulted in Claimants being damaged as alleged in the Claim.




For the foregoing reasons we find that Carrier violated the Agreement as alleged in paragraph (1) of the Claim; and, the prayer for a monetary Award, in paragraph (2) of the Claim, is sustainable as damages. We will sustain the Claim.


FINDINGS: The Third Division of the Adjustment Board, upon the whose record and all the evidence, finds and holds:




That the Carrier and the Employes involved in this dispute are respeetively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;


That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and












Dated at Chicago, Illinois, this 22nd day of December 1965.