NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
(Supplemental)
Don Harr, Referee
PARTIES TO DISPUTE:
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
LOUISVILLE AND NASHVILLE RAILROAD COMPANY
STATEMENT OF CLAIM: Claim of the System Committee of the
Brotherhood that:
(1) The Carrier violated the Agreement when it assigned the
work of grading and of building two (2) new bridges on the new
branch line near Cumberland, Kentucky to other than its Bridge and
Building subdepartment forces. (Carrier's file E-201-4 E-201)
(2) That the following quoted claim as presented under date
of October 30, 1962, be allowed. "Claim is made on behalf of the
following named employes in the class concerned, with seniority in
each class shown, that they each be paid an equal proportionate
share of the total man hours consumed by employes of the Codell
Construction Company, a contractor who is assigned the work of
grading and the building of bridges on the new branch line near
Cumberland, Kentucky:
Name Rank
4 Rank 5 Rank 6
M. C. Herber -Foreman 4-20-46 3- 4-42 10-21-36
Chester Miracle-Carpenter 12-24-53 8-20-48 7-28-48
P. H. Greer-Carpenter 3-23-54 10- 8-48 1-13-47
Eugene Frazier -Carpenter 7-26-57 1-10-49 1-10-49
J. V. Hall-Carpenter 5- 7-51 10- 7-46
David Hurst -Helper 1- 5-54 10- 6-52
Kenneth Jones-Helper 2-15-54 6-22-53
D. W. Parks-Helper 3-23-54 9-17-51
R. E. Rowlett -Helper 5-3-54 8- 3-53
M. R. Helton -Laborer 5-26-52
Oscar Abner -Laborer 2-16-53
M. D. Britton -Laborer 3-21-53
H. Wilson-Laborer 1-27-54
M. H. Miracle-Laborer 2- 2-54
Arnold Estep-Laborer 5-11-54
[8537
14122-2 854
The above named employes, with one or two exceptions, were
cut off in force reduction or working in a lower class than their
seniority entitled them to work in and thus their rights have been
violated under the rules of the current Agreement, effective May 1,
1960 as revised and amended, and each claimant should be made
whole insofar as pay, vacation rights, Health and Welfare benefits
or other benefits are concerned."
EMPLOYES' STATEMENT OF FACTS:
When the General Chairman
learned that the Carrier had assigned the work of constructing two (2) bridges
on the new branch line near Cumberland, Kentucky to employes of the CodellOman Construction Company, who hold no seniority rights under the Agreement, he wrote to the Carrier's highest appellate officer on September 28,
1962 and again on October 3, 1962, urging the Carrier to assign the work to
the claimants. When the General Chairman did not receive a reply to either of
said
letters, he
presented the subject claim to the Carrier's Division Engineer,
wherein he set forth the facts in the case as follows:
"The contractor's forces built one bridge approximately 6 miles
from Cumberland, Kentucky, finishing that bridge on or about October
16, 1962. This bridge, which is a three span steel bridge, is supported
by two poured concrete abutments approximately 2 feet by 12 feet by
18 feet and two concrete piers approximately 4 feet by 15 feet by 18
feet. The Contractor's forces built the piers and abutments and
set the steel spans thereon, however, B&B Department employes are
scheduled to place the deck, that is, the supporting timbers for the
track, on the bridge.
The second bridge built by the contractor's forces is located
approximately 7s/a miles from Cumberland, Kentucky, and will be
about the same, if not exactly like, the bridge described above.
Claimant M. C. Herber does not hold seniority as B&B Foreman,
but is fully qualified for such work and has done quite a bit of
relief work in the foreman's class due to vacations, sickness, etc.
There is no reason why employes named herein could not have
performed the work in question because machines and other equipment were readily available and could have performed all of the
work, including the setting of the spans on these bridges.
The spans involved are approximately 10
feet by
25 feet (2
spans) and 10 feet by 37 feet (1 span).
It cannot be argued that equipment belonging to the railroad
company could not have gotten to the site of these bridges simply for
the reason that the contractor succeeded in getting his equipment
there for use on the bridges and the same would follow insofar as
the equipment belonging to the railroad is concerned.
The railroad company has concrete mixers of sufficient capacity
to have mixed the concrete for the pouring of the piers and abutments and they have cranes of suffcient capacity to fill the forms
needed for the pouring of such piers and abutments."
Claim was timely and properly presented and handled at all stages of
appeal up to and including the Carrier's highest appellate officer.
14122-15
$67
Without in any way prejudicing its position, carrier submits that that
portion of Section 2 of employes' claim pertaining to Health, Welfare benefits,
vacation rights, and other benefits are concerned should be disregarded as it
is not within the jurisdiction of the Railroad Adjustment Board.
In view of the circumstances as set forth in the foregoing, carrier asserts
the claim is without merit and should be denied.
OPINION OF BOARD: In January, 1962, Carrier contracted with CodellOman, Contractors, for the construction of a roadbed and drainage structures
which included bridges for an industrial spur track on Carrier's Cumberland
Valley Division.
The Employes protested the contractor building the bridges and doing
the grading in connection therewith, alleging that such work should have been
performed by employes in Carrier's Bridge and Building Subdepartment.
Claim was properly presented, on behalf of the named employes, and
appealed up to the Carrier's highest appellate officer.
The Carrier takes the position that the Agreement permits the contracting out of work and that it has been their practice, over a period of years, to do
so. In their submission they state that this Board has denied similar claims.
Carrier contends that the exception contained in Rule 2(f) is applicable
in this case. Rule 2(f) provides:
"RULE 2.
EXCEPTIONS TO RULE 1
2(f) The railroad company may contract work when it does not
have adequate equipment laid up and forces laid off, sufficient both
in number and skill, with which the work may be done."
The dispute in this case is whether or not the Carrier had ". . adequate
equipment laid up and forces laid off . . ." The Carrier states it could not meet
these conditions and the Employes attempt to prove that they could.
We have carefully reviewed the records in three previous cases involving
the same parties and rules. Awards 11085 (Boyd), 11289 (McMahon) and
13979 (Williams). In each of these awards the Board denied the Employe's
claim.
We can find no substantial difference between these previous cases and
the case at bar. The Board in these prior awards found that the record contained
probative evidence presented by the Carrier to sustain it's position. The
evidence contained in the record here is similar.
We feel that the Carrier under the provisions of Rule 2(f) was entitled
to contract this work. We will deny the claim.
FINDINGS: The Third Division of the Adjustment Board, after giving
the parties to this dispute due notice of hearing thereon, and upon the whole
record and all the evidence, finds and holds:
14122-16
868
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
AWARD
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of THIRD DIVISION
ATTEST: S. H. Schulty
Executive Secretary
Dated at Chicago, Illinois, this 26th day of January 1966.