® sea
Award No. 14297
Docket No. MW-12090
NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
(Supplemental)
G. Dan Rambo, Referee
PARTIES TO DISPUTE:
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
CHICAGO, BURLINGTON & QUINCY RAILROAD COMPANY
STATEMENT OF CLAIM:
Claim of the System Committee of the
Brotherhood that:
(1) The Carrier violated the effective Agreement when, on
or about January 1, 11959, it assigned the work of constructing a
new Depot Building, a new Service Building and the remodeling and
repair of the Mill Building, together with other work incidental
thereto, including the construction of the necessary drive-ways and
platforms at St. Joseph, Missouri, to a General Contractor whose
employes hold no seniority rights under the provisions of this Agreement.
(2) The employes holding seniority in Groups 2, 3 and 4 of
the Bridge and Building Sub-department and Group 1 of the Roadway Equipment Machines Sub-department on the territory where the
work was performed each be allowed pay at his respective straight
time rate for an equal proportionate share of the total man-hours
consumed by the Contractar's forces in performing the work referred to in Part (1) of this claim, retroactive to sixty days from
June 27, 1959.
EMPLOYES' STATEMENT OF FACTS:
On or about January 1, 1959,
the Carrier assigned ,the Thomas Construction Company, whose employes
hold no seniority rights under the provisions of this Agreement, to perform
Maintenance of Way and Structures Department work at St. Joseph, Missouri.
Specifically, the work consisted of
(1) The construction of a brick and stone depot building, 40
feet in width by 80 feet in length, and other work incidental thereto.
(2) The construction of a brick and stone service building,
20 feet in width by 80 feet in length, and other work incidental
thereto.
the work was started, and 12 days after this large project was completed.
The claim was declined at all stages of handling on the property on the basis
of the procedural defects involved on the part of Petitioner, and on the complete lack of contractual support.
The schedule of rules agreement between the parties, effective September
1, 1949, and amendments thereto including the August 21, 1954 Agreement
and Mediation Agreement A-5987, effective December 1959, are by reference
made a part of this submission.
OPINION OF BOARD:
This claim arose from the assignment of the
work of constructing a new Depot Building, a new Service Building, and the
remodeling and repair of the Mill Building and other work incidental thereto
at St. Joseph, Missouri to a contractor whose employes were not covered
by the Agreement.
The same or similar issues presented in the instant claim involving the
identical parties and on the same property have been before this Board on
several occasions and have been thoroughly discussed in the Awards. See
Awards 7600, 10937, 11716, 13638 and 14207. A further discussion here
would be repetitious.
The foregoing awards have established a definite pattern and precedent
on this property. We can find no substantial difference between these previous claims and the claim at bar. Therefore, we hold that the Agreement
was not violated.
FINDINGS: The Third Division of the Adjustment Board, after giving
the parties to this dispute due notice of hearing thereon, an,'' upon the whole
record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the:
dispute involved herein; and
That .the Agreement has not been violated.
AWARD
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOAR]>
By Order of THIRD DIVISION
ATTEST: S. H. Schulty
Executive Secretary
Dated at Chicago, Illinois, this 31st day of March 1966.
Keenan Printing Co., Chicago, Ill. Printed in U. S. A_
14297 3