The lining operation outlined above completely removes the machine from the left rail thereby breaking the shunt circuit. Then, on completion of the lining operation the reverse sequence lowers the wheels and places the track liner back on the rails, again completing the shunt circuit. Since the lining sequence requires less than a minute to complete, as previously shown, and the machine lines 11,000 to 2,000 feet of track per hour, each time the track liner is spotted and operated to align the track, the shunt circuit is broken and the coding equipment is activated.
4. The frequent breaking of the shunt circuit due to the normal operation of the track liner creates unnecesary operation of the coding machines, and in order to prevent such useless overworking of said machines, the track force was required to place a shunt (a wire with set_screw clamps at each end to enable the wire to be secured to the rails to make an electrical circuit) on the track circuit in which the machine was operating.
5. Members of the track force were not required to nor did they at any time make any test to determine whether the shunt functioned properly, because the only result that would have obtained from an imperfect shunt would have been the unnecessary and useless working of the coding machines. Signalmen have never placed shunts in these circumstances.
6. Correspondence which passed between the Local Chairman and carrier's Division officers in connection with this claim is reproduced as Cardier's Exhibit "A"; and correspondence passing between the General Chairman and carrier's Assistant Manager of Personnel is reproduced as Carrier's Exhibit "B".
OPINION OF BOARD: This controversy arises from the shunting of track circuits by Track Department employes instead of signalmen while operating a track liner during specified days in November 1959. The question for determinaton is whether the placing of a temporary shunt on a track circuit while a track liner is in operation constitutes signal work within the scope of controlling Agreement between the Carrier and Employes of the Signal Department. Maintenance of Way employes placed temporary shunt wires between the rails by fastening the wire to the base of each rail with a set screw attached to the shunt, thereby preventing intermittent signal changes.
The Organization claims this is work belonging to Signalmen under the °'Scope Rule" of their Agreement. Organization contends that the sole purpose of the shunt was to protect the signal system during the operation of the track liner and that this class ~of work is clearly reserved to Signal Department employes under the Agreement and applicable Awards of this Board. (Award 3688)
In .the first instance, Carrier contends that the claim should be dismissed because it is vague and indefinite and further that proper notice was not given to a necessary and interested party, the Brotherhood of Maintenance of Way Employes. The record discloses that Carrier failed to object to the indefiniteness of the claim while the dispute was considered on the property
and .the Board has no authority to consider new matters. Moreover, the record contains probative evidence clearly showing that the dispute was properly brought to the attention of all interested parties, including the Maintenance of Way Employes. Therefore, we find these contentions without merit.
With respect to the merits of the dispute, Carrier contends that the placing of a temporary shunt on a track circuit during machinery operation does not constitute signal work falling within the scope of the controlling Agreement to be performed exclusively by employes in classes within the Signal Department. Carrier asserts that the placing of temporary shunts on rails in conjunction with machinery work on the track or rails has never been recognized as being the exclusive work of signalmen and that the practice of applying shunts by employes other than signalmen antedates the controlling Agreement. The Scope Rule in the Agreement before us reads:
It is clear that the application of temporary shunts in the instant dispute was an adjunct to the work being performed with machinery by track employes. Shunts were used to prevent the intermittent changing of signals during the operation of machinery. In fact, the shunt cord supplemented the shunt partly provided by the machines themselves. Necessary precautions for protecting roadway machines against train movements were accomplished by other means such as placing switches in hand-throw positions at both ends of the working limits and obtaining clearance from the dispatcher. Therefore, it is evident that the disputed work is not encompassed with the specific criteria of the Scope Rule and the burden is upon the Organization to show through probative evidence that such work is generally recognized as signal work.
(The Organization asserts that the disputed work was necessary to protect the signal equipment and that the purpose of the work performed falls within the province of the signalmen. Organization has offered in evidence the Carrier's Operating Rules do support of its position but has failed to present any evidence concerning their application by the Carrier which would support the instant claim. Specifically, the Organization has failed to prove that Carrier interpreted its miss in the same manner as the Organization suggests is proper.
No other evidence was offered by the Organization in support of its contention that the temporary shunting in issue had been recognized as being the exclusive work of signalmen throughout Carrier's property and the
Carrier has denied such exclusiveness. Moreover, the Organization has not denied Carrier's assertions that other employes have normally performed such work.
A careful analysis of the Awards cited by the parties convinces us that Awards 5428 and 11595 are relevant and controlling in this case. The application of temporary shunts was merely an adjunct to the operation of a machine performing maintenance work and the Organization has failed to show through "tradition, custom and practice" the work involved belonged exclusively to ,them.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and