NATIONAL RAILROAD ADJUSTMENT BOARD

THIRD DIVISION

(Supplemental)




PARTIES TO DISPUTE:


STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:





EMPLOYES' STATEMENT OF FACTS: From September 17 through October 9, 1964 and on October 20, 1964, employes of the Ellard Construction Company, who hold no seniority rights under the Agreement, were assigned to perform paving work and to grade for, move, straighten and lower track near the passenger station at Athens, Alabama. In the performance of this work, the contractor's forces used equipment similar to that which the Carrier owned and had available, i.e., bullgraders, a dragline, end loaders and dump trucks.


The claimants were cut off employes on the seniority district where the subject work was performed. They were available and fully qualified to perform all of the subject work, and would have done so if the Carrier had assigned them to it.


Claim was timely and properly presented and handled at all stages of appeal, up to and including the Carrier's highest appellate officer.

and it was declined by the Director of Personnel on December 14, 1964, by the following letter:

"LOUISVILLE AND NASHVILLE RAILROAD COMPANY

Office of Director of Personnel

Louisville, Kentucky






    Mr. W. P. Gattis, General Chairman Brotherhood of Maintenance of Way Employes Nashville, Tennessee


    Dear Sir:


    Your letter of December 8, concerning claim of C. M. Atwell, J. D. Clement, B. A. Franklin and E. E. Hodges that they be paid for the work performed by Ellard Construction Company, Athens, Alabama, between September 17 through October 9, inclusive, and October 20, 1964, while engaged in grading and paving in connection with lowering tracks near the passenger station.


    In handling this matter with the Chief Engineer, we have been furnished with a copy of his letter to you dated December 3, 1964; and, in view of the circumstances as outlined therein, we see no basis for the claim, and it is, therefore, respectfully declined.


    We shall, however, be glad to discuss this matter with you at our next conference if you so desire.


                      Yours truly,


                        /s/ W. S. Scholl

                        Director of Personnel"


The claim was then discussed in conference on February 25, 1965, at which time it was again declined, and nothing further was heard from the claim until notice was received from the Board of employes' intention to file ex parts submission.

OPINION OF BOARD: From September 17 through October 9, 1964 and on October 20, 1964, Carrier contracted with Ellard Construction Company to perform paving work and to grade for, move, straighten and lower track near the passenger station at Athens, Alabama.

The Employes protested the contractor performing this work, alleging that Claimants and equipment were available to have performed all the subject work if 'Carrier had so assigned them to it.

Carrier takes the position that the Agreement permits the contracting out of work, and that it has been this practice over a period of years to do so. Carrier contends that the exception contained in Rule 2 (f) is applicable in this case.

14967 6
    Rule 2 (f) is applicable in this case. Rule 2 (f) provides:


    "2 (f) The railroad company may contract work when it does not have adequate equipment laid up and forces laid off, sufficient both in number and skill, with which the work may be done."


The issue, as we see it, is similar to the issue that was disposed of by Awards 11085 (Boyd), 11289 (McMahon), 13979 (Williams), 14122 (Harr) and 14820 (Lynch), involving these same parties.

    They were denial awards.


We can find no substantial difference between these previous cases and the instant case.

    Therefore, we will deny the Claim.


FINDINGS: The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds and holds:

    That the parties waived oral hearing;


That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;


That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and

    That the Agreement was not violated.

                AWARD

    Claim denied.


              NATIONAL RAILROAD ADJUSTMENT BOARD By Order of THIRD DIVISION


              ATTEST: S. H. Schulty

              Executive Secretary


Dated at Chicago, Illinois, this 30th day of November 1966.

Keenan Printing Co., Chicago, Ill. Printed in U.S.A.
14967 7