(1) The Carrier violated the Agreement when it assigned the work of removing the top of Lost Gap Tunnel to employes of a contractor who hold no seniority rights under the Agreement. (Carrier's File 134-241-444 Spl. Care No. 312 MofW.)
(2) Machine Operators A. C. Turman, B. M. Turman, R. L. Foreman, C. Parker, D. H. Davis, L. L. Hurst, C. L. Slade and K. L. Neese each be allowed pay at their respective straight time rate for an equal proportionate share of the total man-hours consumed by contractor's forces in performing the work referred to in Part (1) of this claim.
"'Lost Gap Tunnel,' said Roy L. Harwood, division engineer for the Mississippi Division,' is a long brick barrel built right through the middle of a hill'."
. After the bids were reviewed, the contract was awarded to Railroad Maintenance & Construction, Inc., of Irving Texas, as the lowest bidder.
The contractor's bulldozers, tractors and road scrapers began to arrive at Lost Gap early in September. All of the equipment, bought new for this job, came to the tunnel area over the Illinois Central rails from Springfield, Illinois. Les Hambrick, Vice-President of Railroad
The work on this project was started early in September and completed on November 20, 1963.
On October 8, 1963 the union filed a claim alleging violation of the agreement. The company declined the claim at each step of the appeal on the basis the work was properly let to a contractor. The agreement with the Brotherhood of Maintenance of Way Employes dated June 1, 1962 is by reference made a part of this Statement of Fact.
OPINION OF BOARD: The parties herein litigated a very similar claim before the Board which resulted in denial Award 11493. The basic contentions of the parties are the same in each case. We are persuaded that Award 11493 is proper and in point and should be followed in this case.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and