NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
(Supplemental)
THE CINCINNATI, NEW ORLEANS AND TEXAS PACIFIC
RAILWAY COMPANY
Carrier's signal forces installed signals and CTC on the approximately 25 miles of newly constructed track.
One of the grading contractors on the project was S. S. Purcell Jr. Company, Broadhead, Ky. Because of the heavy boulders and sharp rocks through cuts and on fills in the area between Tateville and Greenwood, it was decided that a specially designed armored CTC code cable should be installed in the ground for 15,000 feet to carry CTC circuits, which prior thereto were carried on pole lines, and to install conventional armored cable in the ground for the remaining distance of 33,000 feet. It was out of the question to even consider having the trench for the armored cable dug manually with picks and shovels, or even with any ditch digging machinery which Carrier owned. Furthermore the time in which the work bad to be performed was limited. In this situation Carrier contracted with S. S. Purcell Jr. Company to excavate a ditch approximately 12 inches wide, 18 inches deep and 10 feet west of the center line where track No. 2 would be located on the grade and through the cuts and over the fills between Tateville, Ky., milepost 170, Greenwood, Ky., milepost 179, for a distance of approximately 9 miles.
On December 27, 1962, the contractor began digging the trench for the armored cable with special heavy duty machines. The contractor used a heavy trenching machine. In some areas where the trenching machine could not be used a backhoe machine was used in removing the heavy boulders. Explosives were also used in blasting out some of the rock.
After the trench was dug Carrier's signal employes laid the armored cable in it. The contractor hauled dirt and screenings to the scene and distributed them. Carrier's signal forces shoveled in the trench on top of the cable as a cushion approximately 2 inches of dirt and screenings, after which the contractor's machines filled the trench covering the cable. The referred to work was completed in March 1963. This was long before train operations over the new track began.
The six construction projects were completed and the new line was opened for train operations in July 1963.
OPINION OF BOARD: Brotherhood complains of the subcontracting of the digging of a ditch and backfilling of it after installation by Brotherhood employes of 14,400 feet of signal cable. Carrier argues: 1. that the involved work does not belong exclusively to Brotherhood; 2. that the equipment needed was not possessed by it, and skills required were not available from its Brotherhood employes; and 3. that as a "larger installation in connection with new work" it was in any case excepted from coverage of the Scope Rule under the terms of the fourth paragraph of that Rule.
The whole job involved is described by Carrier without contradiction as follows:
Carrier's signal forces installed signals and CTC on the approximately 25 miles of newly constructed track.
Carrier's argument that digging and backfilling in connection with installation of the signals and CTC is not covered by and reserved to Brotherhood by the Agreement is wrong. We have held often that such "unskilled" work, when done as a necessary incident to the skilled signal work, is covered by the Agreement. (See Award No. 14371)
We are of the opinion, however, that Carrier has shown the necessary basis for an exception to to Scope Rule. The signal work part of the major project here was the installation of signals and CTC on approximately 25 miles of newly constructed track. On a project that large, particularly when such work was also required on other parts of the project, the excavating, ditch digging and backfilling is reasonably separable from the laying of cable and installation of the signals. And it is on the face of it a "large installation."
Since we find that fourth paragraph of the Scope Rule relieved Carrier of its obligation to assign the involved work to its Brotherhood employes, we need not deal with the argument as to whether the skills and equipment availability warranted the contracting out in this case.
FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and