THIRD DIVISION
(Supplemental)
On March 25, 1966, the Director of Labor Relations replied to the General Chairman's letter as follows:
OPINION OF BOARD: This is another in the series of similar issues between these parties which have been before the Board. In a number of Awards (e.g., 11733, 132'36, 15689, 15874, 15888), the Board has held that work of this kind could and should have been performed by Carrier's own employes, since it was not a large installation "in connection with new work," which would exempt it from the prohibition on contracting under the Scope Rule.
Carrier contends that the work was performed by authority of the Light, Gas and Water Division of the City of Memphis, "under the laws and regulations of the State of Tennessee," and was at the expense of that Division. However this does not meet the other exemption from the Scope Rule, which applies to "smaller installations if required under provisions of State or Federal law or regulations." There is no evidence that the State of Tennessee required performance of this work.
Although the claim was originally filed on August 7, 1965, on behalf of five named men plus others unnamed, it was revised on the property on September 10, 1965, to list 10 men. The original claim on the property had indicated that the others would be named later. It was so worded-"all men assigned to and working in his gang"-that they were readily identifiable. Hence it cannot be held that Carrier was not properly apprised of the claim on the property.
The claim charges that work which should have been assigned to Claimants was performed both by a contractor and also by "Tenn. Power Co.," beginning June 15, 1965. Carrier responded to the claim by stating that no work had been performed for it by "Tenn. Power Co.," but that the Light,
Gas and Water Division had relocated a section of Carrier's transmission line on May 10, 12, and 13. This statement was not rebutted, and that portion of the claim is therefore barred, since it concerns an occurrence more than 60 days before the date of the claim which was filed on August 7.
Carrier stated that the work of the contractor, Winsett-Simmons Engineers, Inc., was performed between July 20 and August 9. The number of man-hours involved is not known to the Organization, and its claim therefore is that Carrier be "required to review its records in cooperation with the Organization to determine the amount of work and time . " Since such information was not available to the Organization, its request for Carrier's assistance should be granted. Carrier violated the Agreement and the data necessary to establish the remedy should be furnished if it is beyond the ability of the Organization to obtain it.
One employe named in the claim, H. D. Fowler, was off duty due to sickness during the period involved, and therefore he is stricken from the list of employes to whom compensation is due.
FINDINGS: The 'Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:
That the Carrier and the Employe involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21,1934;
That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and
The parties shall ascertain from available records the number of manhours worked by emPloyes of Winsett-Simmons Engineers, Inc. on behalf of Carrier between July 20 and August 9, 1965, in the manner proposed in the claim. That number of hours shall be divided proportionately among Claimants (excluding H. D. Fowler), and each shall be paid at his straight-time rate for his proportionate number of such hours.