PARTIES TO DISPUTE:
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
NORTHERN PACIFIC RAILWAY COMPANY

STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:




EMPLOYES' STATEMENT OF FACTS: In conference on March 3, 1965, the Carrier's highest appellate officer sought the undersigned General Chairman's approval of the Carrier's proposal to assign the work of placing, leveling and grading fill material necessary in the construction of an extension of the passing track at Frenchtown, Montana, to a Contractor. Despite the General Chairman's non-concurrence, the Carrier did assign the aforementioned work to a Contractor who performed the work during the period from May 19, 1965 to June 5, 1965.


The Carrier owned several units of the grading equipment necessary for this work and the claimants are just a few of the many employes of the Carrier who are skilled in the operation of said machines.


Claim was timely and properly presented and handled by the Employes at all stages of appeal up to and including the Carrier's highest appellate officer.


The Agreement in effect between the two parties to this dispute dated December 1, 1962, together with supplements, amendments and interpretations thereto is by reference made a part of this Statement of Facts.


CARRIER'S STATEMENT OF FACTS: Frenchtown, Montana is located between Missoula and Paradise. A siding approximately 6,600 feet in

length is located at Frenchtown. In 1965 it became necessary to extend this siding approximately 6,000 feet in conjunction with the installation of a CTC system between Missoula and Frenchtown.


The construction of the extension to this siding necessitated the placement of approximately 9,300 cubic yards of material for the grade for the trackage. The Carrier did not have available in the immediate vicinity the material necessary for this grade. Consequently, a contract was entered into with an outside concern, under which contract the Carrier purchased in place the material for the grade for the siding extension. The contractor secured the embankment material from a pit located approximately one-half mile from the siding extension and placed this material in the area where the siding extension was to be constructed. The pit from which the contractor

secured the embankment material is located oft the property of the Railway Company.


The contractor consumed the following number of hours in placing the embankment material in the siding extension site:





All track work necessary in the extension of this siding was performed by Railway Company forces.



ment material at the siding extension site, Messrs. Worthington, Bowman, Kay and Carpenter were employed as follows:























diesel shovel operators, for payment of their proportionate share of 100 hours consumed by the contractor in loading the embankment material into trucks at the pit site.


16440 2






dumper truck operators, for payment of their proportfonate share of $00 hours consumed by the contractor in hauling the embankment material from the pit site to the siding extension site.









tractor operators, for payment of their proportionate share of 124 hours consumed by the contractor in leveling the embankment material at the siding extension site.

The Employes in their notice dated July 11, 1966 to Executive Secretary S. H. Schulty have appealed a claim in behalf of the following employes:







tractor operators, for payment of 24 hours each at straight time rate and 7 hours each at time and one-half rate, or a total of 124 hours, representing the number of hours consumed by the contractor in leveling the embankment material at the siding extension site.



OPINION OF BOARD: In order for Carrier to extend its siding at Frenchtown, Montana, approximately 9300 cubic yards of fill material was required. Because such material was not available on the property, Carrier purchased the material from an outside independent contractor. The contract included the loading, trucking, and leveling of the material at the site.

Petitioner alleges that Carrier violated its Agreement when it assigned the work of leveling and grading the fill material at the extension site to the independent contractors. No claim is made for the loading and trucking, as that was work performed off Carrier's property.

Two questions are presented in this dispute: 1) Was there an exclusive right on the part of the employes to perform the work involved in the claim by virtue of the general seniority rules and the Letter Agreement of September 12, 1962; and 2) If so, did Carrier nevertheless have the right to contract out the work because it was an integral component of a single agreement.

With respect to the first question, the general rule has been succinctly stated by Referee Ives in Award 14942:

16440 3


We must determine, therefore, whether the Letter Agreement of September 12, 1962, satisfies Petitioner's burden of proof.






While the language might be considered inartful and subject to different interpretations, the Board is satisfied that it constitutes recognition by both parties that construction of tracks, structures or facilities located on the Carrier's right of way is work reserved to the employes, and cannot be given to anyone else without further agreement or special circumstance. The burden of custom has thus been met by Petitioner. The Board further finds that leveling and grading is included in "construction."

We come next to the second question: Even if the work had been customarily performed by the employes, did the leveling and grading of the

16440 4

material constitute an integral component of the overall contract, thus freeing Carrier from its obligation to utilize the employes?


Carrier contends that the grading work was an "integral part of a contract the major portion of which consisted of work admittedly not covered by the agreement", and further contends that "Each phase of this work was a component part of the entire project of furnishing the embankment material for the siding extension. One component part of this project could not reasonably be dissociated from the entire project.


Carrier can prevail on this theory only if it is shown that the parts or phases of the work are so interrelated and dependent that a contract could not be entered into absent any one of the parts or phases. The word "integral" is defined in Webster's New Collegiate Dictionary as "Essential to completeness ' ' ' Lacking nothing of completeness; entire; ' ' '." It is clear that the leveling and grading of fill material on the property can easily be separated from the loading and trucking of such fill material.


FINDINGS: The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds and holds:



That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;


That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and








Dated at Chicago, Illinois, this 20th day of June 1968.

Keenan P-inting Co., Chicago, Ill. Printed in U.S.A
16440 5