.400-sss
Award No. 17061
Docket No. SG-17699
NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
(Supplemental)
Paul C. Dugan, Referee
PARTIES TO DISPUTE:
BROTHERHOOD OF RAILROAD SIGNALMEN
THE ATCHISON, TOPEKA & SANTA FE RAILWAY COMPANY
(Coast Lines)
STATEMENT OF CLAIM:
Claim of the General Committee of the
Brotherhood of Railroad Signalmen on the Atchison, Topeka and Santa Fe
Railway Company that:
(a) Carrier violated and continues to violate the Scope of
the current Signalmen's Agreement, as amended, when on or about
and subsequent to August 1, 1966, it contracted, farmed out, assigned and/or otherwise allotted work generally recognized as signal work on the Coast Lines to persons not covered by the Signalmen's Agreement.
(b) Carrier be required now to pay Signalman G. A. Cochran
and Signal Helpers H. M. Phifer and F. P. Schmitt at their respective pro rata rates for all hours worked by the Contractor's employes while constructing cement foundations and battery boxes
used in installations of the Signal Department of the Coast Lines
commencing on or about August 1, 1966, and continuing forward
until the violation of the Signalmen's Agreement is stopped.
(c) Carrier be required now to pay also Signal employes W. L.
Bennett, Bill James, and C. D. Millhouse at their respective pro rata
rates for all hours worked by the Contractor's employes while constructing cement foundations, battery boxes and appurtenances, and
cement products used in installations of the Signal Department of the
Coast Lines commencing on or about August 1, 1966, and continuing
forward until the violation of the Signalmen's Agreement is stopped.
(Carrier's File: 132-57-24.)
EMPLOYES' STATEMENT OF FACTS: On or about the year 1939
Carrier purchased and/or provided a cement mixer and all the necessary
cement forms to construct the Signal Department's concrete foundations and
battery boxes at the Signal Shop at San Bernardino, California, for the
Coast Lines. Signal employes assigned to the Signal Shop at that location
were assigned to construct the cement foundations and battery boxes for
use of the Coast Lines Signal Department, and Signal employes have per-
2-23-66 Log, cement anchors 6"x6"x48" 400 400 0
3-25-66 Black, anchors 6"x18" Concrete 15 15 0
1-13-66 Slab 25"x25"x6" Concrete for Flasher 250 153 97
Sig. Poles
2-23-66 Foundation
concrete for
Sheet Steel 80 80 0
instrument case 4'-0" high with
Anchor Bolts extension 5s/4" above
top with 2" thread and anchor
bolt spacing "A" 23/4"
2-23-66 Slab 25"x25"x6" Concrete for 125 0 125
Flasher Sig. Poles
2-23-66 Slab concrete 28"x34"x6" 40 40 0
2-23-66 Log, Cement Anchor 6"x6"x30" 250 250 0
4-14-66 Concrete Scanner Foundations 8 8 0
4-18-66 Foundation Concrete for Steel in- 50 16 34
strument case 4'-0" high with
Anchor Bolts extension 51/4 above
top with 2" thread and anchor
bolts spacing "A" 23/4" and "B"
18'/2 Plan F-207 Rev. 3/14/45
4-18-66 Slab 25"x25"x6" concrete for 100 0 100
flasher sig. Pole
(Exhibits not reproduced.)
OPINION OF BOARD:
The Organization claims that the Carrier violated the Agreement when on or about August 1, 1966, it contracted out the
work of making cement foundations and battery boxes to an outside contractor, Permacrete Products Corporation, South Holland, Illinois. The Organization contends that the work of making these prefabricated components for
the construction of concrete foundations and battery housings has always
been performed by signalmen for 27 years and that the work has generally been recognized as signal work as covered by the Scope Rule of the
Signalmen's Agreement.
Carrier's position in this dispute is that on past occasions Carrier has
purchased these items without complaint or claims being filed by the Organization; that Signal Department employes have not exclusively constructed
such cement foundations and battery boxes used in Signal Department construction.
The Organization's primary argument is that by past practice Signal
Department employes have performed the work in question. In support thereof,
the Organization submitted five statements from Signal Department employes stating that they constructed cement foundations and battery boxes
at San Bernardino for the past
twenty-seven years
. This contention is vigorously denied by Carrier, and in support of its refutation of said past practice contention by the Organization, Carrier presented as exhibits Requisition Stubs showing requests for said foundations which were from the
Massey Concrete Products Corporation, and this was as far back at 1949.
17061 7
Assuming that the Organization proved "exclusivity" to the work at
San Bernardino, California by the statements of signed department employes, which Carrier emphatically denies, nevertheless, the
Organization has
the burden of proving that such work has always been reserved to it systemwide.
Therefore, inasmuch as the Scope Rule is void of specific language clearly
showing an intent to assign the work in question exclusively to Signal
Department employes, and having failed to prove by custom, tradition and
past practice that such specific work has been exclusively reserved and performed system-wide by Signal Department employes, we must deny this
claim.
FINDINGS: The Third Division of the Adjustment Board, upon the
whole record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of THIRD DIVISION
ATTEST: S. H. Schulty
Executive Secretary
Dated at Chicago, Illinois, this 16th day of April 1969.
Keenan Printing Co., Chicago, Ill. Printed in U.S.A.
17061 8