PARTIES TO DISPUTE:



STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood of Railroad Signalmen on the Seaboard Coast Line Railroad Company that:

(a) Carrier violated the Signalmen's Agreement, particularly the Scope, when it required or permitted contractors' forces and/or employes other than those classified therein to perform recognized signal work covered by the scope of said agreement, making repairs to signal pole line and signal facilities damaged by ice storm in the Hamlet, N. C., area. Such work being performed on February 18, 19, 20, 21, 22, 23, and 24, 1969.


(b) Carrier pay signal employes listed or identified herein for all man hours contractors' forces and Carrier Electricians worked performing recognized signal work, or for 444 man hours on each date, February 18, 19, 20 and 21; 490 man hours on February 23, 1969. Claimants to be paid a total of 2266 man hours on a prorated basis at their respective overtime rates of pay in addition to any compensation already received. Claimants are as follows: All signal employes in Hamlet Signal Shop, including Foreman R. M. Adams, CTC Inspector B. S. McGirt, Signalmen J. E. Graham and J. McDaniel, Assistant Signalmen P. R. Eubanks and J. H. Rice, Signal Helper A. F. Anderson; Signal Maintainer J. F. Power and Assistant Signal Maintainer Edward Hodge, Hamlet, N. C.; Signal Maintainer W. H. Robinson, Aberdeen, N. C.; Signal Maintainer J. R. Lockamy, Sanford, N. C.; All signal employes assigned to signal gang No, 6, W. W. Kelly, Foreman, including Foreman W. W. Kelly, Signalmen W. E. Weaver and G. H. Grant, Assistant Signalmen F. E. Hodges and C. B. Sweatt, Signalman C. E. Anderson; All signal employes assigned to Signal Gang No. 4, W. E. Warren, Foreman, including Foreman W. E. Warren, Signalmen D. R. Croslyn,* W. S. Walls, V. J. Veasey, W. R. Russell and G. L. Strickland.


(c) Carrier pay claimants listed or identified in part "b" above for a total of 560 man hours on a prorated basis at three (3) times their respective straight-time rate of pay, account Carrier did not permit them to work Saturday, February 22, 1969, a rest day and a





EMPLOYES' STATEMENT OF FACTS: Beginning February 18, and ending February 24, 1969, inclusive, extensive repair was made to the signal pole line and signal facilities in the Hamlet, North Carolina area, because of damage resulting from a snow and ice storm.


In making the needed repairs, Carrier used thirteen (13) employes of the Harrison Wright Construction Company, eleven (11) employes of the Stackhouse Construction Company, eleven (11) employes of the Hunter and walder Construction Company and two (2) Diesel Shop Electricians.


Employes of the Signal Department, Claimants in this dispute were used with the above forces on February 18, 19, 20, 21, and 24. At the close of work on the 21st however, Claimants were instructed not to report for duty on the 22nd or 23rd, but to report for work again on the morning of the 24th. The contractors' forces however, and the two (2) Diesel Shop Electricians worked 16 hours on Saturday, February 22 and 14 hours on Sunday, February 23.


The signal work performed by the Contractors' forces and the Diesel Shop Electricians is covered by the Signalmen's Agreement, especially the Scope. The instant claim was therefore filed as a result of the violation, and the Scope of the Signalmen's Agreement is shown below for ready reference.






The dispute was handled in the usual and proper manner, up to and including the highest officer of the Carrier, designated to handle such disputes, without obtaining a satisfactory settlement. Pertinent correspondence has been reproduced and attached hereto, identified as Brotherhood's Exhibit Nos. 1 through 10. There is an Agreement in effect between the parties bear-


18559 2


To complete the record the handling of the claim on the property, attached as Carrier's Exhibit "A" are copies of correspondence exchanged between General Chairman Harper and Superintendent Communications and Signals DePriest in connection therewith.




OPINION OF BOARD: Due to extensive damage caused by a snow and ice storm in the Hamlet, North Carolina area, Carrier used thirteen (13) employes of the Harrison Wright Construction Co.; eleven (11) employes of the Stackhouse Construction Co.; eleven (11) employes of the Hunter & Waldea Construction Co.; and two (2) Diesel Shop Electricians beginning February 18, 1969 and ending February 24, 1969 to make the necessary repairs. Employes of the Signal Department, Claimants herein, were used with the above mentioned outside forces on all dates except February 22nd and 23rd. The record establishes the fact that only a portion of the work performed by the outside forces belonged to Signalmen; however, the Organization has failed to prove the number of hours performed by outside forces that come within the Signalmen's scope. The record also reflects that Carrier offered to settle this dispute and the dispute contained in Award No. 18560, for a total of 352 hours at the time and one-half rate of pay. The record discloses that the Claim in this Award and the Claim in Award No. 18560, arise from the same work, but involve two different groups. Therefore, this Claim will be sustained in the amount of 352 hours at the time and one-half pay rate with the provision that the parties to this dispute and the dispute contained in Award No. 18560, will devise and apportion the distribution of the proceeds. It is specifically ordered that this Award for a total of 352 hours at the time and one-half rate covers and includes Claimants in Award No. 18560, as well as the Claimant in this Award and the proceeds will be apportioned to both set of Claimants.


FINDINGS: The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds and holds:




That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;


That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and




18559 12


Claim sustained in the amount of 352 hours at the time and one-half rate to be apportioned by the parties to Claimants involved in this Award and Claimants involved in Award No. 18560.






Dated at Chicago, Illinois, this 13th day of May 1971.

Keenan Printing Co., Chicago, Dl. Printed in U.S.A.
18559 13