H. G. Harm
NATIONAL RAILROAD ADJUST:1RNT BOARD
Award Number 19268
THIRD DIVISION Docket Number SG-19194
Thomas L. Hayes, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Penn Central Transportation Company, Debtor
STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood of Railroad
Signalmen on the former New York Cent--al Railroad Company
(Lines West of Buffalo) that:
(a) Carrier violated the current Signalmen's Agreements, as amended,
when it permitted the Railroad Accessories Corporation to install highway crossing protection at Mel
(b) Carrier should now be required to pay, as a result of this violation, additional compensatio
Signal Foreman
M. E.
Campbell
Signal Mechanics E. Garner, W. C. Schroeder and N. Peterson
Assistant Signal Mechanics J. J. Newby and D. L. Knoch
19th and 20th - 8 hours pro rata and 4 hours overtime
21st - 8 hours pro rate and 6 hours overtime
22nd - 8 hours pro rate and 5 1/2 hours overtime
23rd - 10 hours overtime
24th - 12 1/2 hours overtime
25th - 8 hours pro rata
(Carrier's File: SIG. C-12)
OPINION OF BOARD: The Organization learned from Carrier in November of 1967
that a substantial amount of signal work was to be performed
in the Northern Region in relation to crossing protection projects and that Carrier was considering
firms.
The Organization informed Carrier by a copy of a letter dated November
22, 1967, that it was against contracting any signal work to out side firms, that
it was not impressed with Carrier's argument that it could not employe sufficient
personnel, that in various parts of the country signal employees were being furloughed and that ther
to recruit signal personnel.
1
Award Number 19268 Page 2
Docket Number SG-19194
Again on March 6, 1969, B. H; Sttruerwald, Vice-President of the
Organization advised Carrier that the Brotherhood was aware that Carrier was
talking about contracting out highway crossing protection in Michigan and that
the "Organization has been continuously harassed by the Penn Central Management
in that they constantly tell us that they want to, or are going to, contract out
signal work that comes within the Scope of our respective agreements."
A portage, Michigan crossing protection project was ordered by the
State-_of Michigan Public Service Commission on July 18, 1968 and. the order. was
subeaquently amended,on July,.31, 1969 to make changes in. the specification requirements.
The Orde;.of July,8, 1968 called for Carrier to have installed and
operative modern automatic, flashing-light signals in conjunction with the opening
-to the Public of the crossing. ,
The dispute now before the Board stems from the fact that Carrier contracted-out to the, Railroad Ac
dates of August 19, 1969 through August 25, 10,69 and it is the position of the
Organization that,, Carrier violated the Signalmen's Agreement when it contracted
out this work.
There is no question about,the fart that the Scope, of the Signalmen's
Agreement specifically includes the work of installing highway crossing protective devises and appur
Moreover, the general rule is that a Ca:rier may not contract with
others for the performance of work within the Scope rule of an agreement and there
are few exceptions to this rule.
On August 19,..20, 21 and 22, 1969 when employes of the Railroad AccessQries Corporation were,instal
the Claimants worked their regular 10 hour work day installing certain bells for
the,Genera~ Food Company at Battle Creek, Michi6an.
Claimants were on their rest days Auguqt 23, 24 and 25, 1969 when employes of the aforesaid outside
at Pottage.
The burden,of,,pro(,f in this case is ou ti.e Carrier to demonstrate by
the presentation of
iact.;
in evidence that its
dk
eruiinatioxL to zontract opt
work can be justified in the light of all the circariscauces.
Award Number 19268 Page 3
Docket Number SG-19194
Carrier does not dispute that the work contracted out was of the type
that the Carrier's signal department employes generally performed but it asserts
that it had been unable to hire and retain a sufficient work force of construction and repair employ
Carrier also contends that time was of the essence with the Portage project because the work of inst
coordinated with the work of the State of Michigan Highway Department extending
Melody Avenue across the Carrier's tracks so that Carrier's work and the highway
construction work would both be completed about the same time.
The Board would point out that Carrier is under a duty to have a sufficient number of signalmen
than a year that a crossing protection installation would be necessary at Portage.
In addition, Carrier failed to demonstrate that it had made a diligent
effort to meet its responsibilities of maintaining a sufficient force of signal
employes.
This Board has held before, and it is basic in order to maintain the
Scope of any collective agreement, that work which b(longs to those under an
agreement. cannot be given away.to others not covered by the agreement except
under circumstances that.are so unusual as to fall within recognized exceptions
to the general rule.
Even if Carrier had made a reasonable effort to maintain a sufficient
force of signalmen, it would be obligated to show that the work which had been
contracted out could not have been performed by the Claimants on rest days, by
way of overtime, or by rearrangement of their work schedule. The Board finds that
Carrier has not met its burden of proving that it could not have worked existing
signal employes on weekends or extra hours during the week to perform the work.
The six Claimants in this case are requesting payment of a total of 492
hours and Carrier contends that any consideration by the Board of monetary payment to the Claimants
employes.
We are persuaded that the outside contractor's employes worked 170.5
hours during the period August 19-August 22 when Claimants were on duty and under
pay. With respect to these hours, compensation is allowed at the regular rate,
such compensation to be divided among the Claimants on a pro rata basis. As to
the 100.5 hours worked by the contractor's employes on August 23, 24 and 25, it
would appear that Claimants have been deprived of overtime work for which they
should receive pay at the overtime rate. Such pay is allowed and is to be
divided among the Claimants on a pro rata basis.
Award Number 19268 Page 4
Docket Number SG-19194
FINDINGS: The Third Division of the Adjustment Board, .upon the
whole record
and all the evidence,. finds and holds:
That the parties waived oral hearing;
That the .Carrier .and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act-,
as epproved June.21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the Agreement was violated.
A W A R D
The Claim is sustained to the extent of 170.5 hours of compensation
at the regular rate and 100.5 hours of compensation at the overtime rate, to be
divided among the Claimants on a pro rata basis.
- NATIONAL W.ILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated at .Chicago, Illinois, this 9th day of June 1972