NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-17900-
Frederick R. Blackwell, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Illinois Central Railroad Company
STATEMENT OF CIA IM: Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated on November 3, 4 and 5, 1966, when Car
Department laborers were assigned to excavate for machine foundations, to relocate a fire house and
SLN-41-B-67/Case 445)
(2) Claimants J. E. Langston, H. R. Parkinson, T.E. Ranft, J. Newcomb,
E. E. Heflin and H. Kracht each be allowed pay at their respective straight time
rates for an equal proportionate share of the total number of man hours consumed
by Car Department laborers in the performance of the work described within Part
(1) of this claim.
OPINION OF BOARD: This is a Scope claim in which Maintenance of Way Employes,
allege that work, which has customarily and traditionally
been assigned to them, was performed by Car Department laborers on November 3, 4,
and 5, 1966. The disputed work concerned the relocation of a fire house and the
stripping of forms from concrete foundations. Claimants J. E. Langston, H. R.
Parkinson, T. E. Ranft, J. Newcomb, E. E. Heflin, and H. Kracht seek an award of
pay at their respective straight time rates for an equal proportionate share of
the total number of man hours consumed by car Department laborers in the perform
ance of the disputed work.
FACTS OF RECORD
On November 3 and 4, 1966, Car Department laborers dug a hole of about
five (5) cubic yard capacity. Thereafter, Bridge and Building employes constructed
wooden forms for the pouring of a concrete foundation for a mechanical department
rolling machine. The Bridge and Building employees also prepared and poured the
concrete for the foundation. On November 5, this work was completed and the
Bridge and Building employees were sent to work at another location.
At this stage of the work Car Department laborers were used to remove
the wooden forms from the concrete foundation. They did not perform work on the
foundation itself. Mechanical department employes then installed the rolling
machine onto the foundation.
Also on November 3 or 4, Car Department laborers moved a wooden shed
from inside a shop building to a point outside the building but still within the
shop area. The shed is called a "fire house" because of its use as a storage
Award Number 19444 Page 2
Docket Number MW-17900
place for fire hoses. It is ten feet square by eight feet high and has no
foundation. The laborers moved it by placing it on skids and then pulling it
outside the building with a small tractor-crane.
Petitioner asserted on the property that all of this work is of a
character customarily and traditionally assigned to Bridge and Building employes,
and in support thereof submitted the following statement.
"Centralia, I11.1-26-68
Mr. P. D. Wheeler:
In regard to time claim made by B&B employes at Centralia,
I11., dated 11-3&4-66, against Car Dept. at Centralia, I11., as
to whether or not the work belonged to B&B employes. We have always done this work.
The moving of buildings, excavating for concrete foundations,
setting and removal of concrete forms, have always been done by
B&B employes.
Examples are many. A few are, all the machine foundations in
the Wheel Shop, in the Power House, Wood Mill, and the many boom
foundations all over the shop. In fact all the foundations (concrete) all over the shop have been do
/S/ J. E. Langston /S/ H. R. Parkinson /S/ F. E. Ranft
/S/ E. E. Heflin /S/ Herbert Kracht"
There is no reference in this statement to the moving of "fire houses"
or similar structures.
RULINGS ON PETITIONER'S CONTENTIONS
The Petitioner alleges a violation of the Agreement because Carrier
assigned Car Department laborers to perform the work of excavating for a concrete
foundation, of stripping wooden forms from the foundation, and of relocating a
fire house.
It is clear from the record that the construction of the forms for the
concrete foundation and the pouring of the foundation was performed by Bridge and
Building employes.
It is also clear that excavating for the forms and the removal of the
forms was part of the work of building the foundation. Consequently, this work
should have been performed by employes covered by the agreement.
As concerns the moving of the small fire house from one location to am ar
within the shop area, the Petitioner has not proved that such work accrues only t.,
Maintenance of Way employees.
We shall sustain the claim to the extent of allowing each of the named
Award Number 19444 Page 3
Docket Number MW-17900
claimants pay at straight time rate for an equal proportionate share of the
total man hours consumed by Car Department laborers in excavating for the machine
foundation and removal of the wooden forms therefrom. We deny any claim in connection with moving of
FINDINGS: The Third Division of the Adjustment Board, after giving the parties
to this dispute due notice of hearing thereon, and upon the whole
record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was violated to the extent shown in Opinion.
A W A R D
Claim sustained to the extent indicated in Opinion and Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST: ~!'N9r~i1~G~
Executive Secretary
Dated at Chicago, Illinois, this 30th day of October 1972.
I