NATIONAL RAILROAD ADJUSTMENT BOARD
TRIED DIVISION Docket Humber MK-19453
Frederick R. Blackwell, Referee
(Brotherhood of Maintenance of Way Employee
PARTIES TO DISPUTE:
(The Illinois Central Railroad Company
STATEMENT Cdr CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned
B&B Foreman L. I. Galley, Jr. instead of Machine Operator B. B. Copeland to
operate Burro Crane PR-39 on March
28,
April 18, 21, 22, 23, 24, 25, 28, 29,
30
and May 1, 1969 (System File SLH-89-M-69/Case 694).
(2) Machine Operator B. B. Copeland be allowed eighty-tb&t (88)
hours' pay at the Burro Crane operator's rate because of the violation referred
to in Pert (1) hereof.
OPINION Cdr BOARD: Claim arises account Bridge and Building Foreman performing
work allegedly accruing to employees within Group 1 of the
foadway Machine Department. Claiammt is an employee within Iroup 1 of the Road
way Machine Department. The claim arisen under Agreement between the parties,
effective September 1, 1934, as ceded through June 1, 1962.
FACTS
Under Rule 2 of the Agreement the Bridge and Building Department and
the Roadway Machine Department are separate sub-depa.rtmenta; the employees in
each sub-department have their seniority rights confined to their own sub-department. Under Rale 2(i
within Group 1 of the Rosdway Machine Department.
On the claim dahes the Carrier caused a burro crane to be operated by
a Bridge and Building Foreman, who held no seniority within the Roadway Machine
Department. At the time the claiment was under pay at a higher rate than the
burro crane operator's rate.
Under date of September 10, 1969, the General Chairman wrote as follows
to the Engineer Maintenance of Way:
"Appeal is made to yon for your consideration in our claim
SLJ-89-M-69 declined by Division Engineer, Mr. Lager, July 23, 1969,
in favor of Group 1 Machine Operator B. B. Copeland for rail crane
operator's rate is addition to his regular earnings on March 28,
April 18, 21, 22, 23, 24, 25, 28, 29,
30
and May 1, of 1969.
Award Number 19519 Page
2
Docket lumber
sit-19453
The claim" is employed in the Groan 1 classification and
the man that operated this machine is not employed in the Group
1 classification. The claimant was ready and willing to perform
this service an overtime and he did have a loss in earnings by
not being allowed to perform this work in accordance with his
seniority. It is requested that this claim be allowed."
In a April
23, 1970
letter Carrier's Manager of Labor Relations
stated that: "You have not cited any provision in the Agreement which reserves the operation of burr
COHTUITI011S OF PARTIES
Petitioner contends the Agreement was violated when the Bridge end
Building Foreman performed work accruing to a Group 1 employee and that claimant suffered loss of wo
he would have received if he
had performed
the work.
Carrier contends the Organization failed to cite any rule as being
violated and that the work could not be assigned to overtime '-ecause the work
was needed in rebuilding a bridge. Carrier also asserts there is no basis for
a monetary award because claimant was under pay during claim period.
RESOLUTION
Virtually these same issues were dealt with in Award
18808
(Devine),
which involved the same agreement and these same parties. In that Award the
Carrier made essentially the same contentions that are made here, namely, that
the claim should be denied because of the lack of citation of a specific rule
as being violated and because of the impossibility of scheduling the disputed
work to be performed by employees to whom it accrued.
In rejecting these contentions in Award
18908,
the Board stated:
"The General Chairman as specific in mating the reason for
the claim and the specific amount claimed. The Carrier could not
have been misled.
There is no showing that the work was of an emergency nature
or that it could not have been scheduled in a manner that it could
be performed by Agreement-covered employee. See Awards
12671,
13832, 14061, 14621,
and
15497.
The claim will be sustained."
We find no reason herein to depart from Award
18508
and we shall sustain the claim.
rt~::u~
r
Award Number 19519 Page
3
Docket Number NP-19453
FINDIIjGS: The Third Division of the Adjustment Board, upon the whole record
acid all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the ilnployes involved in this dispute arc
respectively Carrier and E?:ployes within the meaning of the Railway Labor Act,
as approved June 21,
1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was violated.
A W A $ D
Claim sustained.
NATIOKAL RAILROAD ADJUSTIEa^i 1:OAED
By Order of 'Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 20th day of December 1972.