NATIONAL RAILROAD ADJUSTM[ENT BOARD
THIRD DIVISION Docket Number
MW-19456
Robert M. O'Brien, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUt8:
(Norfolk and Western Railway Company
STATEMENT O' CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned Storehouse
Employe Roscoe Goodwin instead of Hoisting Engineer Robert Dunn to perform
hoisting engineer's work in connection with the construction of tracks at the
Ford Plant at Lorain, Ohio beginning on December 1,
1969
(System File Iii-BVE70-1).
(2) Hoisting Engineer Robert Dunn be allowed pay at the hoisting
engineer's rate for
b
nnnober of man hours equal to that expended by the storehouse employe in the performance of the work
this claim.
OPINION OF BOARD: On December 1,
1969,
Carrier's track forces required the
services of a hoisting engineer in connection with track
construction work they were performing at the Ford Plant, Lorain, Ohio. Instead of using Claimant, w
used Mr. Goodwin, a Store Department employe who holds no seniority within
the Maintenance of Way Department to perform the hoisting engineer's work.
It is the Organization's position that the work of track construction
is work encompassed within the Scope of the MW Agreement and consequently the
operation of any equipment used in the performance of the track construction
work properly belongs to employes covered by the MW Agreement. The machine, it
contends, was used in connection with MW work and the work of operating same
belonged to MW forces.
Carrier admits that the crane in question Has operated by the Stores
Department Crane Operator, an employe holding seniority under the Clerks' Agreement but raises sever
were received for positions as Hoisting Engineers; that all employes holding
seniority as Crane Operators were working; that Claimant was working elsewhere
on the property on the claim dates and could not be spared for the Ford Plant
work; that Claimant was off for personal reasons December 21,
1969
through
January 1,
1970;
and finally that the Store Department employee had been used
with his crane to perform MW work at least since December 1,
1946.
Award Number 19542 Page 2
Docket Number
W-19456
It is uncontroverted that the Schedule Agreement herein reserves all
work of constructing, maintaining, renewing and removing tracks to the MW
Track Department. But does it follow that the operation of a crane used in
connection therewith also belongs to employes covered by the W Agreement? This
Board finds that based on the facts herein the work of operating the crane in
connection with the track construction work at the Ford Plant should have been
assigned to W forces.
We subscribe to the reasoning enunciated in Award
19038
and followed
in Award
19158
that where, as here, we have a machine that could be used by one
or more crafts, the character of work performed by the machine would determine
the craft from which its operator was drawn. Since track construction work is
covered by the W Scope Rule, we feel it is logical that the operation of a
crane in connection with such work also belongs to W forces and employes thereof
should have been assigned to operate the crane.
Nor are we persuaded by Carrier's contention that it received no bids
for a hoisting engineer's position bulletined in September. Had it bulletined
the position closer to the date the operation began with particular reference
to the work location at LOTai3, we are not convinced that bids would not have
been received. Nor can Carrier contend that Claimants were working elsewhere
on the property on the claim dates and were thus not available for the work in
question. Numerous awards of this Division have held that where there has been
an agreement violation, such as here, compensation is due the claimants. See
also Awards No.
4
and No.
5
of the Public Law Board No.
249
involving the
same parties herein. Whether Claimant would have been absent December
21, 1969
through January 1,
1970
had he been employed as the crane operator at Lorain
is a matter of mere conjecture which cannot be used by Carrier as a defense to
the claim herein. We believe the miles relied on by Claimant are clear and
unesmbiguous and support the claim herein, past practice to the contrary notwithstanding. For the ab
FINDINGS: The Third Division of the Adjustment Board, upon the whole record and
all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes arithin the meaning of the Railway Labor Act,
as approved June
21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
Award Number 19542 Page
3
Docket Number
W-19456
That the Agreement was violated.
A W A R D
Claim sustained.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this
20th day of December 1972.