NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-19520
Alfred H. Brent, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Burlington Northern Inc.
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when, without notice to or
agreement with General Chairman Funk, it assigned or otherwise permitted outside
parties to perform the work of relocating main line tracks on operating property
at or near Alderdale, Washington beginning on or about February 1, 1970 and ending on or about March
(2) Machine Operators L. Schuh, F. Williamson, R. Archuleta, R. Roberts,
E. Aguirre, W. Kent, D. Legore, J. Whitney, L. Huot, Truck Drivers S. Suckow, H.
Godfrey, F. Ibabao, and R. Frater each be allowed pay at their respective straight
time rates for an equal proportionate share of the total number of man hours expended by outside par
claim.
OPINION OF BOARD: In this case the Carrier's mainline tracks were previously
relocated on account of the construction of the John Day Lock
and Dam on the Columbia River. The Carrier commenced operating trains on the relocated track in May
due to unstable terrain in the area of the relocation of tracks at Alderdale,
Washington. The Carrier was able to maintain track and line surface until such
time as the horizontal and vertical movements of the track became quite severe,
thus restricting train movement through the area to five miles per hour. At this
point it was the consensus of the officials of the Carrier and the Corps of Army
Engineers to relocate the Carrier's main track around the troublesome area. A
contract was let to an independent company to perform excavating, grading and construction of a new
The Organization immediately filed a claim of Agreement violation, alleging that the Carrier
Award Number 19625 Page 2
Docket Number MW-19520
"All work on Operating property, as classified in this
Agreement, shall be performed by employees covered by this
Agreement, unless by mutual agreement between the General
Chairman and designated Representative of Management, it is
agreed that certain jobs may be contracted to outside parties
account inability of the railroad due to lack of equipment,
qualified forces or other reasons to perform such work with
its own forces. It is recognized that where train service is
made inoperative due to conditions such as, but not limited to,
washouts or fires, individuals or contractors may be employed
pending discussion with respect to such mutual agreement."
The Organization contends that the work here involved was performed
on operating property; that the Carrier had qualified personnel and equipment to
have performed the work and that no discussions were undertaken with the General
Chairman. The Carrier defends its action, asserting that an emergency existed,
necessitating immediate action to forestall complete disruption of train movement
and that the United States Government still retained title to the land on which
the mainline tracks were located and on which the relocated tracks were to be
constructed.
The nub of this dispute is not whether an emergency existed, for under
the controlling rule the Carrier's mainline track was operating property under
the Agreement, notwithstanding the fact that the Government retained title to the
property. Even though an emergency may arise, the Agreement still requires discussion and agreement.
new track was to be constructed. There are conflicting versions on the material
facts of this case. The Organization asserts that the track was relocated between
the Columbia River and the mainline. The length of line change was about 1,320
feet long; with fill about 13,000 yards of fill material used. The Carrier, on
the other hand, asserts the track was constructed on Government owned land, with
the length of relocated trackage being 4,588 feet and that the contractor placed
68,647 cubic yards of embankment material plus 2,400 cubic yards of gravel subballast.
After thorough consideration of the record, it is clear to this Board
that neither party offered conclusive evidence to support their assertions on
the crucial issue of whether the work was actually performed on operating property. This Board canno
Accordingly, the claim will be dismissed.
Avard Number 19625 Page 3
Doc%ct Number MW-1.9520
FI177`'rY.~,g: The
ThJ.:,l
rivision of the Ad,luetn:erit Poar;, upon the whole record
and all i.hi evidcace, finds t:rd hold;;:
That the r',_ties e-aived oral hearing;
That t:', C':,rricr ;rcl the ):'i~:-.~.~^r~·s Involvrd in this disn,·ite are
resprctive·ly Carri.:_-r and Pn:ployee uit'in
ti
nc ren"·nir;; of
the Y,ailkay Labor Act,
as ..^.;>2reved Ju:i= _~
3_...
T'nat tl °.. ri.1-ici.c:;a o:: the Adjust:_c:zt f·;,.r,i has juri.dietion over the
dishte involvt:! 1:
:1
-in; and
That the claim be dismissed.
A ':1 /'. 1: D
Claim dismissed.
i:;;· G:C:. .c..' Viird il_:ision
G3iCC~:.._ . . · '.:2'.: i..tl'y
DGtr.d :': fi:ic7~,·~, lU*: nci:~, i,hi,^.^. 27th
(:.v ~.,"
February 1973.
i