NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-19519
Irwin M. Lieberman, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company (Pacific Lines)
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when, without prior notice
to the General Chairman as required by Article IV of the May 17, 1968 National
Agreement, it assigned the work of constructing a pedestrian overpass at
Guadalupe, California ^_o outside forces (System File MofW 152-729).
(2) B&B Foreman Delbert Bartel, Carpenters Richard Stanuseich,
Gussie Duran, Pablo Munoz, Gilbert Luna .and Helper John Borghini be allowed
pay at their respective straight time rates for an equal proportionate share
of the total number o_° man hours expended by outside forces in the performance
of the work referred to within Part (1) of this claim.
(3) The Carrier shall also pay the claimants six percent (6%)
interest per annum on the monetary allowances accruing from the initial claim
date until paid.
OPINION OF BOARD: The Organization contends that Carrier violated Article IV
of the May 17, 1968 National Agreement by failing to dive
the notice as provided therein to the General Chairman prior to contracting
out the work of constructing a pedestrian overpass at Guadalupe, California.
Claimants were employed in Carrier's B&B sub-department and were qualified to
perform the work in question. The work was contracted for on October 10,
1969 and was completed March 13, 1970.
Carrier claimed that the overpass was constructed pursuant to an
agreement with the City of Guadalupe and in accordance with a decision of the
California Public Utilities Commission. Carrier constructed the overpass,
with City approval of plans and specifications, as a donation. When the work
was completed the overpass coal owned and maintained by the City. Petitioner
does not challenge these facts.
Carrier, among other defenses, raises the issue that this claim
involves construction of a public walk on a public street and that construction
work on property not used in the operation of the railroad itself is not
within the scope of the Maintenance of Way Agreement. The Organization argues
that the structure was used in the operation of the railroad just as all
highway crossings are used in the operation of the railroad. It further
contends that the overpass was constructed on the Carrier's property and
for the Carrier's use in providing a safe means by which pedestrians could
cross the tracks. In support of its position Petitioner cites Award 19440
which deals with improvements to Carrier's property (another Carrier) as
,.
I
, s..l ,
`~
Award Number 19640 Page 2
Docket Number MW-19519
part of an improvement program initiated by the city. That case can clearly
be distinguished since it relates only to work on railroad property (installing
curbs, gutters, walks and driveways) for the benefit of that Carrier, in its
operations.
The matter before us is whether work for the city over railroad
property, completed by Carrier as a donation should be considered within
the scope of the Agreement, for purposes of applying Article IV. We find
that the overpass was not built for the use of. the railroad in its operations.
In Award 4783 we said:
"...where a carrier owns property used not in the
operation of maintenance of its railroad, but for
other and separate purposes, such property is outside
the purview of the Agreement."
The same reasoning was followed in a series of cases, many involving the same
parties herein: Awards 9602, 10080, 10722, 10986, 11462, 14019, 19253 and
others. We see no reason to depart from the doctrine enunciated in the Awards
cited. Since the overpass was not used in the operation or maintenance of
the railroad, we must conclude that its construction was not work within the
scope of the Agreement
Article IV of the May 17, 1968 Agreement requires notice in the
event Carrier "plans to contract out work within the scope of the applicable
schedule agreement". In view of our conclusions above, no notice had to be
served and therefore there was no violation of the Agreement.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved Tune 21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the Agreement was not violated.
Award Number 19640 page 3
Docket Number MW-19519
A
W A R
D
Claim denied.
NATIONAL RAILROAD
ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated a= Chicago, Illinois, this 27th day of February 1973.
..