NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number SG-19395
Robert M. O'Brien, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Burlington Northern Inc.
((Formerly Northern Pacific Railway Compaq)
STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood of
Railroad Signalmen on the former Northern Pacific Railway
Company:
On behalf of Signal Foremen T. L. Glover, J. D. Allison, D. W.
Taylor, and C. D. McInturf; Leading Signalman D. S. Lewis; Signalmen D. D.
Spencer, D. L. Abromeit, D. P. Scott, C. W. Vogt, M. R. Eng, J. H. Hietpas,
and D. K. Smith for twenty (20) hours pro rata pay eactl account persons not
covered by the Northern Pacific Railway Company Signalmen's Agreement fitting
up and wiring, in violation of the Scope of the Signalmen's Agreement, the
8' x12' relay housing which was installed by Carrier's signal forces on or
about December 5, 1969, for the specific location at Chehalis Jct., C.M.St.
P.&P.-N,P. crossing, Tacoma Division, M.P. 57 plus 2,500'.
/Carrier's File: SG-Scope 4/21/70/
OPINION OF BOARD: The claim arose when Carrier put in service a GIG relay
house called a bungalow which had been completely wired
and fitted by persons not covered by its Agreement with the Brotherhood of
Railroad Signalmen. The Organization contends that Carrier violated the
Scope Rule when it allowed other than Signal forces to perform the wiring
and fitting here in dispute. It claims that the Scope Rule applicable herein
specifically reserves to Signal forces the construction and installation of
relay housing and wiring, such as involved here. The Organization says that
prior Awards relied on by Carrier in support of its position are distinguish
able since the bungalow herein was "tailor made" at the direction of Carrier,
in accordance with Carrier's specifications, to be used specifically at
Chehalis Junction.
Carrier denies that the bungalow in question was specially made and
claims that it was ordered from the regular General Railway Signal Company
catalog just as other signal components axe ordered. Carrier further contends
that no provision of the Agreement restricts its inherent right to purchase
ready built component parts, such as the bungalow in question, from the
manufacturer.
Award Number 19645 Page 2
Docket Number SG-19395
Initially, we must decide a procedural objection raised by Carrier
that the claim is barred under the Time Limit Rule. Carrier contends that
the 60 day time limitation began when it purchased the bungalo.,i yet the claim
was not filed until some 14 months after the last of the bungalows were
shipped from the factory and the Organization became aware of this in 1968
when it installed two similar bungalows. We do not agree with this contention.
The claim came into being when it became known that Carrier allowed the General
Railway Signal Company to wire and fit the bungalow to be used at Chehalis
Junction. This, we believe, was December 5, 1969 when the relay house had been
placed upon its foundation and entered by Signalmen. Since the claim wa8 filed
on January 15, 1970, the 60 day limitation provided for in Article V of the
August 21, 1954 National Agreement was fully complied with. We shall proceed
to a determination of the claim on its merits.
Numerous cases have been before this Board involving the purchase
of signal equipment, and the Board has generally upheld the right of Carriers
to purchase pre-wired equipment. However, the Organization avers that the
claim herein is distinguishable since the bungalow was specially made to be
used specifically at Chehalis Junction. The Carrier denies this and tells
us that it is no different from any other bungalow used on this property.
Since we are unable to resolve this conflict from the record particularly
the exhibits relied on by both parties, we cannot determine whether or not
this is a valid distinction. However, we do find that Carrier had the right
to purchase this wired and fitted relay house from the manufacturer, as it
has so often done in the past, without violating the Agreement, and in particular the Scope Rule. Su
manufacturer and we do not believe that the Scope Rule herein applicable
restricts this right Carrier has to purchase pre-wired relay houses.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the Agreement was not violated.
Award Number 19645 Page 3
Docket Number SG-19395
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 27th day of February 1973.
;.