PARTIES TO DISPUTE:
NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Irwin M. Lieberman, Referee
(Brotherhood of Railroad Signalmen
Award Number 19706
Docket Number SG-19388
(Clinchfield Railroad Company
STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood of Railroad Signalm
(a) Carrier has ignored and continues to ignore the Signalmen's
Agreement, particularly the Scope, when, commencing on or about March 9, 1970,
it contracted out pole line installation (setting poles, stringing signal wires)
at Haysi, Virginia.
(b) Carrier should be required to compensate signal employee as
follows:
Foreman J. R. Wigga .··..8 hours time-and-one-half rate at $6.0863 for below
listed days, March 9,10,11, 12, 13, 17, 18, 19, 20, 1970, and others to be
added as long as violation exists.
Leading SC&E Man P. E. Booher, Jr., 8 hours each day at $5.8232, March 9, 10, 11,
12, 13, 17, 18, 19, 20, 1970, and others to be added.
Leading SC&E Man Raymond Wilson .~. 8 hours each day at $5.8232, March 9, 10, 11,
12, 13, 17, 18, 19, 20, 1970, and others to be added.
SC&E Man Harry B. Sykes ...·..8 hours each day at $5.7177, March 9, 10, 11, 12,
13, 17, 18, 19, 20, 1970, and others to be added.
SCE Man J. E. Richards ..,~..8 hours each day at $5.7177, Ma=ch 9, 10, 11, 12,
13, 17, 18, 19, 20, 1970, and others to be added,
SC&E Assistant T. Buchanan , _ 8 hours each day at $5.0669, March 9, 10, 11, 12,
13, 17, 18, 19, 20, 1970, and others to be added,
SC6E Helper D.
R.
Pierson . ..8 hours each day at $4.7334, March 9, 10, 11, 12,
13, 17, 18, 19, 20, 1970, and others to be added,
SC&B Helper
R.
E. Treadway ,.,8 hours each day at $4,7334, March 9, 10, 11, 12,
13, 17, 18, 19, 20, 1970, and others to be added.
Award Number 19706 Page 2
Docket Number SG-19388
OPINION OF BOARD: The claim alleges a diversion of Scope covered work in con
nection with the construction of a six-mile signal pole line
beginning at Haysi Junction, Virginia.
The Organization contends that the property in dispute is a part of the
Clinchfield Railroad; the Carrier denies that contention, stating that the Haysi
Railroad Company is a separate corporate entity and separately recognized carrier.
The Petitioner has presented no evidence of probative value to sustain its contention, and we must t
separate from the respondent Carrier. It appears from the record that the Haysi
Railroad Company contracted out pole line construction and installation work.
In Award No. 19369 we said:
"Numerous disputes have been before the Board where two or
more rail Carriers have found it necessary and desirable to enter
into contracts for the performance by one of them of a joint or
mutual duty or in other ways to share work required to be performed.
It has been consistently held that the work to be performed under
such circumstances falls to the Carrier and its employees who by
reason of such Agreements between the Carriers, have the superior
right or contractual duty to perform it. See Awards 11002, 6210,
3450, among others. Applying this principle to our present dispute,
so long as the C & 0, by reason of its contract with the Wabash
(now N & W) had a right to construct and maintain the interlocking
facility, then such signal work belonged to C & 0 signal employees.
However, when the two Carriers proceeded in a lawful and regular
manner to change the Agreement between them to provide that each
would install, operate and maintain the necessary signal facilities on its own properties and right
signal employees to install and maintain signal facilities on the
Wabash (now N & W) ceased as the Scope Rule cannot extend to work
that does not belong to the Carrier, but only applies to work
that the Carrier has to offer (Award 13056)."
The Petitioner has not shown that Carrier had control over the work in
dispute or that it was for Carrier's operations. Hence, it was not covered by
the Agreement, and we must dismiss the claim.
i
Award Number 19706 Page 3
Docket Dumber SG-19388
FII7DITS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Mploycs involved in this dispute are
respectively Carrier and Lcnloyes within the waning of the Railway Labor Act,
as approved June 21,
1934;
That this Division of the Adjustment Board has ,jurisdiction over the
dispute involved herein; .:nd
That the Agreement was not violated.
A IV A R D
Claim dismissed.
IvATI07:AL RAILROAD ADJUSTI-EM MUM
By Order of Third Division
ATTEST:
~~.A~
~_I~i
Executive Ser_reiK:ry
Dated at
Chicago,
Illinois, this 13th day of April 1973.
~.'T