NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-19671
C. Robert Roadley, Referee
(Brotherhood of Maintenance of Way Employee
PARTIES TO DISPUTE:
(Louisville and Nashville Railroad Company
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned Machine
Operator R. L. Abney instead of Machine Operator J. E. Love to operate the
burro crane used to lay ribbon rail and to pick up scrap rail between Henderson, Kentucky and Nashvi
(2) Machine Operator J. E. Love be allowed pay at the burro crane
operator's rate* for the same amount of time expended by Machine Operator R. L.
Abney in the performance of the aforedescribed work since August 9, 1970.
*Time and one-half rate to be applied to the overtime hours worked
by Mr. Abney - straight time rate to be applied to the time worked by Mr. Abney
during.regularly assigned work period.
OPINION OF BOARD: The basic question involved in this dispute is whether the
Carrier violated the Agreement when it assigned an employee
from the Bridge and Building Subdepartment to operate a burro crane in the performance of work alleg
work performed is alleged to have been the laying of ribbon rail and the picking
up of scrap rails and ditching.
Rule 3, of the Agreement, sets forth the various sub-departments comprising the Maintenance of W
"The employees covered herein shall be grouped in subdepartments,
namely:
3 (a) Track Subdepertment.
3 (b) Bridge and Building Subdepartment.
3 (c) Pump Repairmen and their Helpers.
3 (d) Welding subdepertment.
3 (e) Maintenance of Way - General."
Rule 5, of the Agreement, sets forth the grade and seniority rank of
the various employees within the Track and B&B Subdepartments. Rank 3, in the
Track Subdepartment covers, among others, "Operators of ditchers, cranes, shovel
draglines, etc." Rank 3, in the B&B Subdepartment, covers "Engineers and assistant engineers of
operators."
Award Number
1981)4
Page 2
Docket Number MW-19671
The claimant is a regularly assigned machine operator within the Track
Subdepartment. The employee assigned to operate the crane in question is a regularly assigned operat
Petitioner, in support of its position, stated in its submission to
this Board:
"Although there are machine operators within both the Track
and B&B Subdepartments, there is a clear line of demarcation
relative to the work accruing to said operators. The work
of operating machines used to perform track work accrues to
machine operators within the Track Subdepartment. The work
of operating machines used in the performance of B&B work
accrues to machine operators on the B&B Subdepartment. The
work involved here is that of operating a burro-crane used
to lay ribbon rail and to pick up scrap rails. This is work
that undeniably accrues to track forces."
There is no disagreement between the parties as to the principles ser
forth in the foregoing statement, except that Carrier denies that the crane in
question was used to lay ribbon rail, as claimed, but does concede that the work
performed consisted of picking up scrap and ditching. In the absence of airy
evidence introduced by Petitioner regarding the matter of laying ribbon rail we
will dismiss that portion of the claim but we will consider the merits of the
remainder,of the claim.
In support of its position the Carrier stated in its submission to this
Board that, it has been the practice on this property that when a crane is used in
one sub-department and a more pressing need arises for its use in a different subdepartment the oper
it in :the other sub-department. A careful review of the handling of this claim
on the property shows that this position was not raised by the Carrier but is a
new position appearing for the first time in Carrier submission. Therefore, that
contention of the Carrier is not properly before us and we cannot give it consideration now. See Awa
During the handling on the property the Carrier based its position in
denying the claim on three assertions. First, the claimant did not choose to
exercise his seniority to bid on three vacancies for crane operator jobs and
therefore had demonstrated no interest in such an assignment; secondly, claimant
was regularly assigned as a bushhog operator during the period of the claim and
therefore could not be in two places at the same time - thus he was not available;
and, thirdly, claimant suffered no loss in either work or earnings during the
period of the claim and therefore there is no basis for the claim.
Award Number
19814
Page 3
Docket Number MW-19671
In our view, these three contentions tend to skirt the basic issue
as to whether the work involved, picking up scrap and ditching, is properly
work belonging to employees in the Track Subdepartment and, if so, should not
a "Track" employee have been used to operate the equipment involved. We concur
in the reasoning of Petitioner that the work involved in this dispute is work
accruing to employees in the Track Subdepartment. Additionally, this Board has,
on several prior occasions, enunciated the principle that when a piece of equipment (such as a crane
then it is the character of the work performed that determines from which craft
the operator will be drawn.
In Award No. 13517 we stated:
"Second Division Award 1829 holds that the operation of a
crane is not the exclusive work of any craft. In the same
opinion it continues to say that:
'it ordinarily belongs to the craft whose work
it performs. It is the character of the work
performed by the crane that ordinarily determines
the craft from which its operator will be drawn."'
In Award 19158 we also stated:
"****It would be illogical to reserve scraping and grading
for performance by Employees under the agreement and then
contend that employees from any class, under any agreement,
who were capable of operating the machine, could be assigned."
Also see Award 19038 in which we subscribed to the same principle.
In the light of the foregoing we are persuaded that the Carrier violated
the Agreement in that it assigned work to an employee in the B&B Subdep4rtment
that should have been properly assigned to an employee in the Track Subdepartment.
We will therefore sustain Part 1 of the claim insofar as it relates to picking up
scrap rail sad ditching.
Insofar as Part 2 of the claim is concerned, having found that the
Agreement was violated in this case, we now hold that this monetary portion of
the claim is one for damages and not a penalty claim as argued by Carrier, for
it is clear from the record that the motivation behind the claim was primarily
to seek enforcement of the Agreement. Although there are conflicting prior Awards
on the question of "damages" vs. "penalties" we feel that the Opinion of the Board
as expressed in Award 11701, involving the same parties as in the instant case,
is significant and is quoted, in part, as follows:
nF;M`3..~
Award Number
19814
Page 4
Docket Number MW-19671
"Claimant contends that he is entitled to reparations resulting from the violation of the Agreem
other hand, maintains that Claimant suffered no lose because
he was employed. Carrier also points out that the compensation
requested by Petitioner is in the nature of a penalty and that the
Agreement makes no provision for a penalty payment in the event of
a violation of the Agreement.
We are of the opinion that the fundamental factor in this dispute
is the violation of the Agreement. **** For an Agreement to be
effective, both parties must uphold the terms. It is not enough
to recognize the breach without expecting the violator to accept
the consequences for its act. **** The argument that compensation
to Claimant would be in the nature of a penalty is likewise extraneous, for it brushes aside the san
caused the breach."
This principle has been reiterated in numerous other Awards of this Board, and
we subscribe to the reasoning therein.
However, in view of the fact that claimant suffered no loss in earnings
we find that the portion of the claim regarding payment of overtime is excessive.
Additionally, having dismissed the portion of the claim regarding the laying of
ribbon rail, we will sustain Part 2 of the claim only to the extent that the Carrier records indicat
and tr ditch!" sad, to aoah actat, at the pro-rata rata oela.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record and
all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employee involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
Award Number 19811 Page 5
Docket Number MW-19671
That the Agreement was violated.
A W A R D
Claim sustained to the extent indicated in the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
4, i
Dated at Chicago, Illinois, this 20th day of
Jun* 1973.