NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Pccket Number MW-19840
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Atchison, Topeka and Santa Fe Railway Company
( - Western Lines -
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned or otherwise
permitted Terminal Carpenter Earl Renfro and Engineering Department Employe 11, M.
Baker to install overlay panels on signs on the Southern Division beginning on or
about July 23, 1968 (System File 130-155-A-1).
(2) B&B Painters George Hintz, Henry Renken,
M.
L. Argabright, M. G.
Jones, L. P. Fowler and It. J. Roberts each be. allowed an additional 2-2/3 hours
of straight time pay for each day of the violation described in Part (1) above.
OPINION OF BOARD: On or about July 23, 1968 Carrier "assigned or otherwise
permitted" Terminal Carpenter Earl Renfro and Engineering
Department Employe H.
M.
Baker to install overlay panels on signs on the Southern
Division of Atchison, Topeka and Santa Fe Railway System,
Claimants, as B&B painters, maintain that Carrier violated the agreements
in that this work should have been assigned to them. They cite Award No, 13304
which states that "roadway signs ....have historically been installed, maintained
and painted by B&B painters."
Carrier contends that the only work involved in this dispute was the
securing, by screws or bolts on overlay panels on already existing signs; that
no painting of any kind was performed; that this work was not the exclusive right
of B&B painters, and therefore the agreements were not violated,
In response to this contention Claimants point out that "the application of overlay panel
of roadway signs and that such a change in the method of performing this work does
not change the character thereof."
The Board is of the opinion that Award No. 10369 (which follows the reasoning in previous Award
states:
"We believe that the placing of overlay signs in this
case was a new method for the repainting and/or relettering of existing signs. To this extent, the
Carrier's change in the method of performing the work
did not change the character of the work being performed. We are of the opinion that this work prope
belongs to the Claimants."
Award Number 19868 Page 2
Docket Number MId-19840
In view of the decisions in these previous Awards we
believe that
in this
instance this work properly belonged to Claimants and that Carrier did violate
the terms of the Foreman's and Laborer's
Agreement.
However,
Carrier contends that Claimant L.P. Fowler "is not a proper
claimant as he has relinquished his rights in the B&B Department in order to
remain in the Track
Department", and
that on July 23 and 24, 1968, the dates
this work was
performed, Mr
. Fowler worked as a trackman in the Track Department.
Carrier also contends that Claimant 11. J. Roberts
"ceased working
in
the B&B
Department and
commenced working in the Water Services Department as a
plumber effective September 26, 1967"; that he performed such work on the dates
in question, and therefore he :, not a proper claimant,
These allegations are not denied, it is the opinion of the Board that
L. P. Fowler and J. 1(. Roberts are not proper claimants. and that the claim on
their behalf should be denied.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record and
all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this D?vision of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was violated in accordance with the Opinion.
A W A R D
Claim sustained to the extent indicated in the Opinion and Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 27th day of July 1973.