NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-19867
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Elgin, Joliet and Eastern Railway Company
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned Car Department employes instead of Bridg
the work of removing a portion of and extending the Monorail System in the
Car Shop at Joliet, Illinois (System File BJ-22-70/SM-16-70).
_ (2) Furloughed Carpenter L. P. Martinson be allowed seven (7) days
of pay /eight (8) hours each day/ at the carpenter's straight time rate and
Welder 5. Neri be allowed the difference between what he would have received
at the welder's straight time rate and what he was paid at the _track laborer's
straight time rate for seven (7) days /eight (8) hours each day/ because of
the violation referred to in Part (1) hereof.
OPINION OF BOARD: The facts are undisputed in this case. Beginning October 21,
1970, Carrier was engaged in removing a portion of and extending the Monorail System in its Car
assigned to and being performed by Bridge and Building Gang #1. On October 29,
1970, Carrier assigned B&B Gang I)1 to work elsewhere. At the direction of
Carrier, two Car Department employes continued the work on the Monorail System
to completion.
Petitioner alleges this assignment violated the Agreement on the
grounds that this type of work is specifically granted to B&B forces under
certain provisions contained in Rule 56 1. Carrier does not disagree with
the fact that B&B forces have been utilized on various occasions to perform
such work in Carrier's Car Shop when circumstances required their use, but
contends that the question of scope rule exclusivity is not governing in this
case. Carrier maintains the work involved is properly assignable to Carmen
under provisions contained in Classification of Work Rule 127, and that in
using Carmen to do the work in question Carrier violated no provisions of the
Agreement.
It is well established that all work reserved to a class, unless
such work comes within an exception expressly set forth therein, must be
assigned to and performed by such class of employes. (Awards 12133 by Sempliner; 7585 by Cluster; 10
Award Number 19956 Page 2
Docket Number MW-19867
However, this issue is not germane to the dispute here. Our question is
whether or not this particular type of work was reserved to a class.
In the statement of Position of Employes on page 14 of the Record
Petitioner states: "There can be no question but that the Monorail System
is a part of the superstructure of the Joliet Car Shop building and, as such,
work thereon belongs to Maintenance of Way employes under the applicable provisions of Rule 56.
essence, the work in question consisted of construction and dismantling work
on the Joliet Car Shop building and/or appurtenances thereto and welding work
in connection therewith."
On the other hand, in declining this claim in a letter dated February 1, 1971, Carrier's Divisio
"the crane monorail system is not an integral part of the building; it is a
fixture of "equipment" functioning with and adjustable to various types of
car rebuilding programs."
Thus, we get around to this question: Did the Monorail System become a part of the building, or
used only in the building and repair of freight cars?
In a repair car shop, such as the one involved here, numerous
types of tools are used by the employes, such as dies, car horses, roller
supports, jigs, conveyers, etc. We understand the Monorail System is used
to support reamers and riveters which are used in the fabrication process.
It is mounted adjacent and parallel to both sides of Track K6. It is true
the upright channel iron members are mounted on the floor and fastened by
expansion bolts. It is also bolted to support beams which are attached to
the building. But does this, in itself, make the Monorail an appurtenance
to or a part of the building? We think not. Because of the different types
of cars worked on, the Monorail System must at times be lengthened or shortened. Sometimes it is eve
and reconstructed at another site. Therefore, it is not a part of the superstructure of the Car Shop
A superstructure connotes an integral part of a building above the
foundation. Even though the Monorail System is above the foundation, it provides no structural suppo
building. The relocation of it can hardly be construed as a "repair to the
building." It certainly is not a building in itself. It may or may not constitute a "fixture", but i
of an "appurtenance." An appurtenance must have some supportive or integral
relationship to the structure of the building itself. This Monorail System
could conceivably be constructed for operation to serve its purposes outside
of a building, though this might not be very practical. The point we make
Award Number 19956 Page 3
Docket Number MW-19867
is that, as set forth in Award 19306, the craneways in the instant case are
self-supporting, do not contribute to the support of the building structure,
and the posts, columns, bolts and brackets installed were to support the
craneways only. Thus, since this Monorail System is not an appurtenance to
the Car Shop the disputed work is not expressly reserved to the B&B carpenters and welders under
denied.
The amount of time involved to do the work in question -- whether
it required 14 man-days as claimed by Petitioner, or 12 man-hours as claimed
by Carrier -- becomes immaterial.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim Denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 28th day of September 1973.
.I