(Brotherhood of Railroad Signalmen PARTIES TO DISPUTE: (Seaboard Coast Line Railroad Company

STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood
of Railroad Signalmen on the Seaboard Coast Line
Railroad Company that:

(a) Seaboard Coast Line Railroad Company violated and continues to violate the Signalmen's Agreement when outside contractor forces were permitted to install a shielded aerial cable to replace open signal circuit control wires mounted on crossarms at M.P. S-0.3 to M.P. S-10.9, and M.P. A-0.5 to M.P. A-4.5 on former ACL RR Line.

(b) Seaboard Coast Line Railroad Company should pay to the following employes at their respective overtime rates of time and onehalf for the actual time that c with the hanging and lashing of aerial cable and installing of line junction boxes including terminated aerial cable in junction boxes, and any other signal work connected with said project. The total number of hours worked by contractor forces will be divided equally among the employes named within this claim
Gang No. 2 - P. L. Ellis, Jr., Foreman




Gang No. 8 - D. W. Weaver, Foreman




Gang No. 9 - M. E. Drury, Foreman






." . 1



(c) Seaboard Coast Line Railroad Company should make available the time records of H. P. Foley Construction Co. which were kept by said Company in connection with the installation of signal aerial cable and are available to Seaboard Coast Line Railroad Company, as a basis for just settleme


OPINION OF BOARD: Since 1912, near Richmond, Virginia, the Virginia
Electric and Power Company's 115 Kv Transmission line occupied Carrier's right of way parallel'ng its communication and signal wire lines. In 1970 the Power Company desired to upgrade and increase the power load of its transmission line. It was recognized that this upgrading would seriously interfere with the proper functioning of the adjacent communicat Power Company at its sole expense would eliminate the problem by providing new aerial shielded cable existing poles to replace the open wire lines. It was agreed that the new shielded cable facility would be conveyed to Carrier only after satisfactory completion of the installation whereupon Carrier's employees would then transfer the ap wire facility to the new shielded cable. The Power Company engineered the work, supplied the materials required and hired an outside contractor to perform the installatio herein.

The Carrier argues that the work in question was solely for the account of and at the expense of the Power Company. Further it is urged that the installation required the use of special equipment not owned by Carrier; this contention is not denied by the Petitioner who states that the equipment could have been leased. The Organization alleges that the work is indisputably reserved by the Scope of the Agreement to employees of Carrier's Signal Department and the Agreement accords no relief to Carrier work involved only signal circuits, not power circuits and the Power Company had no authority or jurisdiction to perform the work unless granted by Carrier.

In a long series of Awards going back to 1951, we have held consistently that work which is not for the exclusive benefit of Carrier and not within Carrier's co violation of the Scope Rule (see for example Awards 5246, 6499, 13745 and 19718). Petitioner cites the Award in Public Law Board No. 387 in support of its position. That Award must be distinguished in that



the work was started by Carrier's forces and while unfinished transferred to outside forces for Board No. 747, which involved almost identical circumstances to those herein, it was said:











We concur in the reasoning cited above. Since the work involved herein was not for the benefit o and not under its direction or control, it did not violate the terms of the Scope Rule of the Agreement. In addition it is well settled that work may be contracted out when special skills, equipment or materials are needed, which are not possessed by Carrier (See Awards 5563, 11208, 13273, 18046, 18931 and many others). For the reasons indicated above the Claim must be denied.







That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes wit the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and





        Claim denied.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


ATTEST: /li
xecutive Secretary

Dated at Chicago, Illinois, this 28th day of February 1974.
        Dissent to Award No. 20156, Docket No. SG-19911


Award No. 20156 is no better than the precedent upon which it relies. The Majority has cited Award No. 18931 and others: In our Dissent to Award No. 18931 we called attention to certain errors of interpretation there committed; our Dissent there is equally applicable here. Award No. 20156 is in error and dissent is registered.

                                W. W. Altus, Jr.

                                Labor Member fir'