NATIONAL
RAILROAD ADJUSTMENT
BOARD
THIRD DIVISION Docket Number SG-19896
PARTIES Frederick R. Blackwell, Referee
(Brotherhood of Railroad Signalmen
TO DISPUTE:
(Chicago, Rock Island and Pacific Railroad Company
STATEMENP OF CLAIM: Claim of the General Committee of the Brotherhood
of Railroad Signalmen on the Chicago, Rock Island
and Pacific Railroad Company.
I
I
(a) Carrier violated the Signalmen's Agreement, Particularly
Rules 17 and 62, when it did not properly compensate Signal Maintainer
D. 0. Kidd for 5-6/12 overtime hours worked on March 18, 1971.
(b) Carrier should now pay to Mr. D. 0. Kidd 5-6/12 hours
time at his hourly overtime rate.
ZCarrier's File: L-130-47_1%
OPINION OF BOARD: On March 17, 1971 a train derailment occurred at
Missouri Division Junction, destroying a switch
and a switch machine. A straight rail was installed on the 17th; on
the 18th the switch was replaced and the Claimant Signal Maintainer
installed a secondhand switch machine. If the switch machine had
operated properly upon installation, the installation would have been
completed within Claimant's regular hours. However, because of improper operation, the switch machin
internally, and re-installed. As a result the Claimant worked 5~
hours beyond his regular hours to complete the job of installing the
switch machine. The Claimant, a monthly rated employee, now claims
overtime for the 5k hours.
j The pertinent agreement provisions
fourth paragraphs of Rule 62, read as follows:
d in f the third and
"RULE 62. MONTHLY RATED SIGNAL MAINTAMRS:
No overtime is allowed for time worked in excess
of eight (8) hours per day on the regularly assigned
five (5) days per week tae employee is scheduled to
work, nor on the first scheduled rest day (6th day) of
the work week or holidays- on the other hand, no time
is to be deducted unless the employee lays off on his
own accord.
Award Number 20208
I Docket Number SG-19896
Page 2
"On the regularly assigned five (5) days per
week the employee is scheduled to work, ordinary
Maintenance and Construction work will not be required outside of their bulletined assigned hours.
This does not apply to such travel time or work a
Maintainer might run into when in completing a certain job worked on, during the day he might leave
regu
lar assigned or return thereto outside his regu-
i gned hours,
The Employes say the 5j hours of disputed work involved
"ordinary Maintenance and Construction work" as such term is used
in the first sentence of the fourth paragraph of Rule 62; in consequence, the disputed work is gover
which provides
that "ordinary Maintenance and Construction work
will not be required outside of...assigned hours." The Carrier's
response is that it merely exercised its prerogative under the third
and fourth Paragraphs of Rule 62 to require a monthly rated signal
maintainer to perform work that he "might run into" on a job which
he had begun but not completed during his regular hours. The Carrier also says the work was not ordi
been deferred, but resulted from a derailment of the previous day.
On the basis of the foregoing, and the whole record, we con-
. clude that the work following Claimants regular hours was work "run
into" within the meaning of the second sentence of the fourth paragraph
of Rule 62. Thus, irrespective of whether Carrier's urgency to have
the switch installed was slight or great, the Carrier is not required
to pay:overtime. We are mindful that the nature of the fourth paragraph
of Rule 62 is such that it could possibly be misused by the Carrier. We
are also mindful that, in this case, a lengthy period was required to
perform the work "run into" in completing a certain job. For these
reasons we have studied the facts closely. We note though, that the
Employes did not dispute that the work would have been completed within
regular hours if all had gone well. Nor did the Employes contend that
the Carrier could have foreseen the malfunctioning of the switch machine,
that the Carrier had any knowledge about the machine's defects which
would have relieved Claimant of the duty to complete the job, or that the
job could have gone over until the next day. The Employes' Rebuttal does
suggest that Claimant made repairs to the second-hand switch machine which
should have been made by the shop forces. If established of record, this
point might have placed the case in a different posture; however, the
argument was not raised on the property and therefore it cannot be con
sidered now. Consequently, in the facts which obtain here, we cannot
conclude that the Carrier's action was not in conformity with the Agree
ment. We shall therefore deny the claim.
Award Number 20208 Docket NumberSG-19896
Page 3
FINDINGS: The Third Division of the Adjustment Board, upon the
whole record and all the evidence, finds and holds;
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes
the Railway Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdicti3n over the dispute involved herein; an
The Agreement was not violated.
A W=
Claim denied.
NATIONAL RAILROAD AD,TISS
i , r., Rnp;z7
By Order of Third Division
ATTEST:
~~
~~/
E:cecutive Secretary
Dated at C:iicago, 711inois, this 11th day ofApril 1974.