NATIONAL RAILROAD ADJUSTMENT BQARD
THIRD DPVISION Docket Number MW-20213
Frederick R. Blackwell, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Port Terminal Railroad Association
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood
that
(1) The Carrier violated the Agreement when it assigned
other than Maintenance of Way welders to perform welding work on a
Pettibone-Mulliken Speed Swing on March 30 and 31, 1972 /System File
MW-72-4 (PTRA)/
(2) Welder L. R.
Tillery
be allowed eight (8) hours'
pay at his straight time rate and eight (8) hours' pay at his
time and one-half rate because of the violation referred to within
Part (1) of this claim.
OPINION OF BOARD: The MofW Employes assert that, on ?larch 30, 1972 and
Good Friday, March 31, 1972, the Carrier used a machinist to perform welding on a machine assign
and qualified to perform the welding, and that Claimant should now
receive pro rata pay for March 30 and time and one-half for Good Friday, :larch 31, 1972.
The
Employes stated
on the property that welding on Mofa
machines has always been done by MotW welders. The Carrier's response on the property was that there
it did not agree that welding on equipment belonged to any one department inasmuch as Carrier had we
property; that the welding and repair of equipment falls in the category of machinists' work; and th
had the machinist do the welding which consumed approximately twenty
(20) minutes. The Carrier's Submission to this Board states the Carrier's position differently. The
was taken to the shop where a Roundhouse Machinist-Welder was used to
do welding work on the machine, and that such had occurred on previous
occasions; that no work was performed on March 31, 1972, Good Friday;
and that the claim cannot prevail because the MofW Scope Rule is a
general one, and there has been no showing that MofW employes performed the disputed work to the exc
Award Number 20258 Page 2
Docket Number MW-20213
Two of Carrier's defenses have been challenged as not
having been raised on the property. We find on the record that the
defense concerning no work on :larch 31 was raised by Carrier's assertion that the work consumed no
therefore consider this defense. However, the Carrier made no reference on the property to the gener
the exclusivity doctrine and, consequently, this defense is not properly before the Board.
The remaining defenses by Carrier raise the question of
whether the MofW Employes have an agreement right to the disputed work.
The Employes contend that Award 19949, involving the same issue and the
same parties, has resolved this question in favor of the MofW Employes.
We concur. In that Award repair work being performed by MofW Employes
on MofW roadway equipment was claimed by the Machinists, whereupon the
Carrier unilaterally transferred the work to the Machinists. In adjudicating the ensuing MofW claim
agreement, this
Board concluded
that repair work on equipment within
the MOEW Department belonged to MofW Employes. The welding work in
dispute here is repair work on equipment within the MofW Department.
Thus, the issue and the parties in the instant dispute are the same as
in Award 19949 and we shall therefore sustain Part 1 of the claim. In
respect to Part 2 of the claim we note that the Carrier, as previously
indicated, did not directly challenge the monetary amount of the claim
on the property by making any express contention that no work was performed on March 31; however, th
challenged such
monetary amount by its statement that the work consumed only twenty
minutes. We believe it would be
hyper-technical to
rule that this
was not a challenge to the Employes contention that the welding entailed two days of work, especiall
points out that March 31 was a holiday and that, so far as its records
reflect, no work was performed on the holiday by either Machinists or
MofW Employes. Accordingly, we shall sustain the claim for
March 30, 1972, and deny the claim for March 31, 1972.
FINDINGS: The Third Division of the Adjustment
Board, upon
the
whole record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes
Railway Labor Act, as approved June 21, 1934;
Award Number 20258 Page 3
Docket Number MW-20213
That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; an
The Agreement was violated.
A W A R D
Part 1 of the claim is sustained. Part 2 of the claim is
sustained in part and denied in part as per Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By 'rder of Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 31st day of May.1974.
I,l