(Brotherhood of Railroad Signalmen

            PARTIES TO DISPUTE:

            (Southern Pacific Transportation Company (Texas

            ( and Louisiana Lines)


            STATEMENT OF CLAIM: Claim of the General Comnittee of the Brotherhood

            of Railroad Signalmen on the Southern Pacific

            Transportation Company--Texas and Louisiana Lines (former Texas and

            New Orleans Railroad Company):


          On behalf of San Antonio Division Signal Maintainer E. Lillie, Jr., for 269 hours pay at time and one-half rate account signal supervisory personnel workin were out of service at Langtry during June and July, 1971.


          OPINION OF BOARD: The main line of the Southern Pacific Transporta

          tion Company between Del Rio and Sanderson, Texas,

          winds through several deep cuts made through rock and sandstone for

          mations. Due to many factors, materials become dislodged on steep

          bluffs in these cuts and slide or roll down to the tracks below.

          Periodically these bluffs are "scaled". On June 24, 1971 scaling

          operations began near Mile Post 447, and Signal employes removed the

          rockslide detector fences and completely dismantled all protective de

          vices which had been incorporated into the Carrier's Signal System.

          Temporary electrical wiring or "jumpers" were installed into the sig

          nal system to make the signals operate "False Cleared" as if the rock

          Canoes had not been removed. Thus it became necessary to provide the

          protection normally afforded by the rock fences through a visual sur

          veillance and in the case of actual falling rocks the manual removal

          of the temporary jumper wires and the application of a "shunt" to the

          signal track circuit. The scaling operation was concluded on July 12th.


          The Organization contends that the Carrier violated the Signalmen's Agreement, particularly the Scope Rule, when it used Assistant Signal Supervisors Shaw and Haas, not covered by the Agreement to maintain t for its trains during the time Signal employes were not assigned. The Carrier contends that Assistant Signal Supervisors Shaw and Haas never performed any "work" that came within the Scope Rule. It is not disputed that there were no instance of the Supervisors' evening watches.


' The Scope Rule provides that the "Agreement shall apply to
          work or service performed by the employes specified herein in the

          Signal Department and governs the rates of pay, hours of service and


:fit,:.
                    Award Number 20369 Page 2

                    Docket Number SG-20091


working conditions of all employes covered by Article I, engaged in the ...maintenance... fp) detector devices connected with signal systems..."

That the "shunting of the track and the removing of the false battery from the coil relay, thereby putting the signals at the atop position", the work that would have to be done if a rock slide was visually detected, was within the Awards of this Division. The question now to consider is whether or not the Scope Rule was violated where supervisory employee, not covered by the Agreement, whose sole running from 11, 12 and 13 consecutive hours was visually protecting Carrier's trains from rock elides, and the sole means of actuating the signals to provide this protection for Carrier's trains when and if needed was the shunting process described above? We decide that in the narrow circumstances of this case the Scope Rule was violated.

The statements of Assistant Supervisor Shaw clearly shows that the sole, continuous function of the supervisor was the protection of Carrier's train during stated hours throughout the night.

        Assistant Signal Supervisor Shaw stated:


        "...then I would go back to where the work had been done

        and sit up during the night ....To the beat of my knowledge,

        this is the time I spent ab, nights: June 24, 8 p.m. -

        7 A.M., June 25, 7 P.M. -_7 A.M., June 26. 9 P.M. - 8 A.M.,

        June 27, 6 P.M. - 7 A.M... July 3 - P (sic) P.M. - 7 A.M.

        Of these nights I was watching for fallen rocks at the

        two bluffs, there were never any rocks that fell."


Clearly then, the sole function of the Supervisors during the night watches at the bluffs was the protection of trains from rock slides.

In this case the sole method of protecting the Carrier trains in the event of a rock slide was the use of the shunt and cable processby an employs.. These is no r communicative device that could provide communication with trains in the area; nor was there ashy defense offered by the Carrier that the supervisors bad radio equipment to contact accessible signal maintainers in the area capable of applying the shunt and cable process in the event of a rock slide. Indeed, Signal Foreman Mouton stated in his report:

        "In event of a rock slide I was to immediately shunt the track and remove false battery from coil relay, thereby putting signals on either side of rock detector at stop position. As I had no radio on the truck I was using it

                  Award Number 20369 Page 3

                  Docket Number SG-20091


        "would be delivered to the train the cause of stopping either by walking to train or ride truck if possible to stopped train."


It is uncontroverted that when Signal Maintainer Lilie performed the same functions as Signal Foreman Mouton and the two Supervisors, his instructions were the same in the event of a rock slide, "remove the battery connection from the relay to provide signal protection". It would be most unreasonable to speculate that the Supervisors had another means available to them other than the method of shunting which is Signal Maintainers Scope work. The record leaves little doubt but that had a rock slide occurred the Supervisors would have exercised their only option, that of the shunting and cable process which is Signal Maintainers Scope work.

We find that the shunting and cable process capability was the sole method of protecting trains in this case; and also find that this capability was so enmeshed in the work performed by the Supervisors on the bluffs that the work considered Scope "work" or "service" even though there actually never was a rock slide where the Supervisors were called upon to utilize the "shunting and cable. capability.

This decision is a narrow one and in no way infringes on management perogatives. Carrier is not required to use Signalmen at every location where a rock fence has been removed. It is solely up to the Carrier to decide whether or not the risks involved at a given site requires visual protection coupled with a "shunting" signaling capability. In a great many circumstances, the bluffs might not be as steep, the traffic not as substantial, the presence (and resulting protection) of other Carrier employes in the vicinity greater, the usability of other communication devices possible etc., so that the Carrier could, in the sole discretion of the Carrier, decide that no employes would be needed at the site. But, when the Carrier decides that an employe is necessary and the trains is the shunting process, then that work must be given to an employe covered by the Signalmen's Agreement.

Award 11799 does not support Carrier's position in this case. In 11799, in the movement of a CTC machine the Organization alleged that an Assistant Signal Superintendent was standing by to perform signal maintainer duties of standing by to perform his own duties as a Supervisor. The Carrier demonstrated that the Organiza by showing that an employe performing supervisory functions was required to go from one station to a
                  Award Number 20369 Page 4

                  Docket Number SG-20091


were present to perform any signal work that might occur.

        FINDINGS: The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds and holds:


        That the parties waived oral hearing;


That the Carrier and the EMployes involved in this dispute are respectively Carrier and Employes the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over.the dispute involved herein; an
        That the Agreement was violated.


                  A W A R D


Claimant to be paid time and one-half rate for the time submitted in his claim, less the hours submitted for the time marked off on July 2 through July 5th; less all the time claimed while Signal Gang Foreman Mouton, an employe covered by the Signal Agreement and not excepted from p Scope Rule, was on duty; less the time claimed for time in which the Supervisors were not on the bluff property; less the time signalman Lilie worked overtime on Jun
                        NATIONAL RAILROAD ADJUSTMENT BOARD

                        By Order of Third Division


ATTEST: do'II!/
Executive Secretary

Dated at Chicago, Illinois, this 23rd day of August 1974.