NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-20033
Irving T. Bergman, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Norfolk and Western Railway Company
STATEMENT OF CLAIM: Claim of the System Committee of the Brother-
hood that:
(1) The Carrier violated the Agreement when it used outside forces (San San Incorporated) to rep
Rexford Tunnel and refused to assign Carpenter Foreman Joseph Piccin,
B&B Carpenters Peter Cieresewski, John A. Panepucci, Albert P. Fiutem,
Louis Katona, Jr. and W. C. Hoskinson to perform said repair work
(System File
MW-BRS-71-10).
(2) Each employe named above be allowed pay at his re*
spective rates for all time worked by outside forces since April 29,
1971 in repairing Rexford Tunnel.
OPINION OF
BOARD: This
case involves the Carrier's right to contract
oat an interior tunnel repair job without using
its
B & B
employes for all or any part of the work. Rule 40 (a) of
the Agreement states: "All work of--, repair--of,--,tunnels,--,
built of brick, tile, concrete, stone, wood or steel,--, as well as
all appurtenances thersto,loading and unloading and handling all
kinds of bridge and building material, shall be bridge and building
work, and shall be performed by employes in the Bridge and Building
sub-department. Construction work may be done by contract where there
is not a sufficient number of properly qualified--or the Railroad
Company does not have proper equipment to perform it."
The work of stabilizing inner surfaces of the tunnel
had been done in the past by a Gunite process. This consisted of
covering with metal lath and filling with hydraulically applied
concrete. It is not disputed that in 1958 the parties agreed by
exchange of letters that the Gunite work could be done in a tunnel by a contractor using its equipme
man and a hose man with the preparation work being done by B & B
forces; the superintendent to tell the B & B foreman what he wanted
and the foreman to convey the information to the B & B forces.
Award Number 20372 Page 2
Docket Number MW-20033
The Organization has argued that this letter understanding should
also control the present situation. The Carrier contends that this
was not a formal supplemental agreement to cover all future situations. In addition, the claim is no
til October 1970 when the Carrier had all the work done by a contractor. The Organization made a cla
on the same facts which was pending when this claim was made in-1971.
Since then, the pending claim was dismissed because it was not properly presented on the property in
the Carrier to meet the issue involved. Nevertheless, in that case
Award 19976, it was stated that Rule 40 (a) is not general or ambiguous in requiring that tunnel rep
forces. The claim was not determined on the merits.
The Carrier's position is based primarily on the fact that
upon finding that the Gunite process was not satisfactory, it has substituted the Shotcrete process
requiring equipment that it does not own and requiring skill beyond
that of the B & B forces. The Shotcrete process is described by the
Carrier only as using a different material and method of application.
The Organization has gone into greater detail in explaining that Guniting is done with a mixture of
a sealer applied in the same manner as Shotcreting. The only difference being that Shotcrete, mixed
three quarter inch stone instead of pea gravel. Petitioner has also
detailed, without contradiction in the handling on the property,
that the B & B forces had worked in the same Rexford Tunnel involved in this claim for a total o
scaling and installing roof bolts. Additionally, Petitioner has
cited from the 8th Edition of Railway Track & Structures Cyclopedia
published in 1955 that shotcreting was used prior to 1955. Quoted
from the text is the following: "Shotcrete, a material composed of
cement, sand and water, and applied pneumatically with a cement gun,
-- " The Carrier's final position is that it tried to prevail on
the contractor to work with the B & B forces but that the contractor
would not guarantee the job unless it used its own employes for the
preparation of the surface as well as for the application of shotcrete.
Petitioner shows that in Award 18628 between the same
parties, Rule 40 (a) was held to be clear and free from ambiguity.
Award 6905 held that scope rules cover work not equipment and that
a claim for equal amount of time worked by contractor employes is
proper. Award 9612 held that where work is within the Scope Rule,
Award Number 20372 Page 3
Docket Number MW-20033
Carrier has the burden to justify an exception and that no loss of work
by claimants, is not a defense. Award 19158 held that exceptions prove
the rule and that by consenting to piecemealing the Rule has not been
waived. Award 6892 held that the Carrier has the burden of showing that
its employes are not qualified and, in Award 18056, that assertions are
not proof.
The Carrier has submitted many Awards to support their position.
On the subject of use of contractors, the Awards may be summarized as showing special circumstances
11493, where the Carrier lacked equipment costing $278,870, used once in many
years; Award 11856, Carrier proved diligent effort to rent equipment for its
own use without success; Award 11969, involved danger to lives of Carrier's
employes; Award 13272, involved contractor's equipment costing $220,800;
Award 13966, held the Scope Rule to be a general one; Award 18046, set forth
adequate proof to support use of a contractor including necessity for a
licensed engineer. Award 10255, involved a broad ambiguous Scope Rule and
factual data submitted by Carrier to prove its point. Other Awards were concerned with the need for
Rule is general which is not the determining factor in the present case.
Awards on the subject of piecemealing granted to the Carrier the right to
exercise managerial judgment as in 3559, 3278 and 2186. In other Awards
large lump sum jobs were given to Contractors, as in Award 11208 for $500,000,
also involving unique, complicated work requiring special proven skills; and
Award 9335, where twenty classes of employes were used represented by thirteen
different unions; and Award 12532 where management was not required to investigate the possibility o
The record in this case discloses that the Carrier has not submitted
proof that Shotcreting is different from Guniting so that none of the B&B
forces could be used. Continued assertions without support by factual data
sufficient to overcome the clear unambiguous Scope Rule does not meet the
required burden of proof to establish an exception which is not stated in the
Agreement. We do not find that in all future similar situations the letters
in 1958 control this situation. We are of the opinion that contracting out
the work has been justified, with B&B forces being used as agreed upon in
1958. Also, the record does not show that preparatory work which B&B forces
have performed under the direction of the contractor was specifically rejected
by this contractor as being unsatisfactory or that other contractors were contacted for this job who
into consideration, we believe that B&B forces are entitled to perform repair
work in the tunnel, and in this case, to the extent that they were used in 1958.
I
Award Number 20372 Page 4
Docket Number MW-20033
FINDINGS: The Third Division of the Adjustment Board2 upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
The Agreement was violated.
A W A R D
Claim disposed of as and to the extent indicated in the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST: or
414
0
am
Executive Secretary
Dated at Chicago, Illinois, this 6th day of September 1974.