STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:


      (1) The Carrier violated the Agreement when it assigned Store Department employes instead of B&B Department employes to build racks for the storage of rails and frogs at Brainerd, Minnesota during the period extending from May 19 to May 29, 1970 inclusive (System file MW-84 8/28/70.)


      (2) B&B employes D. C. Smith, A. L. Ramsdell, A. M. Novotny, A. H. Berndt, R. L. Dixon, J. E. Swartout, L. L. Felton, D. L. Hyatt, L. C. Hyatt, R. C. Carlson, J. L. Brennan and G. L. Ramsdell each be allowed pay at their respective straight time rates for an equal proportionate share of the total number of man hours expended by Store Department employes (296 hours)in the performance of the work referred to within Part (1) of this claim.


      OPINION OF BOARD: Carrier maintains one of its major shop facilities at

      Brainerd, Minnesota. In conjunction therewith it maintains a large Store Department which handle Facility at Brainerd. Included in the materials handled are switch points, frogs and guard rails. Because of the size of said materials they had been stored out of doors on material skids located at the extreme easterly end of the rail storage yard rather than in the 50' x 300' Store Building. The location was adjacent to track facilities but not readily accessible for highway vehicles. In order to facilitate the handling of material orders by highway, Carrier decided to relocate the aforementioned track material approximately 150 yards, in an easterly direction, so that it could be loaded either on highway vehicles or on rail cars.


      Beginning May 9, 1970, Carrier assigned a number of Store Department employes to perform the wor foundation blocks be cut to the required length, placed at required intervals at precisely the proper elevation so as to provide a level base on which to place the cross timbers. The cross timbers were also cut to the required


i~
                Award Number 20380 Page 2

                Docket Number MW-19630


length before they were placed on and fastened to the foundation blocks with spikes. The tools used in the construction work included, inter alia, a chain saw, a framing square, carpenter's level, chalk line, drills, hammers. MW, Petitioner herein, alleges that: (1) the construction work involved consumed 296 hours; (2) contractually the work was reserved to B&B Subdepartment employes. On the other hand, Carrier states that: (1) the Scope Rule of the MW Agreement is general in nature; (2) MW failed to prove that work of the kind was by history, tradition and custom, on a system wide basis, the exclusive work of B&B employes; (3) the work was incidental to the duties of the Store Department employes; and (4) Carrier "estimates" that the total work time consumed in the construction of the racks was 60 hours and any additional time was devoted to Store Department employes moving stores from the old location to the new.

Carrier correctly categorized the MW Scope Rule as general in nature. But, in a Letter of Agreement, between the parties herein, dated September 12, 1962, it is stated

        Employes included within the scope of the agreement effective December 1, 1962 between the North the Track Subdepartment of the Maintenance of Way Department in connection with the construction and maintenance or repairs of, and in connection with the dismantling of tracks, structures or facilities located on the the operation of the Railway Company in the performance of common carrier service. (Emphasis supplied.)


We also have before us our sustaining Award No. 3277, issued August 2, 1946, involving the parties herein, in which a similar issue at Brainerd was adjudicated. In the Opinion o
        Whether the work belonged to Store or B&B employes is not determinable solely from its temporary or permanent character. Clearly, there is bound to be tem in and around the Stores Department of such magnitude that it belongs solely to B&B employes. On the other hand there is bound to be permanent B&B work in the Stores Department in such small amounts that it can well be treated as incidental to the work of employes in the Stores Department. While there is much that can be said on both sidesof the question, we are of the opinion that the excavating for and the laying of sleepers and sills for a temporary runway 7 feet wide and 140 feet long is work within the scope of the Agreement of the Maintenance of Way employes. While we think the temporary bracing or planking of runways and platforms to meet the necessities of the occasion in handling store materials,

                      Award Number 20380 Page 3

                      Docket Number MW-19630


              or even the making-of minor permanent repairs, are incidental to the work of Store employes and may properly be performed by them, we do not think it can be said that work of the magnitude here described can be incidental in the Stores Department. There is evidence of a small amount of sawing and spiking being done. While we do not deem it sufficient to provide a proper basis for d group the work belonged in the present case, it does tend to support the position taken by the B&B employes. The claim will be allowed for the number of hours shown by the joint check to have been worked on the runway here involved.


        Predicated on Award No. 3277 and the Letter of Agreement dated September 12, 1962, we find that the work of constructing the rack structure at Brainerd in the peri Claim.


        As to paragraph 2 of the Claim, neither MW nor carrier proved by substantial evidence of probative value the actual work time employed in the construction of the rack at Brainerd. MW avers it was 296 hours which it seeks to support only by a self serving declaration that the amount of time in actual construction of the work was observed by B&B employees -nothing more. Carrier say "estimates" 60 hours. Consequently, we are compelled to sustain paragraph (2) of the Claim only to the extent of 60 hours instead of the 296 hours alleged in said paragraph by MW.


        During the course of the proceedings the Board, by certified mail served a Third Party NOTICE on the Brotherhood of Railway and Airline Clerks (BRAG) in the manner required by Section 3, First (j) of the Railway Labor Act. BRAC did not appear.


                FINDINGS: The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds and holds:


              That the parties waived oral hearing;


        That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;


        That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and


    i


r
                Award Number 20380 Page 4

                Docket Number MW-19630


        That Carrier violated the Agreement.


                    A W A R D


        Paragraph (1) of the Claim is sustained.


Paragraph (2) of the Claim is sustained to the extent setforth in Opinion, supra.

                        NATIONAL RAILROAD ADJUSTMENT BOARD

                        By Order of Third Division


ATTEST:
        Executive Secretary


Dated at Chicago, Illinois, this 6th day of September 1974.