(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE: (Burlington Northern Inc.

STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:

(1) The Carrier violated the Agreement when it assigned or otherwise permitted other than B& erection work (steel tower) at Portland, Oregon from August 2 through August 13, 1971 (System File 374F/MW-84(s)-3, 9-11-71).

(2) The Carrier violated the "NOTE to Rule 55" when, without advance notice to or agreement with the aforesaid work as indicated in (1) above.

(3) B&B Foreman L. Fricke, Asst. Foreman M. Middleton, Carpenters H. Tucker, H. Katzberg, H. Dietrich, D. Paul, J. Dolson and S. Glenzer each be allowed seventy (70) hours' pay at their respective straight time rates.

(4) Machine Operator D. Legore be allowed sixteen (16) hours` pay at his straight time rate.

OPINION OF BOARD: In August 1971, Carrier commenced construction of a steel
microwave antenna tower at Portland, Oregon on the prop
erty of the former Spokane, Portland and Seattle Railway Company (SP&S). The
tower, 26 feet wide at its base and 120 feet high, was assembled into sections
on the ground and the assembled sections hoisted into place by a crane. Car
rier utilized employes from the Communication Department to perform the assembly
and an outside contractor for the crane operation.

The record indicates that the former SP&S Communication Department employes were, at the time of the tower assembly, represented by the Brotherhood of Railroad, Airlin 1973 these employes have been represented by the International Brotherhood of Electrical Workers (IBEW) and covered by the schedule Agreement between Carrier and that Organizatio
By letter dated August 19, 1971, Petitioner filed the instant claim on behalf of the named claimants. Petitioner relies primarily upon its classification of Work Rule 5 Rule 69(c) also has been cited by Petitioner. The pertinent provisions of the Agreement read as follows:



"RULE 55

"I. Steel Bridge and Building Mechanic.

An employe assigned to the setting of columns, beams, girders, trusses, or in the general structural erection, replacement, maintaining or dismantling of steel in bridges, buildings and other structures and in the performance of related bridge and building iron work, such as riveting and rivet heating, shall be classified as a steel bridge and building mechanic. NOTE: On former SP&S and NP, B&B carpenters performed this type of work a Rule 44."

"NOTE to Rule 55: The following is agreed to with respect to the contracting of construction, maintenance or repair work, or dismantling work customarily performed by employes in the Maintenance of Way and Structures Department:

"Employes included within the scope of this Agreement-in the Maintenance of Way and Structures Department, including employes in former GN and SP&S Roadway E and welding employes-perform work in connection with the construction and maintenance or repairs of the dismantling of tracks, structures or facilities located on the right of way and used in the operation of the Company in the performance of common carrier service, and work performed by employes of named Repair Shops.

"By agreement between the Company and the General Chairman, work as described in the preceding paragraph which is customarily performed by employes described herein, may be let to contractors and be performed by contractors' forces. However, such work may only be contracted provided that special skills not possessed by the Company's employes, special equipment not owned by the Company, or special material available on through supplier, are required; or when work is such that the Company is not adequately equipped to handle the work, or when emergency time requirements exist which present undertakings not contemplated by the Agreement and beyond the capacity of the C,:mpany's forces. In the event the Com work because of one of the criteria described herein, it shall notify the General Chairman of the Organization in writing as far in advance of the date of the contracting transaction as is pracitcable and in any event not less th thereto, except in 'emergency time requirements' cases. If the











Petitioner maintains that the express language of Rule 55(1) specifically grants to B&B employes the general structural erection of steel in structures, including the microwave tower here in issue. Accordingly, Petitioner argaes that Carrier violated said rule by assigning the work to employes not covered by its Agreement, i.e. the Communication Department employes. Additionally, Petitioner contends that contracting out of the crane work without notification and conference with a violation of the Note to Rule 55.

Carrier has denied the claim in its entirety, primarily on the ground that no clear reservation of the work in question is found in Petitioner's Agreement. On this premise, Carrier asserts that Petitioner has failed to demonstrate exclusive rese practice or tradition, and, accordingly, urges that the claim must fail. In this latter connection, Carrier points out that custom and practice relegates the work to FBEW-represented Communication Department employes rather than to Petitioner. Without prejudice to its substantive position, on the merits, Carrier insisted throughou performed on the tower on dates of August 2, 3, 4, 5 and 6, 1971. Finally,

















i



As to the question of damages, Carrier asserts that the Claimants were employed full time when the violation occurred. This Board has held in numerous recent awards that notwithstanding "full employment" or the lack of a specific rule granting monetary relief, pro rata damages may be awarded upon the proven loss of work and earnings opportunity through Carrier misassignment of Agree 19552, et al. In our judgment, there was unquestionably lost work opportunity to claimants in the de subject to the Maintenance of Way Agreement to perform work reserved to them by the Agreement in August 1971.

As noted supra, there was some ambiguity on the record concerning the actual number of days worked by the Communication Department employes in the erection of the tower. Petitioner asserts it was August 2, 3, 4, 5, 6, 9, 10, 11, 12 and 13, 1971. Carrier has maintained throughout that the Communication Department crew worked on the project August 9, 10, 11, 12, 13 and 25, 1971. Both parties concur that the crane was operated on August 10 and 11, 1971.

We do not find it necessary to decide the number of days and hours actually worked on the erection of the tower. The make whole theory will be satisfied by Carrier paying to each Claimant in Claim (3) his straight time rate for the hours actually worked in erection by the Communication Depart ment employes, as recorded in Carrier's records kept in the ordinary course of business; but in no case less than the 48 hours as admitted by Carrier on the record herein. See Awards 14004, 20042. As to Claim (4) there is no such dispute and it is sustained accordingly.

We reiterate that the decision herein is based strictly upon the Agreement, facts and circumstances applicable upon the former SP&S property in August 1971 and cannot be deemed dispositive of questions regarding this type of work on the merged property in futuro. Such claims will turn on their merits if and when they arise.





That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and







        Claim (1) is sustained.


        Claim (2) is sustained.


        Claim (3) is sustained to the extent indicated in the Opinion.


        Claim (4) is sustained.


                        NATIONAL RAILROAD ADJUSTMENT BOARD

                        By Order of Third Division


ATTEST:
        Executive Secretary


Dated at Chicago, Illinois, this 27th day of September 1974.