(Brotherhood of Railroad Signalmen PARTIES TO DISPUTE:



STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood of
Railroad Signalmen on the Chesapeake and Ohio Railway Company (Chesapeake District) that:

(a) The Carrier violated and continues to violate the current Signalmen's Agreement, particularly Scope Rule 1 and Rule 34, on or about December 1, 1971, when it allowed or otherwise assigned the maintenance and future repairs toward the improved signal facilities located at Gast Street, Cincinnati, Ohio to persons not covered by the Agreement we have with this Carrier. As a result of such action we now ask;


ID-2271444, at his applicable pro rata rate of pay, and for a comparable
amount of time that other than C&0 signal employes perform the work cited
in part (a) of this claim. Furthermore;

(c) Due to this being a continuing violation, we further ask that said claim continue until such time as Carrier takes the necessary corrective action to return said work to its signal employes. LCarrier's File: 1-SG-304/

OPINION OF BOARD: This dispute is the companion to the matter dealt
with in Award 20181. Both disputes involve the interlocking plant at Gast Street on Carrier's proper The history, in summary, is that Carrier, by Agreement with the CNO & TP and C.U.T. of November 1933 (which superseded agreements going back to 1902) was given the responsibility to construct and maintain certain signal facilities at the crossing of CNO & TP tracks with its own tracks at Gest Street. At about 1929 an interlocking facility was constructed at this location and it was maintained by Carrier's signal forces until 1971. In 1971 Carrier, the B & 0, CNO & TP and C.U.T. entered into a new agreement which provided among other things, for the ownership, construction, and maintenance of a new interlocking facility including Gest Street. This agreement provided that the work of constructing and maintaining the new facility would be performed by the B & 0.

The Scope Rule of the applicable Agreement covers employes engaged in the maintenance, repair and construction of interlocking plants, in addition to other work. In Award 20181 we held that Carrier erred in ceding the work of improving the Gast Street facility to employes of another



Carrier: the B & 0. In this dispute we reaffirm the reasoning of the companion Award. To be consistent, we cannot hold that Carrier did not have the right to rebuild the interlocking facility using employes of another Carrier but under the same agreement does have the right to contract out the maintenance of find that Carrier may not have B&0 employees performing maintenance work at the Gest Street facility which work properly belongs to its own Signal forces.

As we said in the earlier Award, we note that the B & 0 and this Carrier have the same overall management and this dispute may well have been resolved on the property had there been adequate communication.

We repeat herein that which was stated in the companion dispute,
in that this Award is not intended to impair the understanding that
the B & 0 signal employes have the overall responsibility for maintenance
of the interlocking facility; the sole exception is that any maintenance
work involving the new facilities replacing the tilting target signals at
Gest Street properly accrues to signal forces of this Carrier.





That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and








                        By Order of Third Division


        ATTEST: Executive Secretary


Dated at Chicago, Illinois, this 8th day of November 1974.
                                    Serial No. 282


              NATIONAL RAILROAD ADJUSTMENT BOARD


                    THIRD DIVISION


            INTERPRETATION N0. 1 TO AWARD N0. 20511


                  DOCKET N0 . SG-20208


NAME OF ORGANIZATION: Brotherhood of Railroad Signalmen

NAME OF CARRIER: The Chesapeake and Ohio Railway Company
(Chesapeake District)

Upon application of the representatives of the Employes involved in the above Award, that this Division interpret the same in light of the dispute between the parties as to the meaning and application, as provided for in Section 3, First (m) of the Railway Labor Act, as approved June 21, 1934, the following interpretation is made:

After careful review of the petition of the Organization for an interpretation of Awards 20181 and 20511, and Carrier's response thereto, we find that the Organization's understanding of the intent of the two Awards is erroneous.

We indicated in both of the Awards a careful restriction of the work in dispute to that which related only to the replacement and subsequent maintenance ". . . invo other work in the overall project accruing to Claimants. As we examine the record herein, it seems that the work has been adequately defined in Carrier's letter dated April 3, 1975 as that involving eight signals which replaced the tilting target signals at Gest Street together with certain specified appurtenances. It was not our intention to include within the remedy any other work on the interlocking facility, and certainly not "all signals and related equipment between C & 0 Mile Post 0 and Mile Post 8.2", or work on C 6 0 No. C-1 and C-2 tracks between Gest Street and C 6 0 Mile Post 0.

Referee Irwin M. Lieberman, who sat with the Division, as a neutral member when Award No. 20511 was adopted, also participated with the Division in making this interpretation.

                        NATIONAL RAILROAD ADJUSTMENT BOARD

                          By Order of Third Division

            a

ATTEST:
        Executive Secretary


Dated at Chicago, Illinois, this 13th day of February 19'/6.