NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number SG-20335
Irwin M. Lieberman, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Illinois Central Gulf Railroad- Former
( Gulf, Mobile and Ohio Railroad
STATEMENT
OF
CLAIM: Claim of the General Committee of the Brotherhood
of Railroad Signalmen on the Gulf, Mobile and
Ohio Railroad Company that:
(a) Carrier has violated and continues to violate the Signalmen's Agreement, particularly the Scope,
otherwise permitted Commonwealth Edison Company or persons not covered
thereby to install underground cable for signal circuit use between
Lambert and Summit, Illinois--a distance of approximately eight (8)
miles.
(b) Carrier should pay to the assignees of the positions
advertised in Northern Region Bulletin No. V-494 additional time equal
to the number of man-hours of work performed by persons not covered by
the Signalmen's Agreement on the complained-of project, on a prorated
basis at their respective overtime rates.
(c) Carrier should, in event the claim is sustained, check
its records jointly and in cooperation with Representatives of this
Brotherhood to determine the number of man-hours worked by or paid
to Commonwealth Edison Company employes or persons not covered by the
Signalmen's Agreement, in aiding to determine the amount of compensation due Claimant's. LCarrier's
OPINION
OF
BOARD: In 1971 The Commouwealth Edison Company, a public
service utility company, in expanding its service
constructed a new high voltage transmission line between certain
points in Illinois. In this respect the power company desired to
erect a segment of the high voltage line on eight miles of Carrier's
right of way, parallel to its tracks, between Summit and Lambert, Illi
nois. It was recognized that the new high voltage line would seriously
interfere with Carrier's adjacent pole line signal circuits. Carrier
agreed to the power company high voltage line on the condition that
Commonwealth replace the pole line with inductively shielded cable
buried along the right of way. Subsequently, the underground cable
Award Number 20529 Page 2
Docket Number SG-20335
was installed to Carrier's specifications by Commonwealth Edison and
its contractor at Commonwealth's cost; all signal connections were
made by signal department employes covered by the Agreement herein.
It is noted that the old signal circuits were placed on the pole line
of Western Union Company in this area by virtue of an agreement entered
into in 1909.
The Organization contends that Carrier violated the Scope
Rule of the Agreement when it contracted or otherwise permitted persons
not covered by the Agreement to install the underground cable replacing the existing pole line circu
signal employes have historically and traditionally installed, maintained and repaired the entire We
in question is either owned by Carrier or Carrier has complete control
of its maintenance and repair; the new cable was installed for the
benefit of Carrier and is not owned by Commonwealth Edison as alleged
by Carrier; Claimants were deprived of work by virtue of the employment
of outside forces.
Carrier, in denying the Claims made by Petitioner asserts
that this is the only underground cable installation on its property
and hence there is no "history and tradition" with respect to this
work: there is no evidence or rule support for the proposition that
the work in question is reserved to its signal employes. Carrier also
states that the new cable is owned by the Utility Company, but presented no evidence in support of t
it did not contract out any work but gave permission for the undertaking to the Commonwealth Edison
Company - not the Carrier. Carrier also contends that Claimants were
fully employed during the period of the claim and suffered no loss in
any event.
It is well established by this Board that work which is not
for the benefit of the Carrier, and not within its control,
may be contracted out without violation of the Scope Rule (see for example Awards 14888, 15906, 1936
the Award of Public Law Board No. 387 involving the Long Island Railroad in support of its position.
the installation ofa new cable was started by employes of Carrier and
completed by employes of the Utility company; furthermore that Board
found this to be merely a "technical" violation of the scope rule and
awarded no monetary payments to claimants. There have been three
awards covering virtually identical circumstances as those herein:
Awards No. 2 of Public Law Board 747 and 20156 and 20280. In the
three Awards indicated, all with this Organization and other Carriers,
Award Number 20529 Page 3
Docket Number SG-20335
it was held that the work was not for the benefit of Carrier, not
at its expense, not under its direction or control and therefore
did not violate the provisions of the respective scope rules.
The reasoning in those Awards is not in palpable error and we shall
follow and concur in those opinions.
FINDINGS: The Third Division of the Adjustment Board, upon the
whole record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier. and the Employes involved in this dispute are respectively Carrier and Employe
the Railway Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; an
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
00.0
,d
qa'a"!~.
Executive Secretary
Dated at Chicago, Illinois, this 22nd day of November 1974.