(Brotherhood of Railroad Signalmen PARTIES TO DISPUTE: (Illinois Central Gulf Railroad- Former ( Gulf, Mobile and Ohio Railroad

STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood
of Railroad Signalmen on the Gulf, Mobile and
Ohio Railroad Company that:

(a) Carrier has violated and continues to violate the Signalmen's Agreement, particularly the Scope, otherwise permitted Commonwealth Edison Company or persons not covered thereby to install underground cable for signal circuit use between Lambert and Summit, Illinois--a distance of approximately eight (8) miles.

(b) Carrier should pay to the assignees of the positions advertised in Northern Region Bulletin No. V-494 additional time equal to the number of man-hours of work performed by persons not covered by the Signalmen's Agreement on the complained-of project, on a prorated basis at their respective overtime rates.

(c) Carrier should, in event the claim is sustained, check its records jointly and in cooperation with Representatives of this Brotherhood to determine the number of man-hours worked by or paid to Commonwealth Edison Company employes or persons not covered by the Signalmen's Agreement, in aiding to determine the amount of compensation due Claimant's. LCarrier's
OPINION OF BOARD: In 1971 The Commouwealth Edison Company, a public
service utility company, in expanding its service
constructed a new high voltage transmission line between certain
points in Illinois. In this respect the power company desired to
erect a segment of the high voltage line on eight miles of Carrier's
right of way, parallel to its tracks, between Summit and Lambert, Illi
nois. It was recognized that the new high voltage line would seriously
interfere with Carrier's adjacent pole line signal circuits. Carrier
agreed to the power company high voltage line on the condition that
Commonwealth replace the pole line with inductively shielded cable
buried along the right of way. Subsequently, the underground cable



was installed to Carrier's specifications by Commonwealth Edison and its contractor at Commonwealth's cost; all signal connections were made by signal department employes covered by the Agreement herein. It is noted that the old signal circuits were placed on the pole line of Western Union Company in this area by virtue of an agreement entered into in 1909.

The Organization contends that Carrier violated the Scope Rule of the Agreement when it contracted or otherwise permitted persons not covered by the Agreement to install the underground cable replacing the existing pole line circu signal employes have historically and traditionally installed, maintained and repaired the entire We in question is either owned by Carrier or Carrier has complete control of its maintenance and repair; the new cable was installed for the benefit of Carrier and is not owned by Commonwealth Edison as alleged by Carrier; Claimants were deprived of work by virtue of the employment of outside forces.

Carrier, in denying the Claims made by Petitioner asserts that this is the only underground cable installation on its property and hence there is no "history and tradition" with respect to this work: there is no evidence or rule support for the proposition that the work in question is reserved to its signal employes. Carrier also states that the new cable is owned by the Utility Company, but presented no evidence in support of t it did not contract out any work but gave permission for the undertaking to the Commonwealth Edison Company - not the Carrier. Carrier also contends that Claimants were fully employed during the period of the claim and suffered no loss in any event.

It is well established by this Board that work which is not for the benefit of the Carrier, and not within its control, may be contracted out without violation of the Scope Rule (see for example Awards 14888, 15906, 1936 the Award of Public Law Board No. 387 involving the Long Island Railroad in support of its position. the installation ofa new cable was started by employes of Carrier and completed by employes of the Utility company; furthermore that Board found this to be merely a "technical" violation of the scope rule and awarded no monetary payments to claimants. There have been three awards covering virtually identical circumstances as those herein: Awards No. 2 of Public Law Board 747 and 20156 and 20280. In the three Awards indicated, all with this Organization and other Carriers,
                  Award Number 20529 Page 3

                  Docket Number SG-20335


it was held that the work was not for the benefit of Carrier, not at its expense, not under its direction or control and therefore did not violate the provisions of the respective scope rules. The reasoning in those Awards is not in palpable error and we shall follow and concur in those opinions.

        FINDINGS: The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds and holds:


        That the parties waived oral hearing;


That the Carrier. and the Employes involved in this dispute are respectively Carrier and Employe the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; an
        That the Agreement was not violated.


                  A W A R D


        Claim denied.


                        NATIONAL RAILROAD ADJUSTMENT BOARD

                        By Order of Third Division

ATTEST: 00.0 ,d qa'a"!~.
        Executive Secretary


Dated at Chicago, Illinois, this 22nd day of November 1974.