NATIONAL RAILROAD ADJUSTMENT BOAR
THIRD DIVISION Docket Number SG-20219
Joseph A. Sickles, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Missouri Pacific Railroad Company
STATEMENT OF CLAIM: Claims of the General Committee of the Brotherhood of
Railroad Signalmen on the Missouri Pacific Railroad
Company (Gulf District):
Claim No. 1
On behalf of the following named members of Signal Gang 291, for
an additional payment of three(3) hours each at time and one-half their respective straight time hou
denied them when the Carrier contracted with an outside party to construct
and install a Meter Loop at FM 2004, Lake Jackson, Texas, on October 20,
1971, in violation of the Scope of the Signalmen's Agreement.
J. G. Freeman Foreman $922.70 per month
J. H. Love Assistant 3.56 per hour
J. T. Harrell Assistant 3.53 per hour
J. L. West Assistant 3.49 per hour
LCarrier's File: B 315-46 General Chairman's File: M206%
Claim No. 2
On behalf of the following named members of Signal Gang 291, for
an additional payment of three (3) hours' straight time each, account work
of their assignments was denied them when the Carrier contracted with an
outside party to construct and install a Meter Loop at Highway 1495, Freeport, Texas, on October 4,
J. G. Freeman Foreman $922.70 per month
J. H. Love Assistant 3.56 per hour
J. T. Harrell Assistant 3.53 per hour
/Carrier's File: B 315-47 General Chairman's File:M206%
Award Number 20532 Page 2
Docket Number SG-20219
OPINION OF BOARD: On two occasions, Carrier utilized its electricians
(rather than signal employees) to install meter loops,
which were to be utilized in connection with highway protection devices.
Claimants urge a violation of its Scope Rule which provides, in
material part:
"This Agreement governs ....working conditions ....of
employes in the Signal Department ....performing signal
work in the construction, installation ....of highway
crossing protection devices and their appurtenances...
and all other work generally recognized as signal work..."
In reply to the initial claim, Carrier advised:
"The meter loop ....was installed by the Railroad Company's Electrical Workers. The work consist
all on a separate creosoted pole for electrical service furnished by a utility power company. The en
cable from the meter loop creosoted pole to the signal
instrument case to serve the flashing light signals was
made by members of Signal gang 291."
During the handling of the matter (on the property) Claimant
failed to dispute the above cited statement. Accordingly, the Board must
accept same as established for purposes of this record.
On the property, the Organization contended that its employees had
installed meter loops. Carrier concedes that meter loops have been installed
by signal employees under certain circumstances, but insists that meter loops
have also been installed by Carrier's electricians and by outside contractors.
Thus, Carrier urges that Claimant has failed to demonstrate an exclusivity
of assignments.
The International Brotherhood of Electrical Workers participated
as a Third Party and filed a Submission. The IBEW states that it has performed
meter loop installation on the property, and urges that the Carrier's assignment in this dispute was
The Organization conceded that electricians may have constructed
and installed meter loops for signal installations. But, such work, if performed, was not known to t
Award Number 20532 Page 3
Docket Number SG-20219
The Claimants asserts that the Scope Rule refers specifically
to installation of highway crossing protection devices and their appurtenances, and because the mete
past practice is not controlling. See Award 12697 (Hamilton). In the alternative, the Organization n
other work generally recognized as signal work
...."
Claimant relies on Awards 19525 and 19526 (Brent) dealing with
installation of meter loops. But in those cases, the Board stressed that
there had been a unilateral change of management policy in regard to assignment of the disput
Carrier cites Awards 19040 (Woody) and 19838 (Blackwell). Award
19040 considered the setting of a pole upon which a meter loop was attached.
The Award noted that:
"While it is correct, as Signalmen argue, that
the purpose of the pole and meter loop together
was to service a crossing signal within their
work jurisdiction, the pole appurtained to the
crossing signal only through the meter loop,
and the meter loop appears to be conceded to be
a work jurisdiction not exclusively reserved for
Signalmen."
Award 19838 considered meter loops installed by electricians and
a signal Scope Rule which covered highway crossings and their appurtenances.
The Award denied the claim based upon Public Law Board Awards, on the property,
which had rejected assertions similar to those raised here.
In the final analysis, this dispute must be determined by the record
established on the property. With the exception of the continuing dispute
concerning the historical performance of the work of installing meter loops,
we note that the record, established on the property, fails to aid the Board
substantially in a resolution of the dispute.
Claimant's position that past practice does not control a specific
Scope Rule is, of course, well taken, but the Board requires proof that the
Carrier's action violates the specific provision. Prior Awards, cited above,
have failed to hold that installation of meter loops of the nature described
herein, are, of necessity, directly related to highway crossing protection.
We do not preclude the Organization from making such a showing in a future
case, but we do not find such a demonstration under this record. Further, we
are unable to find that the Organization has established exclusivity of assignment. The burden of so
(Cull).
i
Award Number 20532 Page 4
Docket Number SG-20219
We fully recognize the plausibility of the Organization's arguments that the disputed work may b
Rule, but we find a failure of proof under this record. We will dismiss
the claim for said failure of proof.
FINDINGS: The Third Division
of
the Adjustment Board, upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the claim be dismissed.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 22nd day of November 1974.