NATIONAL RAILROAD ADJUSTMENT HOARD
THIRD DIVISION Docket Number SG-20276
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(J. F. Aasb and R. C. Haldeman, Trustees of the
( Property of Lehigh Valley Railroad Company,
( Debtor
STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood
of Railroad Signalmen on the Lehigh Valley Railroad
Company that:
(a) Carrier improperly abolished signal employes' positions,
on or about
July
26, 1971, in violation of the Signalmen's
Agreement and the February 7, 1965 Agreement.
(b) Carrier should be required to compensate the following
fifteen affected employes for wage loss suffered, and/or
reimburse them for extra expenses because the force
reductions forced them to exercise displacement rights
to obtain another position which required them to entail
extra expenses:
1. W. Kowalow, -Difference in pay between Signal
Signal Foreman Foreman and Signal Maintainer,
August 9 to 25, 1971, inclusive,
for 105 hours straight-time and
22 hours punitive.
2. C. P. Cannon, -Car mileage,
48
miles per day
Signal Maintainer 9¢, certain specified days
August 2 through
18,
1971 (total
of
13
days).
3.
W. R. Wygrola, -Car mileage, 90 miles per day @
signalman
9¢, certain specified days
July 26 through August 25, 1971
(total of 18 days).
4.
D. E. Allardyce, -Car mileage, 100 miles per day @
Signalman 90, for a total of
5
days,
July
26
- 30,
1971, and 175 miles
per day for
8
days, August 16-25,
1971.
Award Number 20542 Page 2
Docket Number SG-20276
5. W. S. Quinn, -Pay at Signalman rate for a
Signalman total of 18 days, August 2
through 25, 1971 (8 hours per
day).
6. D. A. Spigarelli, - Pay at Signalman rate for a total
Signalman of 7 days, August 23 through 31,
1971 (8 hours per day).
7. J. E. Herds, -Pay at Signalman rate for a total
Signalman of 23 days,
July
26 through
August 25, 1971.
8. L. J. Dowd, - Pay at
Signalman
rate for a total
Signalman of 23 days,
July
26 through
August 25, 1971.
9. F. X. Jewell. -Pay at Signal Foreman rate for a
Signal Foreman total of
18
days, July 26 through
August 18, 1971. Car mileage 150
miles per day @ 9¢, for 5 days,
August 19 through 25, 1971.
10. W. F. Bubick, -Pay at Signal Helper rate for a
Signal Helper total of 23 days, July 26 through
August 25, 1971.
11. G. J. Fech, -Pay for 3 hours' riding time daily
Signalman for 23 days. Car mileage 130
miles per day
a
9¢, for a total
of 16 days.
12. A. P. Brown, -Pay at Signalmaa rate for 5 days.
Signalman
13. R. Azzalina, -Pay at Signal Maintainer rate for
Signal Maintainer a total of 22 days, July 27 to
August 26, 1971.
14.
C. T. Heitzman, -Pay for
40
hours Q $0.0737 per hour,
Relay Inspector 10 hours @ $4
.4498
per hour. Car
mileage, 84 miles per day Q
9f,
for
a total of 5 days.
15. H. McPherson, -Pay at Signalman rate for 1 day,
Signalman
July
26, 1971.
Award Number 20542 Page 3
Docket Number SG-20276
_NOTE: This Statement of Claim is identical to one
being submitted concurrently to the Disputes
Committee established under the February 7, 1965
Agreement, Mediation Case A-7128. That tribunal
is being requested to rule on the issues involving.
that Agreement, whereas the remaining issues are
to be adjudicated by this Board.
OPINION OF BOARD: This case presents claimed violations of the controlling
Signalmen's Agreement on the property and of the
February 7, 1965 National Agreement. The February 7, 1965 Agreement
provides for the establishment of a Disputes Committee to resolve disputes
involving its interpretation or application. That Committee, herein
after Special Board of Adjustment No. 605, rendered Award
No.
368 on
October 18, 1973 on the identical claims herein insofar as they relate
to alleged violations of the February 7, 1965 Agreement. In that Award,
the Special Board resolved each of the claims except
No. 10 (W.
F. Bubick)
and No. 12 (A. P. Brown). Claim No. 10 was remanded to the parties for
determination of Bubick's protected status, under the February 7, 1965
Agreement, with continuing jurisdiction in S.B.A. No. 605 for further
resolution as necessary. Claim No. 12 was dismissed by the Special Board
since Brown is concededly a nonprotected employe under the February 7,
1965 Agreement and the jurisdiction of S.B.A. No. 605 is limited to the
interpretation and application of that Agreement and no other Agreements.
In light of all the foregoing, the parties stipulate and we
find that the only claims remaining before this Division for resolution
are Nos. 10 and 12. Moreover, under generally recognized principles of
res udicata the determination of S. B. A. No. 605 will be recognized by us
as determinative of those claims insofar as they allege violations of the
February 7, 1965 Protective Agreement. Accordingly, our focus on Nos. 10
and 12 is concerned only with the allegations therein of violations of the
controlling Signalmen's Agreement.
The rules that apply to a force reduction of "unprotected"
employes are Section 4 of Article IV of the Signalmen's Agreement, as
amended by the June 5, 1962 National Agreement, and the 16-hour
"emergency layoff provisions" of the August 21, 1954 Agreement. The
net effect of these contractual provisions is to require five (5)
working days written advance notice to such employes, except where
emergency conditions prevail which cause suspension of Carrier's operations and renders the work to
emergency conditions such as flood, snow, storm, hurricane, earthquake,
fire or strike cause such an effect on Carrier's operations and on the
work of the employes, the 5-day notice rule is modified so that no more
than sixteen (16) hours notice need be given.
Award Number 20542 Page 4
Docket Number SG-20276
With the foregoing contractual guidelines established, we turn
to the claims remaining for our consideration. Careful examination of
the record herein shows that Claim No. 10 (W. F. Bubick) alleges improper
abolishment of his position. However, Carrier asserts and Petitioner
does not effectively refute that Bubick's position as Signal Helper was
not abolished; rather he was displaced by a senior employe who had in
turn been displaced from his position. In these circumstances, Bubick
was secondarily affected, if at all, by abolishment and Claim No. 10
must accordingly be denied.
Claim No. 12 (A. P. Brawn) is on a different footing. Carrier
does not deny that Brown was given less than 5 working days advance notice
of the abolishment of his position on
July
24, 1971. Carrier asserts
however that the "16 hour rule" applies to Brown's case because of a
strike against Norfolk & Western Railway on
July
24, 1971 by the United
Transportation Union and because of a threatened strike of Bethlehem
Steel Company by the United Steelworkers of America, which did in fact
materialize on August 1, 1971. Carrier argues that the strike and
threatened strike "affected the business of the Lehigh Valley Railroad",
and therefore there was no violation when it gave Brown 16 hours notice
rather than 5 working days.
This record contains no evidence that as of July 23, 1971 the
strikes in question produced a suspension in Carrier's operations in
whole or in part; neither did they render Claimant Brown's work
non
existent nor impossible of performance. In other words no such "emergency"
existed as is contemplated by the "emergency layoff provisions" of the
August 21, 1954 Agreement. In these circumstances 5 working days notice
should have been given pursuant to Section 4 of Article IV of the
Signalmen's Agreement and Claimant Brown who received less notice is
entitled to compensation. Accordingly, Carrier shall compensate Claimant
A. P. Brown for 5 days beginning July 26, 1971.
FINDINGS: The Third Division of the Adjustment Board upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute
are respectively Carrier and Employee within the meaning of the Railway
Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
That the Agreement was violated to the extent indicated in the
Opinion.
J
Award Number 20542
Docket Number SG-20276
A W A R D
Part (a) is
Part (b) 1.
2.
3.
4.
5.
6.
7.
S.
9.
10.
11.
12.
13.
14.
15.
sustained to the
Claim Dismissed
Claim Dismissed
Claim Dismissed
Claim Dismissed
Claim Dismissed
Claim Dismissed
Claim Dismissed
Claim Dismissed
Claim Dismissed
Claim Denied
Claim Dismissed
Claim Sustained
Claim Dismissed
Claim Dismissed
Claim Dismissed
ATTEST:
114W.,
&a
/wLrme
Executive Secretary
Dated at Chicago, Illinois, this 13th
Page 5
extent indicated in the opinion.
(W. Kowalow)
(C. P. Cannon)
(W. R. Wygrola)
(D. E. Allardyce)
(W. S. Quinn)
(D. N. Spigarelli)
(J. E. Herda)
(L. J. Dowd)
(F. X. Jewell)
(W. F. Hubick)
(G. J. Fech)
(A. P. Brown)
(R. Azzalina)
(C. T. Heitzman)
(H. McPherson)
NATIONAL RAILROAD ADJUSTMENT HOARD
By Order of Third Division
day of December 1974.