(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE: (The Baltimore and Ohio Railroad Company

STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:

(1) The Agreement was violated when Class A Machine Operator Randy Powell, Jr. and Class B. Machine Operator C. R. Corbin were allowed only four hours' pay on December 8 and 15, 1972 and on January 19 and February 1, 1973.

(2) The Agreement was violated when Class A. Machine Operator R. T. Sparks and Class B. Machine Operator Hubert Morrison were allowed only four hours of pay on December 8 and 15, 1972 and on January 19, 1973.

(3) The Agreement was violated when Class B Operator Kenneth Fetters was allowed only four hours of pay on December 15, 1972 and on January 19 and February 1, 1973.

(4) Each of the claimants identified in Parts (1), (2), and (3) above now be allowed twelve (12) hours' pay at their respective straighttime rates. (Carrier's F
OPINION OF BOARD: On the dates in question, Claimants failed to complete
eight (8) hours of work. They (Machine operators)
assert that they were precluded from completing their tours due to incle
ment weather. On the other hand, Carrier alleges that there was work avail
able for Claimants on the days in question, but that they "requested" to be
returned to Camp Headquarters.





The Board feels that this dispute must be resolved on the basis of burden of proof as developed on the property.

The initial claim contended that the Agreement fails to provide for suspension of time for inclement weather. In reply, Carrier stated that:





Although Claimants responded to the above-cited letter, and discussed the applicability of Rule recitation.

Again, in the final denial letter, Carrier repeated that Claimants requested to be returned to C work to be performed.

Claimants never replied to the final denial letter until the matter was submitted to this Board.

This Board has consistently determined that it may only consider matters which have been raised on the property. Moreover, the party asserting the violation must pro full days of work, it was incumbent upon Claimant a to submit probative evidence to the contrary. Se
The Organization, in its Ex Parts and Rebuttal Submissions, presents argument which contains a c identity of the work which was allegedly refused, inasmuch as all employees appeared to be employed on the same project, et c. However, these matters should have been submitted on the property, rather than directly to this Board.







That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and










                        By Order of Third Division


ATTEST:
        Executive Secretary


Dated at Chicago, Illinois, this 21st day of February 1975.

,av