(Brotherhood of Railroad Signalmen PARTIES TO DISPUTE:


STATE~ZNT OF CLAIM: Claims of the General Committee of the Brotherhood of
Railroad Signalmen on the Baltimore and Ohio Railroad Company that:



Claim (a) The Signalmen's Agreement was violated by the welding unit in charge of Mr. Clyde Kennell, when the unit recently thermo welded approximately 40 joints on the recently installed welded rail between.Mile Post 38 pole 20 to Mile Post 45. The welding unit removed all cadweld signal bonds installed by signal forces. The violation occurred between August 14, 1972, and August 29, 1972, a total of twelve days.

(b) The Carrier instructed Signal Maintainer Harrison Mickey not to follow the welding unit and remove the bonds from the joints to be welded.

(c) Harrison Mickey now be allowed one hour at time and one half rate of pay per day for twelve days. ZCarrier's file: 2-SG-59/



Claim (a) The Signalmen's Agreement was violated when Mr. W. R. Flinn, Signal Supervisor, instructed Signal Maintainer E. K. Dunn, Jr., on August 15, 1972, not to follow the welding unit in charge of Mr. Clyde Kennell, when the unit thermo 1972 and September 15, 1972 on the recently laid welded rail between Mile Post 16-03 and Mile Post 21-30. The welding.unit removed the cadweld signal bonds installed by the signal forces.

(b) The Carrier violated the Signalmen's Agreement by having the welding unit remove the signal bonds.

(c) Signal Maintainer E. K. Dunn, Jr. now be allowed one hour per day at one and one half rate of pay for a period of twelve days. farrier's file: 2-SG-60/

I.



OPINION OF BOARD: The Claims herein arose as a result of the installa
tion of continuous welded rail on Carrier's Wheeling
and Pittsburgh Subdivision during August 1972. The issue is whether the
Scope Rule of the Agreement was violated when employes of the Maintenance
of Way Department, welders, removed the bond wires from the joints in the
course of making their welds. An identical dispute involving the same
parties was before this Board and resolved by Award 20536. In that Award
we held that the knocking off and scrapping of bonds in the course of in
stalling continuous welded rail was not work covered by the Scope Rule of
the Signalmen's Agreement since that work did not include repairing or re
placing of the bond wire. That Award is controlling in this dispute and
must be followed.





That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and








                        By Order of Third Division


ATTEST: I~i
        Executive' Secretary


Dated at Chicago, Illinois, this 9th day of May 1975.

.:I