NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number SG-20408
Robert A. Franden, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:(
(Chicago, Rock Island and Pacific Railroad Company
STATEMENT OF CLAIM:Claim of the General Committee of the Brotherhood of
Railroad Signalmen on the Chicago, Rock Island and
Pacific Railroad Company that:
(a) Carrier violated the Signalmen's Agreement, particularly
the Scope, when, on or about January 10, 1972, Carrier assigned or otherwise permitted to be assigne
repairs of certain signal facilities of the Joint Inerlocking (EJ&E-CRI&P
Crossing), Joliet, Illinois, to EJ&E signal employes.
(b) Carrier should pay to Signal Maintainer C. W. Peet, or the
signal maintainer subsequently assigned to the territory including the
Joint Interlocking, additional time equal to 35 hours per month, plus time
equal to the number of man-hours of emergency work and trouble calls performed by EJ&E signal em
commencing January 10, 1972, and continuing thereafter until proper correction is made. (General Cha
L-130-494)
OPINION OF BOARD: In January of 1972 the Joint Interlocking at Joliet,
Illinois between the Elgin, Joliet and Eastern and the
Chicago, Rock Island and Pacific was converted from a mechanical to an
electrical operation.
The control of the interlocking facility was determined by a
contract between the carriers which was entered into in 1911. Said contract provided that the E.J. a
own block signals whether said signals were used wholly as block signals
or performed the functions of both block signals and interlocking signals.
Under the option available to the Rock Island in the agreement,
it chose to maintain the U-5 switch circuit controllers at the point in
question. These controllers were separate devices from the derails with
which they worked in conjunction at this point.
When the interlocking facility was electrified, power switch
machines were installed which replaced both the mechanical derail mechanism and the U-5 switch circu
It is the contention of the organization that the function of
the U-5 switch circuit controllers is now being performed by switch circuit
I
Award Number 20727 Page 2
Docket Number SG-20408
controllers housed along with the electrical derail mechanism but as
an independent apparatus working in conjunction with the new derail
mechanism. It is the right to the maintenance work on the new switch
circuit mechanism which has replaced the U-5 switch circuit controllers
which is the subject of this dispute.
The Carrier contends that the power switch machines were installed primarily to replace the mech
derails and the the machines' circuits are an integral part of the interlocking system which the E.J
E.
is contractually required to maintain.
In that the Rock Island had elected to maintain the signals
in question that work properly belonged to its employes so long as it
existed independent of the interlocking system which the
E.
J. & E
.
was contractually required to maintain.
The record supports the Carrier's contention that the switch
circuit contacts are an integral part of the switch machine. The Carrier was not only within its rig
with the E. J. & E. to permit the
E.
J. & E. Signalmen to maintain the
switch machine a part of the interlocking plant.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST: w
Executive Secretary
Dated at Chicago, Illinois, this 30th day of Play 1975.
i
i
Dissent to Award 20727, Docket SG-20408
In order to set the stage for its denial, the Majority erroneously
holds that:
"In that the Rock Island had elected to maintain
the signals in question that work properly belonged
to its employes so long as it existed independent
of the interlocking system which the E. J. & E. was
contractually required to maintain."
From the record in this dispute it seems to be quite clear that the
involved signals, the circuits of which were controlled by the subject
circuit controller and which the Carrier had elected to maintain with its
own forces, had not, at any time since the installation of the interlocker,
existed independent of the interlocker. Yet, it was the Carrier's option
to perform the maintenance upon them as well as the disputed circuit
controller. Thus, the lack of independent existence is no basis for the
disposition of the dispute.
Award 20727 is in error and I dissent.
) V.