(Brotherhood of Railroad Signalmen PARTIES TO DISPUTE:


STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood of
Railroad Signalmen on the Chicago, Rock Island and Pacific Railroad Company:

Carrier pay to Signal Maintainer R. W. Hafley additional time equal to 5-9/12 hours' overtime for service which he performed on May 4, 1972, in connection with Carrier's scheduled construction and maintenance program. (Carrier's File: L-130-501; General Chairman's File: AV-H-126)

OPINION OF BOARD: In connection with the renovation of a crossing in
East Moline, Illinois Claimant Signal Maintainer worked 5 9/12 hours past his regular quitting time in order to complete the necessary signal work. It is th overtime. The Carrier takes the position that overtime necessary to complete work commenced during regular hours is not compensable under Rule 62.

















The position of the Claimant is that the work performed was ordinary maintenance and construction work as contemplated in the first sentence of the fourth paragraph of the Rule. The Carrier contends that the work falls into the category of work "run into" as contemplated by the second sentence of the fourth paragraph of Rule 62.

The Carrier has cited two Awards dealing with the same parties and the same rule. Both of those Awards (20208 and 20610 which cites 20208 with approval) found that the work in question was not ordinary maintenance and construction work but work run into which was not compensable as overtime.

Award 20208 deals with a situation where the work in question would have been completed during regular hours had the switch machine which was installed operated properly. As a result of it not working properly the work in question had to be performed after regular hours. We believe this case points out an essential element of work "run into". That is, there must be a certain unexpectedness to the necessity of having to have the work performed after regular hours.



In Award 20208 we said "We are mindful that the nature of the fourth paragraph of Rule 62 is such that it could possibly be misused by the Carrier. We are also mindful that, in this case, a lengthy period was required to perform the work "run into" in completing a certain job. For these reasons we have studied the facts closely. We note though, that the Employes did not dispute that the work would have been completed within regular hours if all had gone well. Nor did the Employes contend that the Carrier could have foreseen the malfunctioning of the switch machine, that the Carrier had any knowledge about the machine's defects which would have relieved Claimant of the duty to complete the job, or that the iob could have gone over until the next day." (emphasis supplied)

Ordinary maintenance and construction that was begun during regular hours and then continued aft that the work performed after regular hours was "run into". The wording of
the rule is "This does not apply to work a Maintainer might run into
when completing a certain job worked on " The words "might run into"
suggest a happenstance rather than the performance of work which is part
of regularly scheduled maintenarce or construction. The happenstance may
be either in the nature of the work performed or the time during which it
is performed as was the case in Award 20208. The construction suggested
by the Carrier would permit the Carrier to commence maintenance or construc
tion work toward the end of a shift and work the employes after regular
hours to complete the project without becoming liable for overtime.

In the instant matter there is nothing to suggest that the work in question was not easily forseeable both it its nature and time necessary performance. It was ordinary maintenance or construction work as contemplated by paragraph 4 of Rule to be performed outside of bulletined assigned hours.





That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment BoarJ has jurisdiction over the dispute involved herein; and












ATTEST:
        "Executive ecretary


Dated at Chicago, Illinois, this 18th day of July 1975.

I