NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number IIW-21303
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Norfolk and Western Psilway Company
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The suspension of fifteen (15) days imposed upon Machine
Operator R. L. Procise was without just and sufficient cause, on the basis
of unproven charges and in violation of the Agreement (System File MW-CR74-102).
(2) The charges placed against Machine Operator R. L. Procise
be stricken from his record and he be compensated for all wage loss puffered, all in compliance with
OPINION OF BOARD: This is a discipline case involving 15 days actual
suspension assessed against Machine Operator R. L. Procise on charges of negligent operation of a Tr
question, Claimant was operating the Tie Crane as part of a crew reneVing bridge
ties under the supervision of Mr. A. C. Walker, Jr., Supervisor, B&B. After
completing the work, Walker instructed Procise and his Helper, K. C. Jones,
Jr. to load the Tie Crane onto a flat car using a Bantam Shield Truck Crane.
Claimant inquired of Walker if there was available a double-line snatch
block to make the lift but was told none was avilable at the site. Jones
attached the cable of the Truck Crane to a 4-way chain using an undersized
clevis which was too small to fit over the ring of the chain. The attachment therefore was jerry-rig
the 4-way chain ring and bolting the clevis around the loop in the cable.
This arrangement was observed directly by Supervisor Walker who did not
object to the method of rigging. Jones thereupon attached the chain to the
Tie Crane, gave Procise in the Truck Crane the signal to lift and he did so
lifting the Tie Crane about two feet, but then lowering it again to adjust
the brakes on the Truck Crane. Upon lifting the Tie Crane the second time,
the cable parted and dropped the Tie Crane to the ground thereby damaging it.
Walker, Jones and Procise determined that cable strain due to the method
of rigging was the cause of the accident. Another clevis of the proper
size was then found, the 4-way chain was rigged properly through that clevis
and the lift was made to the flat car without further incident.
Thereafter, by letter dated May 10, 1974, Claimant was suspended
for 15 days without pay by Division Engineer E. H. Wilkinson. Under Rule
32 of the Agreement, the Organization requested an investigation. Following
Award Number 21285 Page 2
Docket Number MW-21303
adjournment the hearing was held on June 6, 1974 with Division Engineer
Wilkinson serving as Hearing Officer. On June 18, 1974 the Hearing Officer
issued his decision as follows:
"Reference previous correspondence, and attaching copy of
investigation held June 6, 1974, concerning the above
subject.
Facts developed in the investigation indicate that Machine
Operator R. L. Procise knew correct procedure for handling
loads of the kind in question but still violated correct
procedure; resulting in extensive damage to Tie Crane NW
10050. 1 can see no reason to change or modify discipline
as has been assessed."
By letter dated June 26, 1974 the instant claim was filed and, failing
resolution on the property has been appealed to this Division.
The position of the Organization herein is twofold to wit: 1)
That Claimant was deprived of fair and impartial handling of thisi~s matbpr
because Division Engineer Wilkinson preferred the charges, held the hearing
and rendered the decision and 2) Claimant was not guilty of negligence because his Supervisor was pr
manner of rigging and lifting, and interposed no objection to the procedure
used. Carrier rejects both these positions on grounds, respectively, that
the Agreement expressly states nothing about conduct of the hearing and that
the negligence. of the Supervisor, if any, is irrelevant to the fact of
Claimant's culpability.
We have reviewed the hearing record carefully and can find no
overt evidence of prejudgment or prejudicial conduct by the hearing officer.
In these. circumstances and in the absence of agreement language on the subject, we cannot find that
per se deprivation of a fair and impartial investigation. Our holding is
not a general endorsement of'such hearing practices, but the Organization
has not carried its burden of proving that the Agreement was violated thereby
in this case.
Turning to the claim of insufficient justification for the 15-day
suspension, we are persuaded that the Organizations position has merit. The
Carrier plainly placed the entire responsibility for the accident upon Claimant's shoulders and eith
fault and bears partial responsibility for the accident. He is not relieved
of all responsibility because of the negligence of others. Accordingly some
Award Number 21285 Page 3
Docket Number MW-21303
discipline was warranted. But a basic tenet of arbitral review in such
cases is that discipline be uniformly and reasonably applied in all of the
circumstances. There is no evidence to suggest that Carrier considered the
mitigating circumstance of Walker's direct order to load the Tie Crane
without a snatch block and the Supervisor's participation in and implicit
approval and authorization of the method of rigging used by Claimant's
helper. In fact, Carrier refused to consider such evidence at all. We
must conclude that a 15-day suspension on these facts is arbitrarily axed
unreasonably harsh. Thus, we shall reduce the discipline imposed to a
suspension of five (5) days without pay. Accordingly, the claim is sustained to the extent that Carr
a five-day suspension and shall compensate him for ten days wage loss
suffered, less outside earnings if any.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the Agreement was violated.
A W A R D
Claim sustained to the extent indicated in the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
49AW,
ea4aQ~
Executive Secretary
Dated at Chicago, Illinois, this 12th day of November 1976.